PRBD201915119
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Progress Inspection | Partial Pass | 04/23/2020 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
04/23/2020
Progress of project... tilt up wall panels installed and braced, steel is being set and is ongoing.
|
||||
| Progress Inspection | Partial Pass | 05/12/2020 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
05/12/2020
Progress of this project is now ongoing, work will continue with a shutdown. The concrete panels are in place along with the structural steel. Other trades are gearing up for their scope of work with this building.
|
||||
| Framing Inspection | Partial Pass | 05/29/2020 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
05/29/2020
Exterior walls at 2nd level on south, west, and east sides are built as per plan design.
|
||||
| Framing Inspection | Partial Pass | 6/2/2020 (12:30 - 2:30) | 6/2/2020 (PM) | 06/02/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/02/2020
Metal stud wall framing on east side of building on 2nd level... approved
Rebar for topping slab at southeast section laid out as per plan detail s6/602
|
||||
| Framing Inspection | Partial Pass | 6/9/2020 (12:30 - 2:30) | 6/9/2020 (PM) | 06/09/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/09/2020
Outside wall framing on 2nd level at east side building inset/ jog.... approved
|
||||
| Framing Inspection | Partial Pass | 6/16/2020 (12:30 - 2:30) | 6/16/2020 (PM) | 06/16/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/16/2020
Framing at exterior north face of building... approved
Lower exterior framing at east side of building... approved
Ok to cover.
|
||||
| Framing Inspection | Partial Pass | 6/29/2020 (8:00 - 10:00) | 6/29/2020 (AM) | 06/29/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/29/2020
Lower exterior framing of wall/soffit detail on south side of building, approved as per drawing detail.
|
||||
| Progress Inspection | Partial Pass | 7/16/2020 (8:00 - 10:00) | 7/16/2020 (AM) | 07/16/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/16/2020
2nd level at NE corner wall section, insulation and poly approved.
|
||||
| Framing Inspection | Partial Pass | 7/28/2020 (12:30 - 2:30) | 7/28/2020 (PM) | 07/28/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/28/2020
Insulation and poly at sections of exterior walls on south, east, and west sides that are in place ... approved to cover.
|
||||
| Framing Inspection | Partial Pass | 8/6/2020 (8:00 - 10:00) | 8/6/2020 (AM) | 08/06/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/06/2020
2nd floor all framing north of stairway, and firestops...approved
Housewrap at all framed wall sections... approved
Underslab poly for concrete placement at main level is ongoing... approved for sections ready for concrete placement.
|
||||
| Framing Inspection | Partial Pass | 8/27/2020 (8:00 - 10:00) | 8/27/2020 (AM) | 08/27/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/27/2020
1st floor Wes side of building framing including the elevator shaft walls.... approved
|
||||
| Framing Inspection | Passed | 9/15/2020 (7:00 - 8:00) | 9/15/2020 (AM) | 09/15/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/15/2020
Framing for bathrooms... approved
spray foam insulation at front overhang is being done in sections to reach all areas.... approved to complete remaining spray foam.
|
||||
| Progress Inspection | Partial Pass | 11/30/2020 (12:30 - 2:30) | 09/29/2020 | |
|
Corrections:
Miscellaneous/Other
Comment Only
09/29/2020
Questions with builder for temp heat needed with front area of work. Temp heat would require a permit and inspection by mechanical inspector. If using propane to heat the area, a tank permit is needed and to be inspected by fire inspector.
|
||||
| Progress Inspection | Partial Pass | 11/30/2020 (12:30 - 2:30) | 11/30/2020 (PM) | 11/30/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/30/2020
Above ceiling and framing of first level areas ... approved.
Above ceiling and framing of second level, in sale mgr, sale, and general office...ceiling supports cannot hang off the ducting or ducting supports. Install separate supports to hanga d support ceiling independently.
Reinspection of these areas at next inspection.
|
||||
| Progress Inspection | Passed | 12/9/2020 (12:30 - 2:30) | 12/9/2020 (PM) | 12/09/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/09/2020
Ceiling supports in areas called out at last inspection were taken off the ducting and it’s supports and attached independently.... approved and ok to cover.
|
||||
| Fire Inspection Final | Passed | 2/19/2021 (8:00 - 10:00) | 2/19/2021 (AM) | 02/19/2021 |
| Building Final Inspection | Partial Pass | 2/19/2021 (8:00 - 10:00) | 2/19/2021 (AM) | 02/19/2021 |
|
Corrections:
Miscellaneous/Other
Carried Forward
02/19/2021
1) Verify EM lighting in all building at 2nd floor and first floor common use areas.
2) complete guard infill at main stair
3) install exit sign to exit route at 2nd level stairs.
4) conference room needs exit signs over doors if occupancy load is over 49. Occupancy signage will also be needed.
5) firestop penetrations in data room at floor.
|
||||
|
Miscellaneous/Other
Comment Only
02/19/2021
EM lighting verified at some areas of first floor. See outstanding comments for corrections to be completed for the final inspection and full occupancy.
Approved for temp occupancy at this time.
|
||||
| Building Final Inspection | Partial Pass | 03/11/2021 | ||
|
Corrections:
Miscellaneous/Other
Resolved
03/11/2021
1) Verify EM lighting in all building at 2nd floor and first floor common use areas.
2) complete guard infill at main stair
3) install exit sign to exit route at 2nd level stairs.
4) conference room needs exit signs over doors if occupancy load is over 49. Occupancy signage will also be needed.
5) firestop penetrations in data room at floor.
|
||||
|
Miscellaneous/Other
Comment Only
03/11/2021
The items from the outstanding list of corrections are completed. Building is able to be occupied and public access allowed.
This permit will still remain open for the next portion of work to be completed and inspected.
|
||||
| Lighting Inspection | Passed | 4/5/2021 | 03/31/2021 | |
| Building Final Inspection | Issue CO | 10/05/2021 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
10/05/2021
Inspections and work pertaining to this permit completed.
Final for this permit approved.
|
||||