Summary

PRBD201910958
Building
Finaled
KNOX & AMERICAN I LLC
New
Not Required
1901 W 80th 1/2 St - Project consists of two apartment buildings mirroring each other. Each apartment building will have 1 level of underground parking with a precast lid and four stories above grade wood framing.
09/17/2019
01/03/2020
12/04/2021
06/07/2021

Locations

Permits

Permit Number: PRBD201910958

Building
Finaled
01/03/2020
12/04/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 01/08/2020
Footings completed. A. Need special inspection final summary report, to final out footings.
Corrections:


Miscellaneous/Other
Comment Only
01/08/2020
8 pad footings. Lines W10 & W11 between grids WH to WE.2. Elevator walls grids W9 & W10 at WD.4 to WE. Approved for concrete placement.

Progress Inspection Partial Pass 9/3/2020 (10:00 - 12:00) 9/3/2020 (AM) 09/03/2020
Fire caulk- 4th floor; - west, south to north wing. Passed. Ongoing work.
Progress Inspection Partial Pass 9/8/2020 (8:00 - 10:00) 9/8/2020 (AM) 09/08/2020
Progress Exterior - A. Window installation, Housewrap. Passed. Ongoing work. B. Flat roof by TPO white membrane, with main roof drain from flat roof, thru building to below underground Podium concrete parking.
Progress Inspection Partial Pass 9/11/2020 (8:00 - 10:00) 9/11/2020 (AM) 09/11/2020
Fire caulk-draft stop: 4th floor east wing. Passed. Ongoing work.
Progress Inspection Partial Pass 9/15/2020 (8:00 - 10:00) 9/15/2020 (AM) 09/15/2020
Progress Passed, ongoing work.
Progress Inspection Partial Pass 9/18/2020 (8:00 - 10:00) 9/18/2020 (AM) 09/22/2020
Passed, on going work.
Progress Inspection Partial Pass 9/22/2020 (8:00 - 10:00) 9/22/2020 (AM) 09/22/2020
On going work. Passed.
Progress Inspection Partial Pass 9/25/2020 (8:00 - 10:00) 9/25/2020 (AM) 09/25/2020
3rd floor West Wing- Fire caulk, Passed Per Sam.Weis builders.
Progress Inspection Partial Pass 9/29/2020 (8:00 - 10:00) 9/29/2020 (AM) 09/29/2020
Progress. Passed . Ongoing work.
Progress Inspection Partial Pass 10/2/2020 (8:00 - 10:00) 10/2/2020 (AM) 10/02/2020
Housewrap - progress. 2nd floor west wing-Fire caulk. Passed.
Progress Inspection Partial Pass 10/6/2020 (8:00 - 10:00) 10/6/2020 (AM) 10/06/2020
Progress - Passed. Ongoing work.
Progress Inspection Partial Pass 10/9/2020 (8:00 - 10:00) 10/9/2020 (AM) 10/13/2020
Progress.
Insulation Inspection Partial Pass 10/26/2020
Insulation - interior. A. exterior walls and party walls. B. Fire caulk. Passed. Ongoing work.
Progress Inspection Partial Pass 11/02/2020
Progress. Ongoing work.
Framing Inspection Partial Pass 02/11/2021
Progress - walk thru. A. Trimming out units, and stairways.
Building Final Inspection Partial Pass 5/10/2021 (8:00 - 10:00) 5/10/2021 (AM) 05/10/2021
Stairwell rated 1.5 hrs doors . A. Must install rated thresholds to achieve smoke rating. B. Corridor rated door closers - a lot of doors not self closing to latch. C. Address numbers painted contrasting color per fire marshal - passed. D. MECHANICAL BALANCING REPORT MUST BE COMPLETED AND APPROVED BY MECHANICAL INSPECTOR Jesse Soller.
Lighting Inspection Passed 05/12/2021
Insulation Inspection Passed 05/13/2021
Progress Inspection Passed 05/13/2021
Framing - partial pass.
Progress Inspection Passed 05/13/2021
Progress inspection.
Housewrap Inspection Passed 05/13/2021
House wrap for exterior siding clad.
Framing Inspection Passed 05/13/2021
Framing is completed.
Fire Inspection Final Passed 5/10/2021 (8:00 - 10:00) 5/10/2021 (AM) 06/02/2021
Building Final Inspection Issue CO 06/07/2021
Per Bpost. A. Need final ...HVAC, Engineering Division, Electrical, Fire, plumbing. Note - landscape and lighting has passed.