Permit Application Status

PRBD201914504


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD201914504
Building
Finaled
SKYWATER TECH FOUNDRY INC
Addition
Not Required
New 2 story steel precast addition - core & shell only.
12/02/2019
01/13/2020
04/07/2021

Locations

Permits

Permit Number: PRBD201914504

Building
Finaled
01/13/2020
04/07/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 3/3/2020 (10:00 - 12:00) 3/3/2020 (AM) 03/03/2020
Corrections:


Miscellaneous/Other
Outstanding
03/03/2020
Slab on metal deck level one .. section is in progress of rebar placement, designer and special inspection is also looking at this and upon their approval, concrete placement can take place.

Footing Inspection Partial Pass 3/4/2020 (10:00 - 12:00) 3/4/2020 (AM) 03/04/2020
Corrections:


Miscellaneous/Other
Comment Only
03/04/2020
Rebar for 5 ft. High wall.. approved

Footing Inspection Not Ready 3/5/2020 (10:00 - 12:00) 3/5/2020 (AM) 03/05/2020
Corrections:


Miscellaneous/Other
Comment Only
03/05/2020
Not ready for inspection

Framing Inspection Partial Pass 3/9/2020 (10:00 - 12:00) 3/9/2020 (AM) 03/09/2020
Corrections:


Miscellaneous/Other
Comment Only
03/09/2020
Footings for area well on S.W. end... approved.

Framing Inspection Partial Pass 3/10/2020 (10:00 - 12:00) 3/10/2020 (AM) 03/10/2020
Corrections:


Miscellaneous/Other
Comment Only
03/10/2020
Viewed waffle slab progress, rebar is being installed as per the plan design. Imbeds to go in after all bar is in, and then all bar will be chaired to maintain clearance to forms.

Framing Inspection Partial Pass 3/11/2020 (10:00 - 12:00) 3/11/2020 (AM) 03/11/2020
Corrections:


Miscellaneous/Other
Comment Only
03/11/2020
Progress of waffle deck: some rebar still needed at East beam and in the SW locations where it is incomplete. Imbeds are being installed and chairing of rebar to take place when all rebar and imbeds are in place. Metal decks: rebar is in process of installation, some small detail work is yet to be done. Special inspection and engineer to view as well prior to concrete placement. Special inspection reports to be submitted to city for all work on this project that they look at... submit reports by email to inspector.

Framing Inspection Partial Pass 3/12/2020 (10:00 - 12:00) 3/12/2020 (AM) 03/13/2020
Corrections:


Miscellaneous/Other
Comment Only
03/13/2020
Rebar approved for Waffle slab, Metal decks. And wall at area well. Approved for concrete placement

Progress Inspection Partial Pass 03/16/2020
Corrections:


Miscellaneous/Other
Comment Only
03/16/2020
Two sections of slab on grade with under slab poly and rebar located at the west end of building. Approved for concrete placement

Framing Inspection Partial Pass 04/30/2020
Corrections:


Miscellaneous/Other
Comment Only
04/30/2020
Partial wall framing interior... framing , spacer bars, and sheet metal covering, and fasteners... approved Firestops at piping at building separation wall... approved

Progress Inspection Partial Pass 08/13/2020
Corrections:


Miscellaneous/Other
Comment Only
08/13/2020
Door rating at room 243 (electrical room) is 90 minutes and verified by the embossed stamp that will be covered with a continuous hinge.

Building Final Inspection Partial Pass 8/28/2020 (10:00 - 12:00) 8/28/2020 (AM) 08/28/2020
Corrections:


Miscellaneous/Other
Carried Forward
08/28/2020
Corrections to be completed for final... 1) penetrations in rated walls to be firestopped on both sides of walls. 2) floor penetrations to be firestopped 3) draftstopping where floors meet walls to be completed, 4) as per Mn. Building Code 2015 section 704.9... fire protected columns that are subject to impact damage need to have a protective covering around them for a height of 5ft. Minimum to protect the fireproofing. 5) complete exterior work of building and landscaping.

Miscellaneous/Other
Comment Only
08/28/2020
See outstanding comments for corrections that are to be viewed prior to or at final. EM lighting, exiting, and signage inspected and approved. Temp occupancy is approved

Fire Inspection Final Partial Pass 8/28/2020 (10:00 - 12:00) 8/28/2020 (AM) 09/01/2020
Building Final Inspection Passed 10/9/2020 (8:00 - 10:00) 10/9/2020 (AM) 10/09/2020
Corrections:


Miscellaneous/Other
Resolved
10/09/2020
Corrections to be completed for final... 1) penetrations in rated walls to be firestopped on both sides of walls. 2) floor penetrations to be firestopped 3) draftstopping where floors meet walls to be completed, 4) as per Mn. Building Code 2015 section 704.9... fire protected columns that are subject to impact damage need to have a protective covering around them for a height of 5ft. Minimum to protect the fireproofing. 5) complete exterior work of building and landscaping.

Miscellaneous/Other
Comment Only
10/09/2020
All corrections are completed. Parking accessibility is approved, and bike rack installed and landscaping completed all soil retainage systems have been pulled.

Fire Inspection Final Partial Pass 10/9/2020 (8:00 - 10:00) 10/9/2020 (AM) 10/09/2020
Miscellaneous/Other Temp C/O approved. Final pending installation on emergency responder radio coverage equipment installation.