Permit Application Status

PRBD201910998


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201910998
Building
Finaled
KNOX & AMERICAN I LLC
New
Not Required
Project consists of two apartment buildings mirroring each other. Each apartment building will have 1 level of underground parking with a precast lid and four stories above grade wood framing.
09/18/2019
01/03/2020
12/04/2021
06/07/2021

Locations

Permits

Permit Number: PRBD201910998

Building
Finaled
01/03/2020
12/04/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 1/24/2020 (10:00 - 12:00) 1/24/2020 (AM) 01/24/2020
First floor framing inspection above precast plank parking deck. Area of building- south east at fire rated stairwell. A. 1st layer of 2 layers of gypsum. Fastener type flush head pneumatic nail gun nails per specifications. 12 inch max spacing. Partial pass. B. Call for second layer of rated stair shaft gypsum nail pattern when ready. C. Anchor bolt type - Titan HD, spacing per plan.
Insulation Inspection Passed 3/16/2020 (8:00 - 10:00) 3/16/2020 (AM) 03/16/2020
Slab on grade poly vapor barrier.
Framing Inspection Partial Pass 5/1/2020 (12:30 - 2:30) 5/1/2020 (PM) 05/01/2020
Framing Inspection Partial Pass 5/12/2020 (12:30 - 2:30) 5/12/2020 (PM) 05/12/2020
Progress - framing inspection general walk thru. A. Fire caulk meeting with trade foreman. B. Fire Rated electrical boxes, draft stop attic air space, rated ceilings and walls, concealed spaces, fire caulk, fire caulk collars. Rated primary structural column and beam members supporting more than 2 stories or 1 story and a roof.
Framing Inspection Passed 5/20/2020 (8:00 - 10:00) 5/20/2020 (AM) 05/20/2020
Fire caulk, electrical wall box 100 sq inches in 100 sq feet of wall, draft stop, wall and ceiling. THIS FOR THE MOCK UP UNIT.
Framing Inspection Partial Pass 6/2/2020 (10:00 - 12:00) 6/2/2020 (AM) 06/02/2020
4th floor - south east corner working north. A. Concealed spaces. B. Ceiling electrical puddy pads. C. Insulate top plate gap of double walls.
Insulation Inspection Partial Pass 6/5/2020 (10:00 - 12:00) 6/5/2020 (AM) 06/05/2020
4th floor south east working north - unit Insulation partial pass, as ongoing work.
Corrections:


Miscellaneous/Other
Comment Only
06/05/2020
4th floor south east working north. (Interior units insulation- Passed.) Ongoing work- partial pass.

Progress Inspection Partial Pass 6/8/2020 (10:00 - 12:00) 6/8/2020 (AM) 06/09/2020
Unit interior Insulation for walls and ceiling - 4th floor south east working north - ongoing inspections.
Framing Inspection Partial Pass 6/9/2020 (10:00 - 12:00) 6/9/2020 (AM) 06/09/2020
Framing - 4th floor south west wing working north. Ongoing inspections.
Corrections:


Miscellaneous/Other
Comment Only
06/09/2020
Framing - south west wing working north. Ongoing inspections.

Progress Inspection Partial Pass 6/10/2020 (10:00 - 12:00) 6/10/2020 (AM) 06/10/2020
Progress Walk thru - passed. Ongoing work.
Progress Inspection Partial Pass 6/22/2020 (10:00 - 12:00) 6/22/2020 (AM) 06/22/2020
Framing - 1st floor-framing, fire rated protection of primary structural members/connectors by gypsum.
Framing Inspection Partial Pass 6/23/2020 (8:00 - 10:00) 6/23/2020 (AM) 06/23/2020
3rd floor East - Framing and fire-caulking by Weis Builders. Passed.Inspector on vacation. 3rd floor west : Framing and fire-caulking. Passed. Ongoing work.
Progress Inspection Partial Pass 6/26/2020 (8:00 - 10:00) 6/26/2020 (AM) 06/26/2020
Progress - main floor common area, one hour rated protection of laminated wood primary structural columns and beams by gypsum, prior to installing gypsum.
Progress Inspection Partial Pass 6/30/2020 (8:00 - 10:00) 6/30/2020 (AM) 06/30/2020
Framing - 2nd floor east wing from south to north. Fire caulk, draft stop, framing.-passed. Ongoing work.
Progress Inspection Partial Pass 7/7/2020 (8:00 - 10:00) 7/7/2020 (AM) 07/07/2020
Framing-firecaulking. A. 2nd floor NORTH WING - Far East to west center of building. Passed. Ongoing inspections.
Progress Inspection Partial Pass 7/10/2020 (8:00 - 10:00) 7/10/2020 (AM) 07/10/2020
Framing and fire caulking : 2 story portion. A. 2nd floor - north to south, units west wing. Passed. ONGOING INSPECTIONS.
Progress Inspection Partial Pass 7/14/2020 (8:00 - 10:00) 7/14/2020 (AM) 07/14/2020
A. 1st floor- east wing: units. Not ready. B. Main 1st floor common area, primary wood structural members covered in 5/8 gypsum. Consult progress. Only partially completed. C. Call for reinspection.
Progress Inspection Partial Pass 7/17/2020 (8:00 - 10:00) 7/17/2020 (AM) 07/17/2020
Progress - Main level common area. A. Fire resistance by 5/8 gypsum for primary and secondary wood structural members for columns and beams. B. Ongoing work.
Progress Inspection Partial Pass 7/21/2020 (8:00 - 10:00) 7/21/2020 (AM) 07/21/2020
Main floor east wing south to north. A. Need fire sprinkler water pipe installed and fire caulked. Verify floor to parking garage plumbing pipe 3 inch or less penetration thru precast plank, for required top side fire caulk requirements.
Progress Inspection Partial Pass 7/24/2020 (8:00 - 10:00) 7/24/2020 (AM) 07/24/2020
Framing - A. Main floor east wing, south to north. B. Framing-passed. C. Fire sprinkler system pipe Is not completed. B. Scheduled Inspection next Tuesday, OK to proceed.
Progress Inspection Partial Pass 7/28/2020 (8:00 - 10:00) 7/28/2020 (AM) 07/28/2020
Main floor wing - framing and fire caulking: A. Far East living units working west to west common area only, but including electrical rooms, work out room, janitor closets.
Progress Inspection Partial Pass 7/31/2020 (8:00 - 10:00) 7/31/2020 (AM) 07/31/2020
Progress: main floor common area, individual gypsum protection around all primary structural members supporting 2 floors or one story and a roof. Passed. Ongoing inspections.
Progress Inspection Partial Pass 8/4/2020 (8:00 - 10:00) 8/4/2020 (AM) 08/04/2020
Main floor - west wing, south to north room units. A. Exterior walls only for insulation. Passed. Note-all floor penetrations will be fire caulked from below in the parking ramp. B. CALL FOR REINSPECTION.
Progress Inspection Partial Pass 8/6/2020 (8:00 - 10:00) 8/6/2020 (AM) 08/06/2020
1st floor - west wing from south to north. Not common area, A. Framing and fire rated assemblies, fire-caulk. Draft stop. NOTE - All floor penetrations to be fire-caulked and fire collar from ceiling of parking ramp below. Passed. Ongoing work.
Progress Inspection Partial Pass 8/7/2020 (8:00 - 10:00) 8/7/2020 (AM) 08/07/2020
Progress on main floor common area. Questions - Not completed at this time. Ongoing work. A. Electrical rooms top of wood walls, wires penetrations- fire caulked.ongoing work.
Progress Inspection Partial Pass 8/14/2020 (8:00 - 10:00) 8/14/2020 (AM) 08/14/2020
Common area fire rated protection - of individual structural members for main floor common area.
Progress Inspection Partial Pass 8/18/2020 (8:00 - 10:00) 8/18/2020 (AM) 08/18/2020
Main floor common area - Individual protection of primary structural wood beams, columns, and connectors. Corrections required. Call for reinspection.
Progress Inspection Partial Pass 8/19/2020 (10:00 - 12:00) 8/19/2020 (AM) 08/19/2020
Main 1st floor common area - A. Individual protection of Main floor common area structural beams and columns supporting more than 2 story, or 1 story and a roof. Sprinklered building. Passed. B. Partial pass status due to ongoing Status of framing
Progress Inspection Partial Pass 8/21/2020 (8:00 - 10:00) 8/21/2020 (AM) 08/21/2020
Framing - main floor common area. Passed. Ongoing work .
Progress Inspection Partial Pass 8/25/2020 (8:00 - 10:00) 8/25/2020 (AM) 08/25/2020
Progress - ongoing work.
Progress Inspection Passed 8/28/2020 (8:00 - 10:00) 8/28/2020 (AM) 08/28/2020
Progress - main floor common area.
Progress Inspection Partial Pass 9/1/2020 (8:00 - 10:00) 9/1/2020 (AM) 09/01/2020
Stairwell gypsum - progress, 2 layer gypsum fire rated assembly - passed. Ongoing work.
Progress Inspection Partial Pass 9/4/2020 (8:00 - 10:00) 9/4/2020 (AM) 09/04/2020
Spray applied mono coat, fireproofing on steel. Special inspection required. Ongoing work.
Progress Inspection Partial Pass 9/8/2020 (8:00 - 10:00) 9/8/2020 (AM) 09/08/2020
Progress - 2 layer gypsum stairway shafts. OK to proceed. Ongoing work.
Progress Inspection Partial Pass 9/11/2020 (8:00 - 10:00) 9/11/2020 (AM) 09/11/2020
Progress inspection, exterior.
Progress Inspection Partial Pass 9/15/2020 (8:00 - 10:00) 9/15/2020 (AM) 09/15/2020
Progress passed, ongoing work.
Progress Inspection Partial Pass 9/18/2020 (8:00 - 10:00) 9/18/2020 (AM) 09/22/2020
Progress. Ongoing work.
Progress Inspection Partial Pass 9/22/2020 (8:00 - 10:00) 9/22/2020 (AM) 09/22/2020
On going work - passed.
Progress Inspection Partial Pass 9/25/2020 (8:00 - 10:00) 9/25/2020 (AM) 09/25/2020
Fire caulk - passed. Ongoing work.
Progress Inspection Partial Pass 9/29/2020 (8:00 - 10:00) 9/29/2020 (AM) 09/29/2020
Progress.
Progress Inspection Partial Pass 10/2/2020 (8:00 - 10:00) 10/2/2020 (AM) 10/02/2020
Progress.passed. Exterior deck rod connections. Ongoing inspections So partial pass.
Progress Inspection Partial Pass 10/6/2020 (8:00 - 10:00) 10/6/2020 (AM) 10/06/2020
South courtyard entry to 2 underground parking ramps. Ongoing work.
Progress Inspection Partial Pass 10/9/2020 (8:00 - 10:00) 10/9/2020 (AM) 10/13/2020
Progress.
Housewrap Inspection Partial Pass 10/26/2020
Progress - A. House wrap, And walk thru. Ongoing work
Progress Inspection Partial Pass 11/02/2020
Progress - ongoing work.
Progress Inspection Partial Pass 11/24/2020 (8:00 - 10:00) 11/24/2020 (AM) 11/24/2020
Final inspection of 3 Unit types - floor clearance, door width, self closing Unit entrance door width, toilet clearance range. Passed.
Progress Inspection Partial Pass 12/1/2020 (8:00 - 10:00) 12/1/2020 (AM) 12/01/2020
Progress - A. BUILDING FINAL ON INTERIOR UNIT ROOMS. PASSED. ONGOING INSPECTIONS. B. PARKING - UNDERGROUND PODIUM BUILDING. PASSED. ONGOING.
Progress Inspection Partial Pass 12/4/2020 (8:00 - 10:00) 12/4/2020 (AM) 12/04/2020
Fire Marshal inspection required . Please schedule Lance for NOX BOX LOCATIONS, AND WALK THRU.
Progress Inspection Passed 12/8/2020 (8:00 - 10:00) 12/8/2020 (AM) 12/08/2020
Progress Inspection Partial Pass 12/11/2020 (8:00 - 10:00) 12/11/2020 (AM) 12/11/2020
Elevator shafts, walk thru parking garage, common areas.
Progress Inspection Partial Pass 12/15/2020 (8:00 - 10:00) 12/15/2020 (AM) 12/15/2020
Parking ramp lighting levels, Landscape, address numbers, Underground Parking ramp stripping and exit signage, elevator final, NO2 and CO2 testing. Special inspection final summary reports.
Progress Inspection Partial Pass 12/18/2020 (8:00 - 10:00) 12/18/2020 (AM) 12/18/2020
Progress.
Progress Inspection Partial Pass 12/22/2020 (8:00 - 10:00) 12/22/2020 (AM) 12/22/2020
Progress - passed. Ongoing work.
Progress Inspection Partial Pass 12/29/2020 (8:00 - 10:00) 12/29/2020 (AM) 12/29/2020
Progress. A. Progress going very well.
Progress Inspection Partial Pass 1/5/2021 (8:00 - 10:00) 1/5/2021 (AM) 01/05/2021
Progress - Elevator lobby for underground basement and 4 floors above. Signage.
Progress Inspection Partial Pass 1/8/2021 (8:00 - 10:00) 1/8/2021 (AM) 01/08/2021
Progress on East building, passed, on going work.
Progress Inspection Partial Pass 1/12/2021 (8:00 - 10:00) 1/12/2021 (AM) 01/14/2021
Progress.
Progress Inspection Partial Pass 1/15/2021 (8:00 - 10:00) 1/15/2021 (AM) 01/15/2021
Need to start doing HVAC FINALS ON ALL LIVING UNITS.
Progress Inspection Not Ready 1/19/2021 (8:00 - 10:00) 1/19/2021 (AM) 01/20/2021
Building final. A. Pending trade finals and exterior tall light poles. B. Special inspection reports and structural engineer of record final report.
Building Final Inspection Partial Pass 1/20/2021 (12:30 - 2:30) 1/20/2021 (PM) 01/21/2021
Need HVAC FINAL; A. PENDING BALANCING REPORT. MISC OTHER BY MECHANICAL . B. NEED FIRE FINAL. C. NEED EXTERIOR ILLUMINATION TEST AT NIGHT TIME BY PLANNING.
Progress Inspection Partial Pass 1/22/2021 (8:00 - 10:00) 1/22/2021 (AM) 01/25/2021
Parking garage. A. Fire marshal Lance with Brian today. B. Underground parking ramp. 2 exits of all exits available from underground ramp are locked by private key fabs. Remove these 2 exit signs. Remaining Balance of exits available meet S-1 maximum travel distance, and distance between the available remaining exit signs. C. Add signage in the parking ramp side at these two entry-exits that are key fobbed. Signage indicates accessible areas of rescue having emergency call station.
Corrections:


Miscellaneous/Other
Comment Only
01/25/2021
Temporary occupancy - 30 days.

Miscellaneous/Other
Outstanding
01/25/2021
Temp occupancy 30 days - issued today.

Progress Inspection Partial Pass 1/26/2021 (8:00 - 10:00) 1/26/2021 (AM) 01/26/2021
Temporary Occupancy - until spring of 2021.
Corrections:


Miscellaneous/Other
Comment Only
01/26/2021
Temp occupancy - Issue until both buildings have sod and ground cover in the spring of 2021.

Progress Inspection Partial Pass 1/29/2021 (8:00 - 10:00) 1/29/2021 (AM) 01/29/2021
Progress - on temp occupancy.
Fire Inspection Final Partial Pass 1/20/2021 (12:30 - 2:30) 1/20/2021 (PM) 02/02/2021
Lighting Inspection Sign Partial Pass 02/09/2021
East building complete, surface parking lot complete, and street parking complete. West building remains.
Progress Inspection Passed 05/14/2021
Progress. Passed. Ongoing work.
Housewrap Inspection Passed 05/14/2021
Lighting Inspection Passed 5/17/2021 05/16/2021
Second half exterior PA III
Landscaping Inspection Passed 5/18/2021 05/18/2021
Building Final Inspection Issue CO 06/07/2021
Final - work completed. A. Trade finals passed
Fire Inspection Final Passed 06/07/2021
Per Lance Stanghor