Permit Application Status

PRBD201906278


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201906278
Building
Expired
LIFESPACE COMMUNITIES INC
New
Residential, care/assisted living facilities
Storage, low hazard
Construct a new 5-story RL (Residential Building) on the Friendship Village campus.
06/12/2019
10/31/2019
05/03/2022

Locations

Permits

Permit Number: PRBD201906278

Building
Expired
10/31/2019
05/03/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Housewrap Inspection Pending
Insulation Inspection Pending
Framing Inspection Pending
Fire Inspection Final Pending
Progress Inspection Pending 12/23/2020 (2:30 - 3:30)
Progress Inspection Pending 6/22/2021 (12:30 - 2:30)
Progress Inspection Pending 6/25/2021 (8:00 - 10:00)
Progress Inspection Pending 6/28/2021 (2:30 - 3:30)
Progress Inspection Pending 7/16/2021 (10:00 - 12:00)
Footing Inspection Partial Pass 11/19/2019
Corrections:


Miscellaneous/Other
Comment Only
11/19/2019
Strip footings with rebar as per plan along east wall approved.

Progress Inspection Passed 12/4/2019 (8:00 - 10:00) 12/4/2019 (AM) 12/04/2019
Corrections:


Miscellaneous/Other
Comment Only
12/04/2019
Poured foundation wall along east wall as per marked drawings approved.

Progress Inspection Passed 12/16/2019 (8:00 - 10:00) 12/16/2019 (AM) 12/16/2019
Corrections:


Miscellaneous/Other
Comment Only
12/16/2019
Foundation walls at elevator and stairwell on northside approved.

Progress Inspection Passed 12/23/2019 (8:00 - 10:00) 12/23/2019 (AM) 12/23/2019
Corrections:


Miscellaneous/Other
Comment Only
12/23/2019
Pad footings and strip footings and poured walls as per field marked plan approved.

Progress Inspection Passed 1/6/2020 (8:00 - 10:00) 1/6/2020 (AM) 01/06/2020
Corrections:


Miscellaneous/Other
Comment Only
01/06/2020
Progress inspection of strip footings and poured walls as per plan marked in the field.

Progress Inspection Passed w/ Conditions 2/5/2020 (8:00 - 10:00) 2/5/2020 (AM) 02/04/2020
Corrections:


Miscellaneous/Other
Comment Only
02/04/2020
Vertical rebar near column line C - 12 presses tight to forms, no clearance provided. Correct as required and OK to pour when corrected. Inspection of poured wall along south wall from column C - 6 to C -12 OK.

Progress Inspection Passed 2/18/2020 (8:00 - 10:00) 2/18/2020 (AM) 02/18/2020
Corrections:


Miscellaneous/Other
Comment Only
02/18/2020
Progress inspection of poured wall at mid section of north wall approved.

Progress Inspection Passed 2/24/2020 (8:00 - 10:00) 2/24/2020 (AM) 02/24/2020
Corrections:


Miscellaneous/Other
Comment Only
02/24/2020
Progress on poured wall on north side and footings on south side as per field marked drawings approved.

Progress Inspection Passed 2/28/2020 (8:00 - 10:00) 2/28/2020 (AM) 02/28/2020
Corrections:


Miscellaneous/Other
Comment Only
02/28/2020
Progress inspection of poured wall on southside approved.

Progress Inspection Passed 3/4/2020 (8:00 - 10:00) 3/4/2020 (AM) 03/04/2020
Corrections:


Miscellaneous/Other
Comment Only
03/04/2020
Progress on poured walls toward west end approved. Refer marked plans for locations.

Progress Inspection Passed 3/6/2020 (8:00 - 10:00) 3/6/2020 (AM) 03/06/2020
Corrections:


Miscellaneous/Other
Comment Only
03/06/2020
Remaining poured wall at west end of North side approved.

Progress Inspection Passed 3/12/2020 (8:00 - 10:00) 3/12/2020 (AM) 03/12/2020
Corrections:


Miscellaneous/Other
Comment Only
03/12/2020
Three pad footings toward west end approved.

Progress Inspection Passed 3/20/2020 (8:00 - 10:00) 3/20/2020 (AM) 03/23/2020
Corrections:


Miscellaneous/Other
Comment Only
03/23/2020
Remaining pad footings and strip footings at West end approved.

Progress Inspection Passed 4/1/2020 (8:00 - 10:00) 3/30/2020 (AM) 03/31/2020
Corrections:


Miscellaneous/Other
Comment Only
03/31/2020
Final inspection of poured walls at west end approved.

Progress Inspection Passed 4/7/2020 (8:00 - 10:00) 4/7/2020 (AM) 04/07/2020
Corrections:


Miscellaneous/Other
Comment Only
04/07/2020
Foundation walls for stoops at west end and turtle deck on southside approved.

Progress Inspection Passed 5/6/2020 (2:30 - 3:30) 5/6/2020 (PM) 05/06/2020
Corrections:


Miscellaneous/Other
Comment Only
05/06/2020
Progress inspection reviewing details on rated walls.

Progress Inspection Passed w/ Conditions 6/8/2020 (10:00 - 12:00) 6/8/2020 (AM) 06/09/2020
Corrections:


Miscellaneous/Other
Comment Only
06/09/2020
Progress inspection reveals need to maintain full nailing at sheer walls into studs.

Progress Inspection Passed 6/29/2020 (10:00 - 12:00) 6/29/2020 (AM) 06/30/2020
Corrections:


Miscellaneous/Other
Comment Only
06/30/2020
On-site meeting to review fire caulking with special inspectors and contractors for information purposes only.

Progress Inspection Passed 7/10/2020 (8:00 - 10:00) 7/10/2020 (AM) 07/10/2020
Corrections:


Miscellaneous/Other
Comment Only
07/10/2020
Progress inspection, no comments at this time.

Progress Inspection Passed 8/7/2020 (8:00 - 10:00) 8/7/2020 (AM) 08/07/2020
Corrections:


Miscellaneous/Other
Comment Only
08/07/2020
Preliminary site visit to inspect progress of structural tiedowns and schedule for completion of the same.

Progress Inspection Passed 9/4/2020 (8:00 - 10:00) 9/4/2020 (AM) 09/04/2020
Corrections:


Miscellaneous/Other
Comment Only
09/04/2020
First progress inspection of shear walls on first floor approved.

Progress Inspection Passed 9/11/2020 (8:00 - 10:00) 9/11/2020 (AM) 09/11/2020
Corrections:


Miscellaneous/Other
Comment Only
09/11/2020
Mansard roof trusses with crossbracing approved. Progress inspection of shear walls at stairwells approved.

Progress Inspection Passed 9/15/2020 (8:00 - 10:00) 9/15/2020 (AM) 09/16/2020
Corrections:


Miscellaneous/Other
Comment Only
09/16/2020
Footing with rebar for north tower approved. Progress inspection on housewrap approved.

Progress Inspection Failed 9/18/2020 (8:00 - 10:00) 9/18/2020 (AM) 09/18/2020
Corrections:


Miscellaneous/Other
Carried Forward
09/24/2020
Make corrections to nailing of shear walls as per list provided in field. Call for reinspection.

Progress Inspection Passed w/ Conditions 9/22/2020 (8:00 - 10:00) 9/22/2020 (AM) 09/22/2020
Corrections:


Miscellaneous/Other
Comment Only
09/22/2020
Corrections on sheer walls on floors one, two and three are substantially complete for proceeding with sheet rock at top 18 inches of walls. Some follow up inspections required. Fourth floor sheer wall inspection shows follow up required in rooms 406 and 412.

Progress Inspection Passed 10/2/2020 (8:00 - 10:00) 10/2/2020 (AM) 10/02/2020
Corrections:


Miscellaneous/Other
Comment Only
10/02/2020
Nailing inspection for shear walls on fifth floor approved.

Progress Inspection Passed 10/7/2020 (8:00 - 10:00) 10/7/2020 (AM) 10/07/2020
Corrections:


Miscellaneous/Other
Comment Only
10/07/2020
Reviewed progress with contractor of drywall installed on rated walls above ceiling line on fifth floor. OK to proceed as discussed on other floors.

Progress Inspection Failed 10/9/2020 (8:00 - 10:00) 10/9/2020 (AM) 10/09/2020
Corrections:


Miscellaneous/Other
Carried Forward
10/22/2020
Discussed continuity of rated shaft needed where penetrating floors with contractor in field. Architect to submit approved design method for corrections to maintain two hour rating continuity.

Progress Inspection Passed 10/16/2020 (8:00 - 10:00) 10/16/2020 (AM) 10/16/2020
Corrections:


Miscellaneous/Other
Comment Only
10/16/2020
Progress Inspection of insulation at energy pack closets on fifth floor approved.

Progress Inspection Passed 10/28/2020 (8:00 - 10:00) 10/28/2020 (AM) 10/28/2020
Corrections:


Miscellaneous/Other
Comment Only
10/28/2020
Progress inspection of insulation and sheet rock in stairwell shafts approved.

Progress Inspection Failed 11/4/2020 (2:30 - 3:30) 11/4/2020 (PM) 11/04/2020
Corrections:


Miscellaneous/Other
Outstanding
11/04/2020
Patch fire proofing on structural steel columns in multiple locations in West end units of first floor. Have reinspected.

Progress Inspection Partial Pass 11/6/2020 (8:00 - 10:00) 11/6/2020 (AM) 11/06/2020
Corrections:


Miscellaneous/Other
Comment Only
11/06/2020
Performed preliminary framing inspection of second floor and reviewed with contractor concerns regarding insulation of concealed corners, bolting requirements of Simpson hold down ties, plywood sheathing in rated shaft, and patching of fire proofing required on steel columns and beams. Contractor will provide special inspectors report with approval of Simpson tiedowns.

Progress Inspection Passed 11/9/2020 (2:30 - 3:30) 11/9/2020 (PM) 11/09/2020
Corrections:


Miscellaneous/Other
Comment Only
11/09/2020
Preliminary framing inspection of third floor to review structural components. No issues at this time.

Progress Inspection Passed 11/13/2020 (8:00 - 10:00) 11/13/2020 (AM) 11/13/2020
Corrections:


Miscellaneous/Other
Comment Only
11/13/2020
Progress inspection of Rebar in connection tower approved.

Progress Inspection Passed 11/19/2020 (2:30 - 3:30) 11/19/2020 (PM) 11/19/2020
Corrections:


Miscellaneous/Other
Comment Only
11/19/2020
Rebar in elevator pit in connection approved.

Progress Inspection Passed 11/25/2020 (2:30 - 3:30) 11/25/2020 (PM) 11/23/2020
Corrections:


Miscellaneous/Other
Comment Only
11/23/2020
Framing inspection of exterior walls only on fifth floor only, approved.

Progress Inspection Passed 11/30/2020 (2:30 - 3:30) 11/30/2020 (PM) 11/30/2020
Corrections:


Miscellaneous/Other
Comment Only
11/30/2020
Inspected fire caulking in exterior walls above ceiling in magic pack closets. OK to sheet rock lids on all floors.

Progress Inspection Passed 12/3/2020 (2:30 - 3:30) 12/3/2020 (PM) 12/03/2020
Corrections:


Miscellaneous/Other
Comment Only
12/03/2020
Vapor barrier on exterior walls of fifth floor units approved. Insulation in fifth floor shear walls approved and OK to cover.

Progress Inspection Partial Pass 12/9/2020 (2:30 - 3:30) 12/9/2020 (PM) 12/09/2020
Corrections:


Miscellaneous/Other
Carried Forward
12/09/2020
Progress inspection of sheer walls on fifth floor with second side enclosed approved. Corridors on all floors reveal wiring penetrations requiring fire caulk before closing.

Progress Inspection Passed 12/14/2020 (2:30 - 3:30) 12/14/2020 (PM) 12/14/2020
Corrections:


Miscellaneous/Other
Comment Only
12/14/2020
Plywood on both sides of shear walls on fifth floor approved. Exterior wall insulation and vapor barrier on fourth floor approved.

Progress Inspection Passed 12/21/2020 (2:30 - 3:30) 12/21/2020 (PM) 12/21/2020
Corrections:


Miscellaneous/Other
Comment Only
12/21/2020
All framing related issues and exterior wall insulation on fifth floor are approved and OK to cover. Fourth floor shear walls are approved to sheet rock top 18 inches

Progress Inspection Passed 1/5/2021 (2:30 - 3:30) 1/5/2021 (PM) 01/05/2021
Corrections:


Miscellaneous/Other
Comment Only
01/05/2021
Third floor exterior walls approved framing ready for insulation. Fourth floor exterior wall insulation and vapor barrier‘s all approved. Rated shaft on all floors of west stairwell progress approved, ready to close Remaining open side.

Progress Inspection Passed 1/11/2021 (2:30 - 3:30) 1/11/2021 (PM) 01/11/2021
Corrections:


Miscellaneous/Other
Comment Only
01/11/2021
Final inspection of shear walls on third floor approved. Exterior wall insulation and vapor barrier in third-floor units approved.

Progress Inspection Passed 1/15/2021 (2:30 - 3:30) 1/15/2021 (PM) 01/19/2021
Corrections:


Miscellaneous/Other
Resolved
01/19/2021
Fire proofing patching required on all structural steel in unit 202, 203, 206, 208, 209, 210, 211, 214 and 216. Call for reinspection.

Miscellaneous/Other
Comment Only
01/19/2021
Fireproof patching on second floor approved.

Progress Inspection Passed 1/22/2021 (2:30 - 3:30) 1/22/2021 (PM) 01/22/2021
Corrections:


Miscellaneous/Other
Comment Only
01/22/2021
Fire caulking in all units on third floor approved. Exterior wall insulation and vapor barrier in all units on second floor approved.

Progress Inspection Passed 1/28/2021 (2:30 - 3:30) 1/28/2021 (PM) 01/28/2021
Corrections:


Miscellaneous/Other
Comment Only
01/28/2021
Shear wall nailing on second floor approved.

Progress Inspection Passed 2/1/2021 (12:30 - 2:30) 2/1/2021 (PM) 02/01/2021
Corrections:


Miscellaneous/Other
Comment Only
02/01/2021
Fire caulk penetrations in wood studs in south east corner of unit 112. Missing nailing on sheer wall on west side of South lounge. Fire patch steel columns where clips are attached. All exterior walls on first level are approved for framing, Ready to insulate.

Progress Inspection Passed 2/3/2021 (2:30 - 3:30) 2/3/2021 (PM) 02/03/2021
Corrections:


Miscellaneous/Other
Comment Only
02/03/2021
Patch fire proofing in southwest corner of unit 214. Corrections required at rated shafts on second floor mezzanine area, call for progress inspections. Framing, fire caulking and insulation approved in all second floor units, OK to cover.

Progress Inspection Passed 2/11/2021 (2:30 - 3:30) 2/11/2021 (PM) 02/11/2021
Corrections:


Miscellaneous/Other
Comment Only
02/11/2021
Shear walls on first floor approved.

Progress Inspection Passed 2/18/2021 (2:30 - 3:30) 2/18/2021 (PM) 02/18/2021
Corrections:


Miscellaneous/Other
Comment Only
02/18/2021
Insulation, vapor barrier and fire caulking of first floor units approved.

Progress Inspection Passed 2/25/2021 (2:30 - 3:30) 2/25/2021 (PM) 02/25/2021
Corrections:


Miscellaneous/Other
Comment Only
02/25/2021
Performed progress inspection of rated shafts on all floors. Confirmed inspection schedule required for sealing shafts at floor levels over the next two weeks.

Progress Inspection Passed w/ Conditions 3/2/2021 (2:30 - 3:30) 3/2/2021 (PM) 03/02/2021
Corrections:


Miscellaneous/Other
Outstanding
03/02/2021
Patch fire proofing on structural steel columns and beams in second floor atrium as required. Remaining sheer walls in unfinished units on floors one through five approved.

Progress Inspection Passed 3/10/2021 (2:30 - 3:30) 3/10/2021 (PM) 03/10/2021
Corrections:


Miscellaneous/Other
Comment Only
03/10/2021
Exterior walls in larger units at east end floors one through five OK to insulate.

Progress Inspection Passed 3/25/2021 (2:30 - 3:30) 3/25/2021 (PM) 03/25/2021
Corrections:


Miscellaneous/Other
Comment Only
03/25/2021
Progress inspection of fire caulking in custom units aligned on five floors approved. Patch fireproofing on structural steel in second floor lobby area as required.

Progress Inspection Passed 3/30/2021 (2:30 - 3:30) 3/30/2021 (PM) 03/30/2021
Corrections:


Miscellaneous/Other
Comment Only
03/30/2021
Progress inspection of rated shafts includes coordination with sheet rock crew to see finishing applications of sheet rock during installation on trash and elevator shafts.

Progress Inspection Passed 4/6/2021 (2:30 - 3:30) 4/6/2021 (PM) 04/06/2021
Corrections:


Miscellaneous/Other
Comment Only
04/06/2021
Progress inspection of rated shaft on all levels approved. Confirmed method to correct and maintain elevator shaft protection on second floor, requiring additional inspection.

Progress Inspection Passed 4/8/2021 (12:30 - 2:30) 4/8/2021 (PM) 04/08/2021
Corrections:


Miscellaneous/Other
Comment Only
04/08/2021
Corrections made to rated elevator shaft wall on second floor approved.

Progress Inspection Passed 4/14/2021 (2:30 - 3:30) 4/14/2021 (PM) 04/14/2021
Corrections:


Miscellaneous/Other
Comment Only
04/14/2021
Follow up inspection of shafts on first and second floors, OK to cover all.

Progress Inspection Passed 6/10/2021 (8:00 - 10:00) 6/10/2021 (AM) 06/10/2021
Corrections:


Miscellaneous/Other
Comment Only
06/10/2021
Insulation of walls and floor in bridge connection to existing building approved, OK to cover on exterior.

Progress Inspection Passed 6/15/2021 (2:30 - 3:30) 6/15/2021 (PM) 06/15/2021
Corrections:


Miscellaneous/Other
Comment Only
06/15/2021
Met on site with contractor to discuss inspection requirements prior to certificate of occupancy for July 16. Performed preliminary exterior review to confirm scope of work required in following weeks.

Progress Inspection Passed 6/16/2021 (2:30 - 3:30) 6/16/2021 (PM) 06/16/2021
Corrections:


Miscellaneous/Other
Comment Only
06/16/2021
Progress inspection walk-through of garage level for preliminary final concerns. Discussed issues with project manager in field.

Progress Inspection Partial Pass 7/9/2021 (10:00 - 12:00) 7/9/2021 (AM) 07/09/2021
Corrections:


Miscellaneous/Other
Outstanding
07/09/2021
1. Current guard rail height at corner units on fifth floor are at 36 inches height. Plan calls for 42 inch height guard rails. 36 inch height guard rails will be excepted for temporary occupancy until replaced with 42 inch height rail. 2. Provide guard rail protection at 10 inch wide opening and deck in unit number 402. 3. Complete installation of guard rails and tighten bolts in unit number 415, 515 and 513. 4. Roof reviewed and approved. 5. Provide three additional illuminated exit signs in garage as discussed in field.

Progress Inspection Passed 7/12/2021 (2:30 - 3:30) 7/12/2021 (PM) 07/12/2021
Corrections:


Miscellaneous/Other
Comment Only
07/12/2021
Progress inspection of pre-final requirements for temporary occupancy, guard rails on decks and third-floor approve.

Progress Inspection Failed 7/13/2021 (2:30 - 3:30) 7/13/2021 (PM) 07/13/2021
Corrections:


Miscellaneous/Other
Carried Forward
07/16/2021
Inspection of deck guard rails on all five levels is complete. List of corrections regarding bolting and fastening to be provided separately. Provide fire blocking separation in cavity at fireplace in lobby at the first, second floor line. Maintain barricade or guard rail at second floor lobby. Door closer in unit number 107 doesn’t close.

Lighting Inspection Passed 07/14/2021
Underground parking garage passed on 7/12/21. Exterior lighting is not for parking and has 90-degree cut-off.
Progress Inspection Passed 7/15/2021 (10:00 - 12:00) 7/15/2021 (AM) 07/15/2021
Corrections:


Miscellaneous/Other
Comment Only
07/15/2021
Temporary occupancy inspection for unit number 502 and 313, including common areas associated with access, exiting and parking needs as required approved. Temporary occupancy approved for the above units for 30 days.

Progress Inspection Passed 7/29/2021 (10:00 - 12:00) 7/29/2021 (AM) 07/29/2021
Corrections:


Miscellaneous/Other
Comment Only
07/29/2021
Temporary occupancy expanded to include all dwelling units. Maintain barricades and guard rail protection as noted before. Maintain proper exiting as noted before.

Progress Inspection Passed 8/11/2021 (2:30 - 3:30) 8/11/2021 (PM) 08/11/2021
Corrections:


Miscellaneous/Other
Comment Only
08/11/2021
Framing on second floor bridge approved. Provide photos of fire proof patching as required.

Fire Inspection Final Partial Pass 7/16/2021 (8:00 - 10:00) 7/16/2021 (AM) 08/16/2021
Building Final Inspection Issue TCO 10/13/2021 (10:00 - 12:00) 10/14/2021 (AM) 10/14/2021
Corrections:


Miscellaneous/Other
Carried Forward
10/14/2021
1. Complete framing and finish of underside of stairs at link stairwell main level. 2. Tighten bolts on guard rail posts at second floor lobby. 3. Extend temporary occupancy approval to December 1.

Building Final Inspection Issue CO 11/04/2021
Corrections:


Miscellaneous/Other
Resolved
11/04/2021
1. Complete framing and finish of underside of stairs at link stairwell main level. 2. Tighten bolts on guard rail posts at second floor lobby. 3. Extend temporary occupancy approval to December 1.

Building Final Inspection Passed 11/04/2021