Permit Application Status

PRBD201910003


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201910003
Building
Finaled
CITY OF BLOOMINGTON
New
Not Required
Remove and replace the existing Dred Scott Wheel House. Site upgrades to replace damaged paving and improve drainage around the wheel house.
08/27/2019
10/18/2019
01/05/2021
07/09/2020

Locations

Permits

Permit Number: PRBD201910003

Building
Finaled
10/18/2019
01/05/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Passed 12/16/2019 (12:30 - 2:30) 12/16/2019 (PM) 12/16/2019
Corrections:


Miscellaneous/Other
Comment Only
12/16/2019
Stripped footings with rebar as per plan for south half of building on sandy soil approved.

Footing Inspection Partial Pass 12/17/2019 (12:30 - 2:30) 12/17/2019 (PM) 12/17/2019
Pour #2 footing.A. Continuous strip footing with continuous rebar per plan. B. Wet set footing dowels for 16 inch on center (core fill CMU Foundation walls per plan. ) C. Special inspections HAS NOT ARRIVED. D. Partial pass, as ongoing footing inspections still remain.
Footing Inspection Partial Pass 12/19/2019 (12:30 - 2:30) 12/19/2019 (PM) 12/19/2019
2 4x4ft pad footings for concrete piers. Balance of east strip footing with large 5x5 footing. PSI COMPANY - special inspector, on site, only doing concrete testing ? REBAR APPROVED BY CITY INSPECTOR. 30 DEGREE F temperature.
Footing Inspection Passed 12/20/2019 (10:00 - 12:00) 12/20/2019 (AM) 12/20/2019
Completion of footings and including 2 poured reinforced concrete piers.
Footing Inspection Passed 1/28/2020 (10:00 - 12:00) 1/28/2020 (AM) 01/28/2020
Corrections:


Miscellaneous/Other
Comment Only
01/28/2020
Eight footing pads, each being 4‘ x 4‘ x 12“ deep with number five rebar each way all on sandy soil approved.

Footing Inspection Passed 1/29/2020 (10:00 - 12:00) 1/29/2020 (AM) 01/29/2020
Corrections:


20"x8" strip footings per approved drawing on sandy soil-OK
Comment Only
01/29/2020
8 foot in pads, 4 x 4 x 12“ deep with number five rebar. Four columns northside approved.

Footing Inspection Passed 1/30/2020 (10:00 - 12:00) 1/30/2020 (AM) 01/30/2020
Corrections:


Miscellaneous/Other
Comment Only
01/30/2020
Eight columns on northside complete. OK to place concrete.

Footing Inspection Passed 1/31/2020 (10:00 - 12:00) 1/31/2020 (AM) 01/31/2020
Corrections:


Miscellaneous/Other
Comment Only
01/31/2020
Eight foundation columns for canopies at south end of project approved.

Framing Inspection Passed 4/8/2020 (10:00 - 12:00) 4/8/2020 (AM) 04/08/2020
Building Final Inspection Failed 6/12/2020 (10:00 - 12:00) 6/12/2020 (AM) 06/12/2020
Corrections:


Miscellaneous/Other
Carried Forward
06/12/2020
Provide full ADA access from parking lot to building. Finish roof and siding work. Need final electrical approval. Call for reinspection.

Fire Inspection Final Partial Pass 6/11/2020 (12:30 - 2:30) 6/11/2020 (PM) 06/16/2020
Fire Inspection Final Passed 6/19/2020 (8:00 - 10:00) 6/19/2020 (AM) 06/19/2020
Building Final Inspection Issue TCO 6/19/2020 (8:00 - 10:00) 6/19/2020 (AM) 06/19/2020
Corrections:


Miscellaneous/Other
Resolved
06/19/2020
Provide full ADA access from parking lot to building. Finish roof and siding work. Need final electrical approval. Call for reinspection.

Miscellaneous/Other
Carried Forward
06/19/2020
Provide handicap parking signage as per ADA. Complete second layer of paving on the path to provide smooth transition to concrete for wheelchair access. Complete trim on metal roofing. Provide cane guard protection at left drinking fountain for height exceeding 27 inches. 10 day temporary occupancy approved, call for reinspection.

Building Final Inspection Passed 7/9/2020 (10:00 - 12:00) 7/9/2020 (AM) 07/09/2020
Corrections:


Miscellaneous/Other
Resolved
07/09/2020
Provide handicap parking signage as per ADA. Complete second layer of paving on the path to provide smooth transition to concrete for wheelchair access. Complete trim on metal roofing. Provide cane guard protection at left drinking fountain for height exceeding 27 inches. 10 day temporary occupancy approved, call for reinspection.