PRBD201910958
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 01/08/2020 | ||
Footings completed. A. Need special inspection final summary report, to final out footings. | ||||
Corrections:
Miscellaneous/Other
Comment Only
01/08/2020
8 pad footings. Lines W10 & W11 between grids WH to WE.2.
Elevator walls grids W9 & W10 at WD.4 to WE.
Approved for concrete placement.
|
||||
Progress Inspection | Partial Pass | 9/3/2020 (10:00 - 12:00) | 9/3/2020 (AM) | 09/03/2020 |
Fire caulk- 4th floor; - west, south to north wing. Passed. Ongoing work. | ||||
Progress Inspection | Partial Pass | 9/8/2020 (8:00 - 10:00) | 9/8/2020 (AM) | 09/08/2020 |
Progress Exterior - A. Window installation, Housewrap. Passed. Ongoing work. B. Flat roof by TPO white membrane, with main roof drain from flat roof, thru building to below underground Podium concrete parking. | ||||
Progress Inspection | Partial Pass | 9/11/2020 (8:00 - 10:00) | 9/11/2020 (AM) | 09/11/2020 |
Fire caulk-draft stop: 4th floor east wing. Passed. Ongoing work. | ||||
Progress Inspection | Partial Pass | 9/15/2020 (8:00 - 10:00) | 9/15/2020 (AM) | 09/15/2020 |
Progress Passed, ongoing work. | ||||
Progress Inspection | Partial Pass | 9/18/2020 (8:00 - 10:00) | 9/18/2020 (AM) | 09/22/2020 |
Passed, on going work. | ||||
Progress Inspection | Partial Pass | 9/22/2020 (8:00 - 10:00) | 9/22/2020 (AM) | 09/22/2020 |
On going work. Passed. | ||||
Progress Inspection | Partial Pass | 9/25/2020 (8:00 - 10:00) | 9/25/2020 (AM) | 09/25/2020 |
3rd floor West Wing- Fire caulk, Passed Per Sam.Weis builders. | ||||
Progress Inspection | Partial Pass | 9/29/2020 (8:00 - 10:00) | 9/29/2020 (AM) | 09/29/2020 |
Progress. Passed . Ongoing work. | ||||
Progress Inspection | Partial Pass | 10/2/2020 (8:00 - 10:00) | 10/2/2020 (AM) | 10/02/2020 |
Housewrap - progress. 2nd floor west wing-Fire caulk. Passed. | ||||
Progress Inspection | Partial Pass | 10/6/2020 (8:00 - 10:00) | 10/6/2020 (AM) | 10/06/2020 |
Progress - Passed. Ongoing work. | ||||
Progress Inspection | Partial Pass | 10/9/2020 (8:00 - 10:00) | 10/9/2020 (AM) | 10/13/2020 |
Progress. | ||||
Insulation Inspection | Partial Pass | 10/26/2020 | ||
Insulation - interior. A. exterior walls and party walls. B. Fire caulk. Passed. Ongoing work. | ||||
Progress Inspection | Partial Pass | 11/02/2020 | ||
Progress. Ongoing work. | ||||
Framing Inspection | Partial Pass | 02/11/2021 | ||
Progress - walk thru. A. Trimming out units, and stairways. | ||||
Building Final Inspection | Partial Pass | 5/10/2021 (8:00 - 10:00) | 5/10/2021 (AM) | 05/10/2021 |
Stairwell rated 1.5 hrs doors . A. Must install rated thresholds to achieve smoke rating. B. Corridor rated door closers - a lot of doors not self closing to latch. C. Address numbers painted contrasting color per fire marshal - passed. D. MECHANICAL BALANCING REPORT MUST BE COMPLETED AND APPROVED BY MECHANICAL INSPECTOR Jesse Soller. | ||||
Lighting Inspection | Passed | 05/12/2021 | ||
Insulation Inspection | Passed | 05/13/2021 | ||
Progress Inspection | Passed | 05/13/2021 | ||
Framing - partial pass. | ||||
Progress Inspection | Passed | 05/13/2021 | ||
Progress inspection. | ||||
Housewrap Inspection | Passed | 05/13/2021 | ||
House wrap for exterior siding clad. | ||||
Framing Inspection | Passed | 05/13/2021 | ||
Framing is completed. | ||||
Fire Inspection Final | Passed | 5/10/2021 (8:00 - 10:00) | 5/10/2021 (AM) | 06/02/2021 |
Building Final Inspection | Issue CO | 06/07/2021 | ||
Per Bpost. A. Need final ...HVAC, Engineering Division, Electrical, Fire, plumbing. Note - landscape and lighting has passed. |