PRBD201915127
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 1/23/2020 (8:00 - 10:00) | 1/23/2020 (AM) | 01/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
01/23/2020
Phase 1 M&M...formed slab on grade with rebar about 11’ around perimeter in the Nickelodeon Universe.... approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 1/29/2020 (12:30 - 2:30) | 1/29/2020 (PM) | 01/29/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
01/29/2020
Escalator pit slab and wall rebar located between grids P and V. Approved
|
||||
Footing Inspection | Partial Pass | 1/31/2020 (2:30 - 3:30) | 1/31/2020 (PM) | 01/31/2020 |
Corrections:
Miscellaneous/Other
Resolved
01/31/2020
Escalator pit slab and wall rebar located between grids P and V. Approved
|
||||
Miscellaneous/Other
Comment Only
01/31/2020
Freight elevator between grids G and J ... base footing of pit approved.
Column pad on grid V... approved
|
||||
Footing Inspection | Partial Pass | 2/14/2020 (12:30 - 2:30) | 2/14/2020 (PM) | 02/14/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/14/2020
Glass elevator pad footing with double mat rebar and piers all tied in. Adjacent pad and pier also with this footing pour. Approved for concrete placement.
|
||||
Footing Inspection | Passed | 2/18/2020 (12:30 - 2:30) | 2/18/2020 (PM) | 02/18/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/18/2020
Foundation walls and piers at glass elevator. Approved for concrete placement
|
||||
Framing Inspection | Partial Pass | 2/26/2020 (10:00 - 12:00) | 2/26/2020 (AM) | 02/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
02/26/2020
2 Escalator pits and floor infill, and freight elevator infill of floor and at bottom of pit... approved
Framing of elevator room and 3rd floor entry... approved
|
||||
Framing Inspection | Partial Pass | 3/9/2020 (12:30 - 2:30) | 3/9/2020 (PM) | 03/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/09/2020
3 walls of Shaft wall framing at first elevator ... approved
|
||||
Framing Inspection | Partial Pass | 3/10/2020 (10:00 - 12:00) | 3/10/2020 (AM) | 03/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/10/2020
Progress installation of the layers of gypsum installed to fist floor elevator shaft. Approved and ok to continue.
|
||||
Framing Inspection | Partial Pass | 3/11/2020 (10:00 - 12:00) | 3/11/2020 (AM) | 03/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/11/2020
Shaft wall framing of 3 sides of elevator shaft at 2nd level .... approved
|
||||
Framing Inspection | Partial Pass | 3/12/2020 (10:00 - 12:00) | 3/12/2020 (AM) | 03/12/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2020
Firesafeing of elevator shaft to floor deck and layering of the 3 layers gypsum to outer shaft on second floor ... approved
|
||||
Framing Inspection | Partial Pass | 3/17/2020 (Morning) | 3/17/2020 (AM) | 03/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/17/2020
Framing of cooridor wall and bulkhead extension... approved. Ok to cover wall, bulkhead extension needs fire sprinkler inspection prior to covering.
|
||||
Concrete Slab Inspection | Partial Pass | 03/26/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/26/2020
Interior floor slab infills... approved
Firestops at inside of new cooridor ... approved
|
||||
Concrete Slab Inspection | Partial Pass | 04/03/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/03/2020
Viewed stair and ramp forms for the concrete placement at 1st level. Rise and run, and ramp rise approved. Approved for concrete placement
|
||||
Framing Inspection | Partial Pass | 04/03/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/03/2020
Viewed elevator front shaft wall framing at levels 1&2... approved to cover with outer gypsum layers.
|
||||
Framing Inspection | Partial Pass | 05/07/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/07/2020
New cooridor is 2 layered gypsum covered at the inside of cooridor to coincide with a 1hour rated wall listing since access to Build A Bear store could not be done at this time. This completes the framing for this permit she’ll buildout.
|
||||
Building Final Inspection | Passed | 5/15/2020 (PM) | 05/15/2020 | |
Corrections:
Miscellaneous/Other
Comment Only
05/15/2020
Final for this permit and the scope of work ...approved.
Contractor has the next phase of this project, the elevator and escalators will be finished with that permit buildout and state sign off for all elevators and escalators will be needed at that time. Fireproofing to be fully completed and / or will be required to be completed with the buildout of the next phase of this project.
|
||||
Fire Inspection Final | Passed | 05/15/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/15/2020
Approved to final this phase of project, the buildout is still under full sprinkler coverage. New buildout will require a new sprinkler permit and inspections. Any plans and work to be verified by the fire inspector.
|