Framing Inspection | Partial Pass | 9/13/2019 (8:00 - 10:00) | 9/13/2019 (AM) | 09/13/2019 |
Wall framing. Passed. CALL FOR ABOVE CEILING INSPECTION. A. May revise plan for new store restrooms? B. Wall framing with existing store front and framing to remain. C. Must patch fireproofing on I-beams at ceiling. Fire caulk and mineral wool one 4-5 inch diameter plumbing floor penetration, visible from mall bsmt. D. Look at the existing above ceiling smoke zones, note existing openings, do not provide for a minimum of 20 sq ft. | ||||
Framing Inspection | Passed | 9/24/2019 (8:00 - 10:00) | 9/24/2019 (AM) | 09/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2019
Above ceiling and framing approved.
Contractor to send pictures to inspector of the pins installed in holes on floor prior to filling with concrete.
|
||||
Fire Inspection Final | Passed w/ Conditions | 10/25/2019 (12:30 - 2:30) | 10/25/2019 (PM) | 10/25/2019 |
Corrections:
Fire extinguisher(s) needed.
Comment Only
10/25/2019
Ensure Fire extinguishers are installed in path of egress.
Final approved pending all other trades and building inspector final.
|
||||
Miscellaneous/Other
Comment Only
10/25/2019
Final approved pending building inspection final.
|
||||
Building Final Inspection | Partial Pass | 10/25/2019 (12:30 - 2:30) | 10/25/2019 (PM) | 10/25/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2019
Approved to stock space only, no opening at this time. See “outstanding “comments for corrections for the final.
|
||||
Miscellaneous/Other
Carried Forward
10/25/2019
1) install accessibility signage for the bathroom, see the approved city plan for the highlighted detail with signage.
2) electrical inspection and final needed for the full final of the building permit.
3) appears to have a removed horn strobe at the back exit hallway of the now mall storage area... wires to be capped and enclosed in a covered junction box.
4) remove smoke detector cover for final once all cleaning is done.
|
||||
Building Final Inspection | Passed | 11/5/2019 (2:30 - 3:30) | 11/5/2019 (PM) | 11/05/2019 |
Corrections:
Miscellaneous/Other
Resolved
11/05/2019
1) install accessibility signage for the bathroom, see the approved city plan for the highlighted detail with signage.
2) electrical inspection and final needed for the full final of the building permit.
3) appears to have a removed horn strobe at the back exit hallway of the now mall storage area... wires to be capped and enclosed in a covered junction box.
4) remove smoke detector cover for final once all cleaning is done.
|
||||
Miscellaneous/Other
Comment Only
11/05/2019
Final approved, ok to occupy and open to the public.
|