Permit Application Status

PRBD202002786


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202002786
Building
Expired
UNITED LAND LLC
New
Not Required
Not Required
Not Required
133 Unit Senior Living - The Pointe Bloomington
03/23/2020
12/29/2020
11/14/2022
07/22/2022

Locations

Permits

Permit Number: PRBD202002786

Building
Expired
12/29/2020
11/14/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Passed 3/9/2021 (12:30 - 2:30) 3/9/2021 (PM) 03/09/2021
Corrections:


Miscellaneous/Other
Comment Only
03/09/2021
Last progress inspection of rated shaft and stairwells approved. First progress inspection of insulated parapits approved.

Progress Inspection Passed 3/12/2021 (12:30 - 2:30) 3/12/2021 (PM) 03/10/2021
Corrections:


Miscellaneous/Other
Comment Only
03/10/2021
Insulated core filling out all precast panel ends complete.

Progress Inspection Passed 3/16/2021 (8:00 - 10:00) 3/16/2021 (AM) 03/16/2021
Corrections:


Miscellaneous/Other
Comment Only
03/16/2021
Progress inspection of parapet insulation approved. Progress inspection of exterior strap anchors approved. First progress inspection of roofing with tapered insulation approved.

Progress Inspection Passed 3/18/2021 (8:00 - 10:00) 3/18/2021 (AM) 03/18/2021
Corrections:


Miscellaneous/Other
Comment Only
03/18/2021
Progress inspection of roof and parapet OK.

Progress Inspection Passed 4/1/2021 (8:00 - 10:00) 4/1/2021 (AM) 04/01/2021
Corrections:


Miscellaneous/Other
Comment Only
04/01/2021
Progress inspection on roof approved. Progress inspection of pre-rock in shower areas on fourth and fifth floor approved.

Framing Inspection Partial Pass 04/06/2021
Corrections:


Miscellaneous/Other
Comment Only
04/06/2021
Progress inspection of framing, reviewed framing and fire caulking approval schedule for next several weeks. Reviewed rated shaft enclosures, approved.

Progress Inspection Passed 4/12/2021 (8:00 - 10:00) 4/12/2021 (AM) 04/12/2021
Corrections:


Miscellaneous/Other
Comment Only
04/12/2021
Insulation inspection in room number 530, mock up room, approved.

Progress Inspection Passed 4/13/2021 (8:00 - 10:00) 4/13/2021 (AM) 04/13/2021
Corrections:


Miscellaneous/Other
Comment Only
04/13/2021
Insulation in units of phase A, fifth floor approved. Observation of shear wall in unit 329 shows need for maintaining flush nail head depth.

Progress Inspection Passed 4/14/2021 (10:00 - 12:00) 4/14/2021 (AM) 04/14/2021
Corrections:


Miscellaneous/Other
Comment Only
04/14/2021
Installation of exterior walls in east stairwell, all floors, approve. Framing, fire caulking, insulation on all floors of east elevator shaft approved.

Progress Inspection Passed 4/15/2021 (10:00 - 12:00) 4/15/2021 (AM) 04/15/2021
Corrections:


Miscellaneous/Other
Comment Only
04/15/2021
Framing and fire caulking on fifth floor, B section approved. Sheet rock on east side elevator shaft, all floors, approved. Insulation on interior walls of east stairwell, all levels, approved.

Progress Inspection Passed w/ Conditions 4/19/2021 (10:00 - 12:00) 4/19/2021 (AM) 04/19/2021
Corrections:


Miscellaneous/Other
Outstanding
04/19/2021
Unit number 519 missing foam insulation above ceiling in bedroom. All other units on fifth floor, B section, approved.

Progress Inspection Passed 4/21/2021 (10:00 - 12:00) 4/21/2021 (AM) 04/21/2021
Corrections:


Miscellaneous/Other
Comment Only
04/21/2021
Framing and fire caulking on fourth floor, section A, approved.

Progress Inspection Passed 4/26/2021 (10:00 - 12:00) 4/26/2021 (AM) 04/26/2021
Corrections:


Miscellaneous/Other
Comment Only
04/26/2021
Insulation on fourth floor, phase A, approved. Framing and fire caulking on fourth floor, phase B, approved.

Progress Inspection Passed 4/28/2021 (10:00 - 12:00) 4/28/2021 (AM) 04/28/2021
Corrections:


Miscellaneous/Other
Comment Only
04/28/2021
Field investigation with contractor to confirm steel columns prepared for intumescent paint.

Progress Inspection Passed 4/29/2021 (10:00 - 12:00) 4/29/2021 (AM) 04/29/2021
Corrections:


Miscellaneous/Other
Comment Only
04/29/2021
Insulation on fourth floor, section B, approved.

Progress Inspection Passed 5/3/2021 (10:00 - 12:00) 5/3/2021 (AM) 05/03/2021
Corrections:


Miscellaneous/Other
Comment Only
05/03/2021
Framing and fire caulking on third floor, section A, approved.

Progress Inspection Partial Pass 5/5/2021 (10:00 - 12:00) 5/5/2021 (AM) 05/05/2021
Corrections:


Miscellaneous/Other
Comment Only
05/05/2021
Progress inspection of fire caulking and insulation on third floor, A and B sections approved. Remaining units to be inspected Thursday.

Progress Inspection Passed 5/6/2021 (10:00 - 12:00) 5/6/2021 (AM) 05/05/2021
Corrections:


Miscellaneous/Other
Comment Only
05/05/2021
Insulation on third floor, section A, approved. Framing and fire caulking on third floor, section B, approved.

Progress Inspection Passed 5/7/2021 (10:00 - 12:00) 5/7/2021 (AM) 05/07/2021
Corrections:


Miscellaneous/Other
Comment Only
05/07/2021
10 stoop footings on west and north sides as per plan approved. Monument sign footing at West entry approved.

Progress Inspection Passed 5/10/2021 (8:00 - 10:00) 5/10/2021 (AM) 05/07/2021
Corrections:


Miscellaneous/Other
Comment Only
05/07/2021
Rated shafts throughout west side (sections C & D) OK to insulate. Call for progress inspection of remaining sheet rock work in rated shafts.

Progress Inspection Passed 5/11/2021 (8:00 - 10:00) 5/11/2021 (AM) 05/10/2021
Corrections:


Miscellaneous/Other
Comment Only
05/10/2021
Exterior insulation on third floor, section B, approved.

Progress Inspection Passed w/ Conditions 5/12/2021 (8:00 - 10:00) 5/12/2021 (AM) 05/12/2021
Corrections:


Miscellaneous/Other
Outstanding
05/12/2021
Fire caulk one penetration in unit 227 bathroom. Fire caulk one Penetration in unit 225 living room. Fire caulk three penetrations in unit 223 living room. OK to insulate when done.

Progress Inspection Passed 5/17/2021 (8:00 - 10:00) 5/17/2021 (AM) 05/17/2021
Corrections:


Miscellaneous/Other
Comment Only
05/17/2021
Fire caulk one penetration in unit 225, living room. OK to cover when done. Insulation approved all other units on second floor, section A.

Progress Inspection Passed 5/18/2021 (8:00 - 10:00) 5/18/2021 (AM) 05/17/2021
Corrections:


Miscellaneous/Other
Outstanding
05/17/2021
Fire caulk one electrical penetration in top plate in unit 225. OK to cover when done. All other units on second floor, section A are approved for insulation. Stucco lath on south end of East wall approved.

Progress Inspection Passed 5/19/2021 (8:00 - 10:00) 5/19/2021 (AM) 05/19/2021
Corrections:


Miscellaneous/Other
Comment Only
05/19/2021
Fire caulking corrections and insulation of units in 2B approved. Stucco lath on south side of section A approved.

Progress Inspection Passed 5/24/2021 (8:00 - 10:00) 5/24/2021 (AM) 05/24/2021
Corrections:


Miscellaneous/Other
Comment Only
05/24/2021
Framing and fire caulking of units and common areas on first floor section A approved.

Progress Inspection Failed 5/26/2021 (8:00 - 10:00) 5/26/2021 (AM) 05/26/2021
Corrections:


Miscellaneous/Other
Comment Only
05/26/2021
Framing and fire caulking issues remain for area B, first floor. Insulation issues remain in area a, first floor. To be reinspected.

Progress Inspection Passed 5/27/2021 (8:00 - 10:00) 5/27/2021 (AM) 05/27/2021
Corrections:


Miscellaneous/Other
Comment Only
05/27/2021
Insulation corrections complete for first floor, section A. Fire caulking corrections complete for first floor section B. Fire blocking issues to be inspected later.

Progress Inspection Passed 6/1/2021 (10:00 - 12:00) 6/1/2021 (AM) 06/01/2021
Corrections:


Miscellaneous/Other
Comment Only
06/01/2021
Followed up on miscellaneous corrections regarding framing, fire caulking and insulation on first floor in sections a and B. All approved.

Progress Inspection Passed 6/3/2021 (10:00 - 12:00) 6/3/2021 (AM) 06/03/2021
Corrections:


Miscellaneous/Other
Comment Only
06/03/2021
Stucco lath on inside corner of East Courtyard approved.

Progress Inspection Partial Pass 6/7/2021 (10:00 - 12:00) 6/7/2021 (AM) 06/07/2021
Corrections:


Miscellaneous/Other
Outstanding
06/07/2021
Provide engineering clarification for bearing requirements for LVL beams in several spaces in section C & D, fifth floor. Framing and fire caulking approved in other units as marked on door jambs.

Progress Inspection Passed 6/9/2021 (10:00 - 12:00) 6/9/2021 (AM) 06/09/2021
Corrections:


Miscellaneous/Other
Comment Only
06/09/2021
Progress inspection of stucco lath center of Courtyard approved. Insulation approved on fifth floor, section C.

Progress Inspection Passed 6/10/2021 (10:00 - 12:00) 6/10/2021 (AM) 06/10/2021
Corrections:


Miscellaneous/Other
Comment Only
06/10/2021
Insulation approved for all fifth floor units in section C & D. East stairwell shaft exterior walls OK to insulate, all floors. Trash room shaft on fifth floor approved. Fire blocking approved at all fireplace voids.

Progress Inspection Passed 6/11/2021 (10:00 - 12:00) 6/11/2021 (AM) 06/11/2021
Corrections:


Miscellaneous/Other
Comment Only
06/11/2021
Framing and fire caulking approved in all units on fourth floor, sections C and D. West trash chute approved all floors.

Progress Inspection Passed 6/15/2021 (10:00 - 12:00) 6/15/2021 (AM) 06/15/2021
Corrections:


Miscellaneous/Other
Comment Only
06/15/2021
Remaining lath inspection in Courtyard area approved. Exterior wall insulation on fourth floor, section C approved. First and second floors of common entry area, framing and fire caulk approved.

Progress Inspection Passed w/ Conditions 6/21/2021 (10:00 - 12:00) 6/21/2021 (AM) 06/21/2021
Corrections:


Miscellaneous/Other
Comment Only
06/21/2021
Foam insulation required in gaps between studs in north and south lobby walls. OK to cover when done.

Progress Inspection Passed 6/22/2021 (10:00 - 12:00) 6/22/2021 (AM) 06/22/2021
Corrections:


Miscellaneous/Other
Comment Only
06/22/2021
Framing and fire caulking on all floors of west stairwell approved. Insulation on fifth floor, west stairwell approved. Observed concrete pour in trash chute on first floor, west side, approved.

Progress Inspection Passed 6/23/2021 (10:00 - 12:00) 6/23/2021 (AM) 06/23/2021
Corrections:


Miscellaneous/Other
Comment Only
06/23/2021
Insulation on fourth floor, section D, approved. Fire caulking first floor soffits , section A approved.

Progress Inspection Passed 6/25/2021 (10:00 - 12:00) 6/25/2021 (AM) 06/25/2021
Corrections:


Miscellaneous/Other
Comment Only
06/25/2021
Framing and fire caulking on third floor, sections C and D, approved.

Progress Inspection Partial Pass 6/29/2021 (10:00 - 12:00) 6/29/2021 (AM) 06/29/2021
Corrections:


Miscellaneous/Other
Comment Only
06/29/2021
Remaining exterior insulation at lobby doors approved. Fire caulking in soffits on first floor, section be approved. Foam insulation in roof of connecting link on east side approved. Rework Sound insulation in ceiling in unit 406 and have reinspected. Provide shop drawings for pool rebar inspection.

Progress Inspection Passed 6/30/2021 (10:00 - 12:00) 6/30/2021 (AM) 06/30/2021
Corrections:


Miscellaneous/Other
Comment Only
06/30/2021
Rebar for pool as per engineered drawings approved. Insulation on third floor, section C, approved.

Progress Inspection Passed 7/12/2021 (10:00 - 12:00) 7/12/2021 (AM) 07/12/2021
Corrections:


Miscellaneous/Other
Comment Only
07/12/2021
Insulation inspection of section C, second floor, approved.

Progress Inspection Passed 7/13/2021 7/13/2021 (AM) 07/13/2021
Corrections:


Miscellaneous/Other
Comment Only
07/13/2021
Framing and fire caulking on first floor, sections C and D, approved.Progress lath inspection on north side approved.

Progress Inspection Passed 7/14/2021 (8:00 - 10:00) 7/14/2021 (AM) 07/14/2021
Corrections:


Miscellaneous/Other
Comment Only
07/14/2021
Reviewed fire caulking in soffits on first and second floor of atrium, approved.

Progress Inspection Passed 7/16/2021 (8:00 - 10:00) 7/16/2021 (AM) 07/16/2021
Corrections:


Miscellaneous/Other
Comment Only
07/16/2021
Insulation approved on second floor, section D. Framing and fire caulking in link approved. Progress inspection of stucco lath on north side approved.

Progress Inspection Passed 7/21/2021 (8:00 - 10:00) 7/21/2021 (AM) 07/21/2021
Corrections:


Miscellaneous/Other
Comment Only
07/21/2021
Progress inspection of stucco lath on north side approved.

Progress Inspection Passed 7/22/2021 (8:00 - 10:00) 7/22/2021 (AM) 07/22/2021
Corrections:


Miscellaneous/Other
Comment Only
07/22/2021
Insulation of exterior walls on first floor, section C, approved.

Progress Inspection Passed 7/28/2021 (8:00 - 10:00) 7/28/2021 (AM) 07/28/2021
Corrections:


Miscellaneous/Other
Comment Only
07/28/2021
Insulation on first level, section D, approved.

Progress Inspection Passed 8/4/2021 (12:30 - 2:30) 8/4/2021 (PM) 08/03/2021
Corrections:


Miscellaneous/Other
Comment Only
08/03/2021
Link insulation approved.

Progress Inspection Passed 8/30/2021 (12:30 - 2:30) 8/30/2021 (PM) 08/30/2021
Corrections:


Miscellaneous/Other
Comment Only
08/30/2021
Deck guard rails on fifth floor, section A and B approved.

Progress Inspection Passed 8/31/2021 (12:30 - 2:30) 8/31/2021 (PM) 08/31/2021
Corrections:


Miscellaneous/Other
Comment Only
08/31/2021
Decking guard rails on third and fourth floors, sections A and B, approved.

Progress Inspection Passed 9/1/2021 (12:30 - 2:30) 9/1/2021 (PM) 09/01/2021
Corrections:


Miscellaneous/Other
Comment Only
09/01/2021
Deck guard rails on second floor, section A and B, approved.

Progress Inspection Passed 9/7/2021 (2:30 - 3:30) 9/7/2021 (PM) 09/07/2021
Corrections:


Miscellaneous/Other
Comment Only
09/07/2021
Deck guard rails on fourth floor, sections C and D, approved. (Unit number 404 to be checked at a later date.)

Progress Inspection Passed 9/9/2021 (12:30 - 2:30) 9/9/2021 (PM) 09/09/2021
Corrections:


Miscellaneous/Other
Comment Only
09/09/2021
Deck guard rails approved on second and third floor in section C and D. Note, unable to check unit number 204, 205 and 304 at this time. To be checked at a later date.

Progress Inspection Passed 9/16/2021 (10:00 - 12:00) 9/16/2021 (AM) 09/15/2021
Corrections:


Miscellaneous/Other
Comment Only
09/15/2021
Inspection of September 14 confirms remaining guard rails on fifth floor, sections C and D, approved.

Progress Inspection Passed 9/20/2021 (10:00 - 12:00) 9/20/2021 (AM) 09/20/2021
Corrections:


Miscellaneous/Other
Comment Only
09/20/2021
Fire caulking in ceilings in common areas with acoustical tile ceilings approved.

Progress Inspection Passed w/ Conditions 10/12/2021 (10:00 - 12:00) 10/12/2021 (AM) 10/12/2021
Corrections:


Miscellaneous/Other
Comment Only
10/12/2021
Reviewed on site with contractor location and corrections needed for exit signs on levels one through five. Garage level exiting to be done at a later date.

Progress Inspection Passed 11/3/2021 (12:30 - 2:30) 11/3/2021 (PM) 11/03/2021
Corrections:


Miscellaneous/Other
Comment Only
11/03/2021
Deck rails in unit 204, 304 and 504 approved. Need access to confirm guard rail in unit 404.

Progress Inspection Passed w/ Conditions 11/24/2021 (2:30 - 3:30) 11/24/2021 (PM) 11/24/2021
Corrections:


Miscellaneous/Other
Comment Only
11/24/2021
Confirmed remaining guard rail in unit 404 approved. Reviewed exit signage in garage and determined additions needed for final inspection, to be confirmed upon final.

Lighting Inspection Passed 12/6/2021 12/06/2021
Garage lighting passes - must inspect lot and entrance light levels - Inspected 11/10 and not ready. Lpease Inspected 12/2 - parking lot lighting and entrance areas passed inspection. MWC
Progress Inspection Passed 12/15/2021 (2:30 - 3:30) 12/15/2021 (PM) 12/16/2021
Corrections:


Miscellaneous/Other
Outstanding
12/16/2021
Complete installation of mallards in garage where required. Provide electronic as built drawings to engineering. 30 day temporary occupancy approved.

Building Final Inspection Issue TCO 12/16/2021
Corrections:


Miscellaneous/Other
Carried Forward
12/16/2021
Complete installation of bollards in garage as required. Provide electronic as built drawings to engineering. 30 day temporary occupancy approved.

Building Final Inspection Issue TCO 01/10/2022
Corrections:


Miscellaneous/Other
Resolved
01/10/2022
Complete installation of bollards in garage as required. Provide electronic as built drawings to engineering. 30 day temporary occupancy approved.

Miscellaneous/Other
Carried Forward
01/10/2022
Interior corrections are complete. Pool construction to be completed in spring. 120 day temporary occupancy approved.

Miscellaneous/Other
Outstanding
02/18/2022
Extend temporary occupancy 60 days to complete pool. Temporary occupancy valid through July 9.

Building Final Inspection Passed 05/18/2022
Corrections:


Miscellaneous/Other
Resolved
05/18/2022
Interior corrections are complete. Pool construction to be completed in spring. 120 day temporary occupancy approved.