PRBD202001540
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Passed | 3/13/2020 (8:00 - 10:00) | 3/13/2020 (AM) | 03/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
03/13/2020
Cashwrap approved. Store setup approved
|
||||
Building Final Inspection | Partial Pass | 03/13/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/13/2020
Approved to open the mango portion of sales... pending EH , and fire approval for full final.
|
||||
Fire Inspection Final | Failed | 3/16/2020 (8:00 - 10:00) | 3/16/2020 (AM) | 03/17/2020 |
Building Final Inspection | Passed w/ Conditions | 8/20/2020 (10:00 - 12:00) | 8/20/2020 (AM) | 08/20/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/20/2020
Final approved with condition to set up final fire inspection with the inspector for this project to address the nitrogen tanks onsite in space.
|
||||
Fire Inspection Final | Partial Pass | 8/20/2020 (10:00 - 12:00) | 8/20/2020 (AM) | 08/21/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
08/21/2020
Must set up Kris to look at tanks. Building to OK TCO.
|
||||
Fire Inspection Final | Not Ready | 9/14/2020 (12:30 - 2:30) | 9/14/2020 (PM) | 09/21/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
09/21/2020
Must set up Kris to look at tanks. Building to OK TCO.
|
||||
Fire Inspection Final | Passed | 10/19/2020 | ||
Corrections:
Miscellaneous/Other
Outstanding
09/21/2020
Must set up Kris to look at tanks. Building to OK TCO.
|