Summary

PRBD201915127
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
DEMOLITION SCOPE INCLUDES REMOVAL OF (1) EXISTING TENANT BUILD OUTS AND A PORTION OF AN EXISTING MALL CORRIDOR WITHIN MALL OF AMERICA, INCLUDING REMOVAL OF EXISTING STOREFRONT CONSTRUCTION, AND FLOOR SLAB CUT OUTS FOR THE RELOCATION OF THE EXISTING ESCALATORS AND NEW ELEVATORS. 5160 Center Court NEW CONSTRUCTION SCOPE INCLUDES NEW DEMISING WALLS FOR NEW CORRIDOR, MODIFICATIONS TO THE STRUCTURE FOR RELOCATION OF EXISTING ESCALATORS AND NEW FREIGHT AND PASSENGER ELEVATOR AS REQUIRED INCLUDING NEW ELEVATOR MACHINE ROOM. SEE ENGINEERING DRAWINGS FOR SCOPE OF MECHANICAL, ELECTRICAL, PLUMBING, AND STRUCTURAL WORK. OCCUPANT LOAD CALCULATIONS, EXITING REQUIREMENTS, AND MINIMUM NUMBER OF TOILET FIXTURES TO BE DETERMINED UNDER FINAL TENANT IMPROVEMENT DOCUMENTS UNDER SEPARATE PERMIT. PER THIS SUBMITTAL, (2) EXITS ARE PROVIDED FROM "SHELL SPACE" (NON-OCCUPIED / UNCONDITIONED SPACE). SCOPE OF WORK DOES NOT INCLUDE INTERIOR TENANT IMPROVEMENTS. SCOPE OF WORK DOES NOT CHANGE THE EXISTING CONSTRUCTION TYPE OR FIRE RATINGS. SCOPE OF WORK DOES NOT MODIFY THE EXISTING BUILDING EXTERIOR. SCOPE OF WORK DOES NOT INCLUDE SITE WORK. SCOPE OF WORK DOES NOT INCLUDE NEW OCCUPANCY. UPON COMPLETION OF THIS PERMITTED WORK, THE SPACE WILL BE A GRAY SHELL. FUTURE TENANT IMPROVEMENT WILL BE UNDER A SEPARATE PERMIT.
12/19/2019
01/22/2020
11/11/2020
05/15/2020

Locations

Property
0102724310017

Address
5160 CENTER CT, BLOOMINGTON, MN 55425

0102724310017
Mall of America, Bloomington, MN 55425

Permits

Permit Number: PRBD201915127

Building
Finaled
01/22/2020
11/11/2020

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Partial Pass 1/23/2020 (8:00 - 10:00) 1/23/2020 (AM) 01/23/2020
Corrections:


Miscellaneous/Other
Comment Only
01/23/2020
Phase 1 M&M...formed slab on grade with rebar about 11’ around perimeter in the Nickelodeon Universe.... approved for concrete placement.

Footing Inspection Partial Pass 1/29/2020 (12:30 - 2:30) 1/29/2020 (PM) 01/29/2020
Corrections:


Miscellaneous/Other
Carried Forward
01/29/2020
Escalator pit slab and wall rebar located between grids P and V. Approved

Footing Inspection Partial Pass 1/31/2020 (2:30 - 3:30) 1/31/2020 (PM) 01/31/2020
Corrections:


Miscellaneous/Other
Resolved
01/31/2020
Escalator pit slab and wall rebar located between grids P and V. Approved

Miscellaneous/Other
Comment Only
01/31/2020
Freight elevator between grids G and J ... base footing of pit approved. Column pad on grid V... approved

Footing Inspection Partial Pass 2/14/2020 (12:30 - 2:30) 2/14/2020 (PM) 02/14/2020
Corrections:


Miscellaneous/Other
Comment Only
02/14/2020
Glass elevator pad footing with double mat rebar and piers all tied in. Adjacent pad and pier also with this footing pour. Approved for concrete placement.

Footing Inspection Passed 2/18/2020 (12:30 - 2:30) 2/18/2020 (PM) 02/18/2020
Corrections:


Miscellaneous/Other
Comment Only
02/18/2020
Foundation walls and piers at glass elevator. Approved for concrete placement

Framing Inspection Partial Pass 2/26/2020 (10:00 - 12:00) 2/26/2020 (AM) 02/26/2020
Corrections:


Miscellaneous/Other
Comment Only
02/26/2020
2 Escalator pits and floor infill, and freight elevator infill of floor and at bottom of pit... approved Framing of elevator room and 3rd floor entry... approved

Framing Inspection Partial Pass 3/9/2020 (12:30 - 2:30) 3/9/2020 (PM) 03/09/2020
Corrections:


Miscellaneous/Other
Comment Only
03/09/2020
3 walls of Shaft wall framing at first elevator ... approved

Framing Inspection Partial Pass 3/10/2020 (10:00 - 12:00) 3/10/2020 (AM) 03/10/2020
Corrections:


Miscellaneous/Other
Comment Only
03/10/2020
Progress installation of the layers of gypsum installed to fist floor elevator shaft. Approved and ok to continue.

Framing Inspection Partial Pass 3/11/2020 (10:00 - 12:00) 3/11/2020 (AM) 03/11/2020
Corrections:


Miscellaneous/Other
Comment Only
03/11/2020
Shaft wall framing of 3 sides of elevator shaft at 2nd level .... approved

Framing Inspection Partial Pass 3/12/2020 (10:00 - 12:00) 3/12/2020 (AM) 03/12/2020
Corrections:


Miscellaneous/Other
Comment Only
03/12/2020
Firesafeing of elevator shaft to floor deck and layering of the 3 layers gypsum to outer shaft on second floor ... approved

Framing Inspection Partial Pass 3/17/2020 (Morning) 3/17/2020 (AM) 03/17/2020
Corrections:


Miscellaneous/Other
Comment Only
03/17/2020
Framing of cooridor wall and bulkhead extension... approved. Ok to cover wall, bulkhead extension needs fire sprinkler inspection prior to covering.

Concrete Slab Inspection Partial Pass 03/26/2020
Corrections:


Miscellaneous/Other
Comment Only
03/26/2020
Interior floor slab infills... approved Firestops at inside of new cooridor ... approved

Concrete Slab Inspection Partial Pass 04/03/2020
Corrections:


Miscellaneous/Other
Comment Only
04/03/2020
Viewed stair and ramp forms for the concrete placement at 1st level. Rise and run, and ramp rise approved. Approved for concrete placement

Framing Inspection Partial Pass 04/03/2020
Corrections:


Miscellaneous/Other
Comment Only
04/03/2020
Viewed elevator front shaft wall framing at levels 1&2... approved to cover with outer gypsum layers.

Framing Inspection Partial Pass 05/07/2020
Corrections:


Miscellaneous/Other
Comment Only
05/07/2020
New cooridor is 2 layered gypsum covered at the inside of cooridor to coincide with a 1hour rated wall listing since access to Build A Bear store could not be done at this time. This completes the framing for this permit she’ll buildout.

Building Final Inspection Passed 5/15/2020 (PM) 05/15/2020
Corrections:


Miscellaneous/Other
Comment Only
05/15/2020
Final for this permit and the scope of work ...approved. Contractor has the next phase of this project, the elevator and escalators will be finished with that permit buildout and state sign off for all elevators and escalators will be needed at that time. Fireproofing to be fully completed and / or will be required to be completed with the buildout of the next phase of this project.

Fire Inspection Final Passed 05/15/2020
Corrections:


Miscellaneous/Other
Comment Only
05/15/2020
Approved to final this phase of project, the buildout is still under full sprinkler coverage. New buildout will require a new sprinkler permit and inspections. Any plans and work to be verified by the fire inspector.