PRBD201910504
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Framing Inspection | Passed w/ Conditions | 11/19/2019 (12:30 - 2:30) | 11/19/2019 (PM) | 11/19/2019 |
Additional restrooms including one wellness room. A. 2 Accessible restrooms, 2 standard restrooms, and new wellness room. B. Call for ALL REQUIRED above ceiling inspections for, FIRE SPRINKLER, HVAC, ELECTRICAL, ELECTRICAL LOW VOLTAGE, AND PLUMBING. | ||||
Fire Inspection Final | Failed | 1/2/2020 (8:00 - 10:00) | 1/2/2020 (AM) | 01/02/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
01/02/2020
Need to close out and final inspection all life safety permits prior to building final inspection.
|
||||
Building Final Inspection | Partial Pass | 1/2/2020 (8:00 - 10:00) | 1/2/2020 (AM) | 01/02/2020 |
Need mothers room sink, accessible knee and toe space clearance panel corrected. A. Need fire marshal final, prior to building final. B. Call for building final when ready. C. All restrooms and drinking fountain work completed as of the date of this inspection. D. TEMP OCCUPANCY APPROVED. | ||||
Fire Inspection Final | Passed | 01/07/2020 | ||
Corrections:
Miscellaneous/Other
Outstanding
01/02/2020
Need to close out and final inspection all life safety permits prior to building final inspection.
|