PRBD201912792
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 12/17/2019 (8:00 - 10:00) | 12/17/2019 (AM) | 12/17/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/17/2019
Walls oat 3rd floor of phase 1.... approved pending pictures of the two plumbing through penetrations being firestopped with an intumescent firestop. Contractor to send pictures to inspector.
|
||||
Framing Inspection | Partial Pass | 1/10/2020 (8:00 - 10:00) | 1/10/2020 (AM) | 01/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/10/2020
Phase 1 above ceiling approved
|
||||
Fire Inspection Final | Partial Pass | 2/6/2020 (12:30 - 2:30) | 2/6/2020 (PM) | 01/28/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/28/2020
Phase I only.
|
||||
Building Final Inspection | Partial Pass | 2/6/2020 (12:30 - 2:30) | 2/6/2020 (PM) | 02/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/06/2020
Phase 1 approved for setup and and tenant occupancy. Exit signs might have to be adjusted with this phase , but will need to be viewed with phase 4 buildout.
|
||||
Framing Inspection | Partial Pass | 2/27/2020 (8:00 - 10:00) | 2/27/2020 (AM) | 02/27/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/27/2020
Bathrooms on 3rd floor above ceiling... approved
Progress of phase 2, 5th floor ... framing approved, no electrical in the framed walls. Remaining portion of this phase is cosmetic finishes... approved to complete this phase. Call for inspections as needed.
|
||||
Fire Inspection Final | Passed w/ Conditions | 3/26/2020 (10:00 - 12:00) | 3/26/2020 (AM) | 03/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/26/2020
Approved pending building inspector final
|
||||
Building Final Inspection | Partial Pass | 3/26/2020 (10:00 - 12:00) | 3/26/2020 (AM) | 03/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/26/2020
Phase 2 east side of 5th floor approved for occupancy pending electrical inspection final.
|
||||
Framing Inspection | Partial Pass | 4/20/2020 (8:00 - 10:00) | 4/20/2020 (AM) | 04/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/20/2020
5th floor office area framing... approved
|
||||
Building Final Inspection | Partial Pass | 5/20/2020 (8:00 - 10:00) | 5/20/2020 (AM) | 05/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
05/20/2020
Phase 3 (5th floor) approved for final .
|
||||
Above Ceiling Inspection | Passed w/ Conditions | 6/30/2020 (10:00 - 12:00) | 6/30/2020 (AM) | 06/30/2020 |
Corrections:
Miscellaneous/Other
Outstanding
06/30/2020
Above ceiling...
1) Cut pipe that penetrates trash room shaft to be firestopped at each end.
2) Entry wall above ceiling to have gypsum patched back in where missing to maintain the 1hour wall construction... wall to also be filled in to the concrete beam.
|
||||
Miscellaneous/Other
Comment Only
06/30/2020
Above ceiling approved to pad out see outstanding comments for corrections, and to be viewed at final inspection.
|
||||
Fire Inspection Final | Partial Pass | 7/13/2020 (7:00 - 8:00) | 7/13/2020 (AM) | 07/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/13/2020
Approved for Phase IV
|
||||
Building Final Inspection | Partial Pass | 7/13/2020 (7:00 - 8:00) | 7/13/2020 (AM) | 07/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
07/13/2020
3rd floor, Phase 4 of project... approved for final.
|
||||
Framing Inspection | Passed | 8/7/2020 (8:00 - 10:00) | 8/7/2020 (AM) | 08/07/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/07/2020
Wall framing approved and pending electrical inspection prior to covering.
|
||||
Progress Inspection | Passed | 8/19/2020 (8:00 - 10:00) | 8/19/2020 (AM) | 08/19/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2020
Ceiling framing and above ceiling... approved
|
||||
Fire Inspection Final | Passed | 8/27/2020 (7:00 - 8:00) | 8/27/2020 (AM) | 08/27/2020 |
Building Final Inspection | Passed | 8/27/2020 (8:00 - 10:00) | 8/27/2020 (AM) | 08/27/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/27/2020
Final for this project permit approved
|
||||
Miscellaneous/Other
Comment Only
08/27/2020
Final for this project permit approved
|