PRBD201914623
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Framing Inspection | Passed | 12/31/2019 (8:00 - 10:00) | 12/31/2019 (AM) | 12/31/2019 |
Corrections:
Miscellaneous/Other
Comment Only
12/31/2019
Wall Framing approved.
|
||||
Fire Inspection Final | Passed | 1/30/2020 (10:00 - 12:00) | 1/30/2020 (AM) | 01/30/2020 |
Building Final Inspection | Partial Pass | 1/30/2020 (10:00 - 12:00) | 1/30/2020 (AM) | 01/30/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/30/2020
Approved for a temp to set up and move in pending the electrical final and verification of rated poke through electrical boxes at openings in floor for cubicles.
|