Permit Application Status

PRBD201906228


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201906228
Building
Finaled
VILLAGE PARK OF BLMGTN LP
Alteration/Repair/Replace
Not Required
(Bedroom & Living Room Wall) Install 365 sq. ft. of R30 ceiling acoustic insulation, hang 400 sq. ft. of 5/8” ceiling drywall, spray 400 sq. ft. of acoustic ceiling texture. Paint 600 sq. ft. ceiling and walls.
06/12/2019
06/13/2019
05/25/2020
12/02/2019

Locations

Permits

Permit Number: PRBD201906228

Building
Finaled
06/13/2019
05/25/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 7/22/2019 (8:00 - 10:00) 7/22/2019 (AM) 07/22/2019
needs to reschedule - Mark with Restoration. mshulfer 06/27/2019 9:34 AM Inspection canceled by contractor (second time) NelsonThorpe Sarah 07/05/2019 9:03 AM
Insulation Inspection Passed 07/22/2019
Ceiling insulation full depth by fiberglass batt.
Building Final Inspection Passed 11/27/2019 (12:30 - 2:30) 11/27/2019 (PM) 11/27/2019