PRBD202001372
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | 8/3/2020 (8:00 - 10:00) | ||
Framing Inspection | Passed | 4/6/2020 (12:30 - 2:30) | 4/6/2020 (PM) | 04/06/2020 |
Corrections:
Miscellaneous/Other
Comment Only
04/06/2020
Wafer pack room and gown room wall framing ... approved
|
||||
Building Final Inspection | Failed | 6/26/2020 (8:00 - 10:00) | 6/26/2020 (AM) | 06/26/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
06/26/2020
Chemical storage room , no framing inspection for building of shaft.
1) Piping being run through the cored holes needs to be firestopped.
2) provide special inspection report for the newly built block walls.
|
||||
Fire Inspection Final | Not Ready | 6/26/2020 (8:00 - 10:00) | 6/26/2020 (AM) | 06/29/2020 |
Progress Inspection | Passed | 06/30/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/30/2020
CMU walls are laid in stack bond, with horizontal reinforcing installed at 16” o.c.
Horizontal bond beam with 2 #5 rebar installed at top of wall.
|
||||
Building Final Inspection | Passed w/ Conditions | 8/3/2020 (8:00 - 10:00) | 8/3/2020 (AM) | 08/03/2020 |
Corrections:
Miscellaneous/Other
Resolved
08/03/2020
Chemical storage room , no framing inspection for building of shaft.
1) Piping being run through the cored holes needs to be firestopped.
2) provide special inspection report for the newly built block walls.
|
||||
Miscellaneous/Other
Comment Only
08/03/2020
Final approved for this room, sprinkler inspection and final is needed and to be completed.
|