Summary

PRBD202002802
Building
Finaled
FINANCING PARTNERSHIP LP
Alteration/Repair/Replace
Not Required
The project is a reconfiguration/remodeling of an existing 581,667 sq ft Best Buy Supply Chain Facility. The scope of work for Civil is new drive at northeast east entrance and reconfigured parking (separate parking lot permit). Architectural scope of work, new interior walls, ceiling, finishes, offices and toilets. Structural scope of work, new exterior overhead doors and loading dock.
03/23/2020
07/16/2020
08/09/2021
02/10/2021

Locations

Permits

Permit Number: PRBD202002802

Building
Finaled
07/16/2020
08/09/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 8/4/2020 (10:00 - 12:00) 8/4/2020 (AM) 08/04/2020
Added time for taking temp and access for COVID screening.
Corrections:


Miscellaneous/Other
Comment Only
08/04/2020
Footings for two stoops approved.

Framing Inspection Passed 8/6/2020 (8:00 - 10:00) 8/6/2020 (AM) 08/06/2020
Corrections:


Miscellaneous/Other
Comment Only
08/06/2020
Framing of will call room walls approved. New office demising wall on column line B approved to cover one side only until electrical rough in approved.

Footing Inspection Passed 9/9/2020 (12:30 - 2:30) 9/9/2020 (PM) 09/09/2020
Corrections:


Miscellaneous/Other
Comment Only
09/09/2020
20“ x 12“ strip footings with two, number four rebar on sandy soil approved.

Framing Inspection Passed 9/9/2020 (12:30 - 2:30) 9/9/2020 (PM) 09/09/2020
Corrections:


Miscellaneous/Other
Comment Only
09/09/2020
Demising wall framing approved. Note, no electrical in this wall.

Framing Inspection Passed 9/18/2020 (12:30 - 2:30) 9/18/2020 (PM) 09/18/2020
Corrections:


Miscellaneous/Other
Comment Only
09/18/2020
Phase 3 progress on framing includes IT room, approved.

Framing Inspection Partial Pass 9/30/2020 (8:00 - 10:00) 9/30/2020 (AM) 09/30/2020
Framing - Balance of Standard framed tall walls - steel stud, with top deflection deep leg track. Passed. Ongoing work partial pass.
Framing Inspection Passed 10/27/2020 (10:00 - 12:00) 10/27/2020 (AM) 10/27/2020
Corrections:


Miscellaneous/Other
Comment Only
10/27/2020
Additional miscellaneous wall framing approved.

Framing Inspection Passed 12/9/2020 (8:00 - 10:00) 12/9/2020 (AM) 12/09/2020
Corrections:


Miscellaneous/Other
Comment Only
12/09/2020
Final framing inspection of framed suspended ceiling OK. Contractor to confirm compliance with engineered support system.

Fire Inspection Final Partial Pass 1/19/2021 (12:30 - 2:30) 1/19/2021 (PM) 01/19/2021
Building Final Inspection Failed 1/19/2021 (12:30 - 2:30) 1/19/2021 (PM) 01/19/2021
Corrections:


Miscellaneous/Other
Carried Forward
01/19/2021
1. Provide cane guard at drinking fountain in corridor. 2. Provide vertical grab bars in ambulatory stall. 3. Provide five exit lights as directed in field. Call for reinspection.

Building Final Inspection Issue TCO 1/25/2021 (10:00 - 12:00) 1/25/2021 (AM) 01/25/2021
Corrections:


Miscellaneous/Other
Resolved
01/25/2021
1. Provide cane guard at drinking fountain in corridor. 2. Provide vertical grab bars in ambulatory stall. 3. Provide five exit lights as directed in field. Call for reinspection.

Miscellaneous/Other
Carried Forward
01/25/2021
Need final electrical approval when furniture is installed. 15 day temporary occupancy approved.

Fire Inspection Final Passed 1/25/2021 (10:00 - 12:00) 1/25/2021 (AM) 01/25/2021
Building Final Inspection Passed 02/10/2021
Corrections:


Miscellaneous/Other
Resolved
02/10/2021
Need final electrical approval when furniture is installed. 15 day temporary occupancy approved.