PRBD201907653
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 10/30/2019 (10:00 - 12:00) | 10/30/2019 (AM) | 10/30/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/30/2019
Wall framing on East half approved
|
||||
Framing Inspection | Partial Pass | 11/6/2019 (10:00 - 12:00) | 11/6/2019 (AM) | 11/06/2019 |
Corrections:
Miscellaneous/Other
Comment Only
11/06/2019
Framing of All walls... approved
Call for above ceiling inspection nice all other trades are inspected.
|
||||
Framing Inspection | VOID | 12/23/2019 | ||
Fire Inspection Final | Partial Pass | 12/31/2019 (10:00 - 12:00) | 12/31/2019 (AM) | 12/31/2019 |
Building Final Inspection | Partial Pass | 12/31/2019 (10:00 - 12:00) | 12/31/2019 (AM) | 12/31/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/31/2019
Phase 1...
install the sink and other appliances, and remaining exit sign.
Extinguishers to be installed in break room and electrical room. Recheck these items once tenant is moved over to this space for start of phase 2.
Approved to move tenant to phase 1 for use of this area.
|
||||
Framing Inspection | Partial Pass | 1/17/2020 (8:00 - 10:00) | 1/17/2020 (AM) | 01/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2020
Phase two framing...
Remove sprinkler piping and head from wall and cleat studs at the notches.
Ok to proceed pending electrical and plumbing inspections.
|
||||
Building Final Inspection | Partial Pass | 2/25/2020 (10:00 - 12:00) | 2/25/2020 (AM) | 02/25/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/25/2020
Phase 2 approved for occupancy pending conditions of Max occupancy sign installation in training room of 49, and directional signage installed near phase 3 exit.
|
||||
Fire Inspection Final | Partial Pass | 2/25/2020 (10:00 - 12:00) | 2/25/2020 (AM) | 02/25/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/25/2020
Final phase II approved with condition of install of max. Occupancy of 49 sign in training room
|
||||
Miscellaneous/Other
Comment Only
02/25/2020
Final phase II approved with condition of install of max. Occupancy of 49 sign in training room
|
||||
Framing Inspection | Partial Pass | 3/9/2020 (2:30 - 3:30) | 3/9/2020 (PM) | 03/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/09/2020
Phase 3 , framing of the two walls for the corner room... approved
|
||||
Fire Inspection Final | Passed w/ Conditions | 4/14/2020 (8:00 - 10:00) | 4/14/2020 (AM) | 04/14/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/14/2020
Approved pending Building Inspector Final
|
||||
Building Final Inspection | Passed | 4/14/2020 (8:00 - 10:00) | 4/14/2020 (AM) | 04/14/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/14/2020
Phased construction is completed and approved for turnover and office use.
|