Permit Application Status

PRBD201906224


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201906224
Building
Finaled
VILLAGE PARK OF BLMGTN LP
Alteration/Repair/Replace
Not Required
Install 315 sq. ft. of R30 ceiling acoustic insulation, hang 345 sq. ft. of 5/8” ceiling drywall, spray 345 sq. ft. of acoustic ceiling texture. Paint 545 sq. ft. of walls and ceilings
06/12/2019
06/13/2019
05/30/2020
12/02/2019

Locations

Permits

Permit Number: PRBD201906224

Building
Finaled
06/13/2019
05/30/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Insulation Inspection Failed 07/22/2019
Ceiling insulation full depth by fiberglass batt at area opened up, for floor rating.
Corrections:


Miscellaneous/Other
Carried Forward
07/22/2019
Work covered with out inspection.

Framing Inspection Failed 7/22/2019 (8:00 - 10:00) 7/22/2019 (AM) 07/22/2019
needs to reschedule - Mark with Restoration. mshulfer 06/27/2019 9:34 Inspection canceled by contractor (second time) NelsonThorpe Sarah 07/05/2019 9:03 AM
Corrections:


Miscellaneous/Other
Comment Only
07/22/2019
Work covered with out inspection.

Building Final Inspection Passed 11/27/2019 (12:30 - 2:30) 11/27/2019 (PM) 11/27/2019
Insulation Inspection Passed 12/02/2019
Corrections:


Miscellaneous/Other
Outstanding
07/22/2019
Work covered with out inspection.