PRBD201909063
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed w/ Conditions | 08/19/2019 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/19/2019
2 walls are approved for framing, but cannot be covered till inspection of electrical is completed and approved to cover..
|
||||
Building Final Inspection | Passed | 10/31/2019 (10:00 - 12:00) | 10/31/2019 (AM) | 10/31/2019 |
Corrections:
Miscellaneous/Other
Comment Only
10/31/2019
Final approved pending fire inspection final.
|
||||
Fire Inspection Final | Passed | 10/31/2019 (10:00 - 12:00) | 10/31/2019 (AM) | 10/31/2019 |