PRBD202000075
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 3/9/2020 (10:00 - 12:00) | 3/9/2020 (AM) | 03/09/2020 |
Rescheduled as electrical not able to be scheduled. jsmidt 03/05/2020 8:39 AM | ||||
Corrections:
Miscellaneous/Other
Comment Only
03/09/2020
Footings for area well on S.W. end ... approved
|
||||
Framing Inspection | Partial Pass | 03/09/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/09/2020
Wall framing and soffit framing... contractor did not take into account deflection at walls that connect to the soffits, they take on the responsibility of any issues that may arise due to this framing method used. Approved to cover
|
||||
Miscellaneous/Other
Outstanding
03/09/2020
Firestop at the low voltage wiring that penetrates through the floor inside the chase will have to be installed and viewed from the parking area below.
The narrow soffit at the front of space is supported off the duct supports and is to be resupported independent of soffit... this needs to be checked at next inspection , lift ceiling tiles for inspector to verify.
|
||||
Framing Inspection | Passed | 4/21/2020 (2:30 - 3:30) | 4/21/2020 (PM) | 04/21/2020 |
Phase 2 of 2. A. Framing-passed. B. Need all trade rough in inspections passed, for walls and above ceiling , prior to covering. B. Upon final inspection, must inspect floor penetrations from parking ramp below, for fire caulk, for electrical non rated floor box, and low voltage chase. Contractor on site today. Permit Card on site today. | ||||
Building Final Inspection | Passed | 5/13/2020 (8:00 - 10:00) | 5/13/2020 (AM) | 05/13/2020 |
Fire Inspection Final | Passed | 5/13/2020 (8:00 - 10:00) | 5/13/2020 (AM) | 05/13/2020 |