PRBD201906400
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 7/18/2019 (8:00 - 10:00) | 7/18/2019 (AM) | 07/18/2019 |
Corrections:
Miscellaneous/Other
Comment Only
07/18/2019
First phase framing of walls approved and above ceiling.
|
||||
Framing Inspection | Partial Pass | 10/9/2019 (2:30 - 3:30) | 10/9/2019 (PM) | 10/09/2019 |
Phase 2 of 2 framing . Need trade inspections above ceiling. | ||||
Fire Inspection Final | Passed | 11/13/2019 (2:30 - 3:30) | 11/13/2019 (PM) | 11/12/2019 |
Building Final Inspection | Passed | 11/13/2019 (2:30 - 3:30) | 11/13/2019 (PM) | 11/13/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2019
Final approved
|