PRBD201907066
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 7/18/2019 (10:00 - 12:00) | 7/18/2019 (AM) | 07/18/2019 |
Corrections:
Miscellaneous/Other
Resolved
07/18/2019
Need electrical rough in approval.
|
||||
Building Final Inspection | Passed w/ Conditions | 07/29/2019 | ||
Final approved, 2 ceiling fluorescents on EM GENERATOR CIRCUIT. A. STILL NEED FINAL FIRE MARSHAL INSPECTION . FINAL BUILDING CONTINGENT UPON FIRE MARSHAL FINAL. | ||||
Fire Inspection Final | Passed | 8/7/2019 (12:30 - 2:30) | 8/7/2019 (PM) | 08/07/2019 |