PRBD201914326
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Framing Inspection | Partial Pass | 1/24/2020 (10:00 - 12:00) | 1/24/2020 (AM) | 01/24/2020 |
New Door framed at end of existing hallway from main desk. A. Correction - Provide 12 inch on the push side, move doorway framing. B. Glass - floor to ceiling glass wall framing not completed. Must provide kicker support at ceiling tile area for ALL tempered glass wall floor to ceiling. | ||||
Framing Inspection | Passed | 04/01/2020 | ||
Framing correction of 1 door for 12 inch push/ 18 inch pull. | ||||
Building Final Inspection | Passed | 04/01/2020 |