PRBD201909585
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 9/24/2019 (8:00 - 10:00) | 9/24/2019 (AM) | 09/24/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2019
Wall framing approved and ok to cover.
Contractor to frame and double gypsum ceiling at far door exit to maintain rating of cooridor. Reinspection required.
|
||||
Framing Inspection | Passed | 9/27/2019 (10:00 - 12:00) | 9/27/2019 (AM) | 09/27/2019 |
Corrections:
Miscellaneous/Other
Comment Only
09/27/2019
At door I set where door recess had to be built, the ceiling needed to be built to tie into the existing rated cooridor wall section to maintain the rating separation.
Framing is attached to the top of walls and is connected to the cooridor wall with 2 adheared layers of 5/8” type “X” gypsum.
Approved.
|
||||
Building Final Inspection | Passed | 11/12/2019 (10:00 - 12:00) | 11/12/2019 (AM) | 11/12/2019 |
Building(Jon) and fire(Kris) finals removed from schedule 11/01/2019. jsmidt 10/29/2019 3:05 PM | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/12/2019
Work completed and is per approved plans. Final and occupancy approved
|