Summary

PRBD202004299
Building
Expired
LIFESPACE COMMUNITIES INC
Addition
Not Required
Phase 2 of the new Healthcare building, including Skilled Nursing, Short Term Rehab and other activity spaces.
05/06/2020
12/16/2020
01/18/2023

Locations

Permits

Permit Number: PRBD202004299

Building
Expired
12/16/2020
01/18/2023

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Not Ready 4/20/2021 (2:30 - 3:30) 4/20/2021 (PM) 04/20/2021
Progress Inspection Passed 4/27/2021 (2:30 - 3:30) 4/27/2021 (PM) 04/27/2021
Corrections:


Miscellaneous/Other
Comment Only
04/27/2021
Pad footings and strip footings for south half of the building as per plan marked in field, approved. Submit special inspectors report regarding compacted soil.

Progress Inspection Passed 5/3/2021 (2:30 - 3:30) 5/3/2021 (PM) 05/03/2021
Corrections:


Miscellaneous/Other
Comment Only
05/03/2021
Poured foundation wall along south east wall approved.

Progress Inspection Passed 5/6/2021 (2:30 - 3:30) 5/6/2021 (PM) 05/06/2021
Corrections:


Miscellaneous/Other
Comment Only
05/06/2021
Poured foundation wall on east side of South wing approved.

Progress Inspection Passed 5/7/2021 (2:30 - 3:30) 5/7/2021 (PM) 05/07/2021
Corrections:


Miscellaneous/Other
Comment Only
05/07/2021
Pad footings and strip footings for north wing as per plans marked infield approved.

Progress Inspection Passed 5/12/2021 (2:30 - 3:30) 5/12/2021 (PM) 05/12/2021
Corrections:


Miscellaneous/Other
Comment Only
05/12/2021
Progress inspection of poured foundation wall on west side of South wing approved.

Progress Inspection Passed 5/18/2021 (2:30 - 3:30) 5/18/2021 (PM) 05/17/2021
Corrections:


Miscellaneous/Other
Comment Only
05/17/2021
Poured foundation wall on east side of North wing approved.

Progress Inspection Passed 5/19/2021 (2:30 - 3:30) 5/19/2021 (PM) 05/19/2021
Corrections:


Miscellaneous/Other
Comment Only
05/19/2021
Poured wall inspection at South connection to existing phase 1 building approved.

Progress Inspection Passed 5/26/2021 (2:30 - 3:30) 5/26/2021 (PM) 05/26/2021
Corrections:


Miscellaneous/Other
Comment Only
05/26/2021
Eight pad footings and poured foundation wall at North East side of North wing approved.

Framing Inspection Passed 10/19/2021 (2:30 - 3:30) 10/19/2021 (PM) 10/19/2021
Corrections:


Miscellaneous/Other
Comment Only
10/19/2021
Reviewed plan requirements and progress of interior rated walls for framing inspection.

Framing Inspection Partial Pass 10/26/2021 (2:30 - 3:30) 10/26/2021 (PM) 10/26/2021
Corrections:


Miscellaneous/Other
Comment Only
10/26/2021
Progress inspection above ceiling fire caulking on second floor approved.

Framing Inspection Passed 11/16/2021 (2:30 - 3:30) 11/16/2021 (PM) 11/16/2021
Corrections:


Miscellaneous/Other
Comment Only
11/16/2021
Progress inspection of fire proofing and fire caulking on second and third floors approved.

Framing Inspection Passed 11/18/2021 (2:30 - 3:30) 11/18/2021 (PM) 11/18/2021
Corrections:


Miscellaneous/Other
Comment Only
11/18/2021
Meeting on site with contractor and subcontractors to review inspections of fire caulking and smoke sealing as required and scheduling.

Framing Inspection Passed 11/23/2021 (2:30 - 3:30) 11/23/2021 (PM) 11/23/2021
Corrections:


Miscellaneous/Other
Comment Only
11/23/2021
Partial inspection of smoke sealing on third floor approved.

Framing Inspection Passed 11/30/2021 (2:30 - 3:30) 11/30/2021 (PM) 11/30/2021
Corrections:


Miscellaneous/Other
Comment Only
11/30/2021
Third floor exterior wall framing approved for insulation. Interior wall framing and smoke penetration protections to be completed when other trades complete.

Progress Inspection Passed 12/2/2021 (8:00 - 10:00) 12/2/2021 (AM) 12/02/2021
Vapor barrier inspection as per contractor
Corrections:


Miscellaneous/Other
Comment Only
12/02/2021
Exterior wall insulation on east wing of third floor approved.

Progress Inspection Passed 12/7/2021 (2:30 - 3:30) 12/7/2021 (PM) 12/07/2021
Corrections:


Miscellaneous/Other
Comment Only
12/07/2021
Framing and smoke caulking of units on third floor approved. Remaining units on third floor insulation and vapor barrier approved.

Progress Inspection Not Ready 12/14/2021 (2:30 - 3:30) 12/14/2021 (PM) 12/14/2021
Progress Inspection Passed 12/21/2021 (2:30 - 3:30) 12/21/2021 (PM) 12/21/2021
Corrections:


Miscellaneous/Other
Comment Only
12/21/2021
Progress inspection of exterior insulation and smoke caulking of unit on second floor approved.

Progress Inspection Passed 12/22/2021 (2:30 - 3:30) 12/22/2021 (PM) 12/22/2021
Corrections:


Miscellaneous/Other
Comment Only
12/22/2021
Exterior wall insulation and vapor barrier‘s in remaining units on second floor approved.

Framing Inspection Passed 11/9/2021 (2:30 - 3:30) 11/9/2021 (PM) 12/30/2021
Corrections:


Miscellaneous/Other
Comment Only
12/30/2021
Progress inspection of first floor exterior walls, some with insulation, some with insulation and vapor barrier, approved as marked in field.

Progress Inspection Passed 1/4/2022 (2:30 - 3:30) 1/4/2022 (PM) 01/04/2022
Corrections:


Miscellaneous/Other
Comment Only
01/04/2022
Exterior insulation and vapor barrier in remaining units on first floor approved.

Progress Inspection Not Ready 1/11/2022 (2:30 - 3:30) 1/11/2022 (PM) 01/13/2022
Progress Inspection Passed 1/18/2022 (2:30 - 3:30) 1/18/2022 (PM) 01/18/2022
Corrections:


Miscellaneous/Other
Comment Only
01/18/2022
Smoke sealing of walls in units on first floor approved.

Progress Inspection Passed 1/25/2022 (2:30 - 3:30) 1/25/2022 (PM) 01/27/2022
Corrections:


Miscellaneous/Other
Comment Only
01/27/2022
Exterior wall insulation in common areas on first floor and remaining common areas of second floor approved.

Progress Inspection Passed 2/1/2022 (2:30 - 3:30) 2/1/2022 (PM) 02/01/2022
Corrections:


Miscellaneous/Other
Comment Only
02/01/2022
Vapor barrier on exterior walls on first floor approved.

Progress Inspection Not Ready 2/15/2022 (2:30 - 3:30) 2/15/2022 (PM) 02/15/2022
Corrections:


Miscellaneous/Other
Comment Only
02/15/2022
Smoke rated walls on first and second levels not ready for inspection.

Progress Inspection Failed 2/22/2022 (2:30 - 3:30) 2/22/2022 (PM) 02/24/2022
Corrections:


Miscellaneous/Other
Carried Forward
02/25/2022
Smoke rated walls on first floor not ready for inspection. Seal all penetrations as required and call for reinspection. Provide detail of ceiling insulation and framing for octagon room and called for separate insulation inspection. Patch fireproofing and structural steel in octagon room as required.

Progress Inspection Not Ready 3/1/2022 (12:30 - 2:30) 3/1/2022 (PM) 03/01/2022
Progress Inspection Partial Pass 3/8/2022 (2:30 - 3:30) 3/8/2022 (PM) 03/08/2022
Corrections:


Miscellaneous/Other
Resolved
03/08/2022
Smoke rated walls on first floor not ready for inspection. Seal all penetrations as required and call for reinspection. Provide detail of ceiling insulation and framing for octagon room and called for separate insulation inspection. Patch fireproofing and structural steel in octagon room as required.

Miscellaneous/Other
Outstanding
03/08/2022
Corrections to insulation and fire proof patching as required in octagon room approved. Smoke rated walls yet to be inspected.

Progress Inspection Passed 3/10/2022 (12:30 - 2:30) 3/10/2022 (PM) 03/10/2022
Corrections:


Miscellaneous/Other
Comment Only
03/10/2022
Smoke rated walls on first floor approved.

Progress Inspection Partial Pass 3/29/2022 (2:30 - 3:30) 3/29/2022 (PM) 03/30/2022
Corrections:


Miscellaneous/Other
Comment Only
03/30/2022
Reviewed touchless sensors in public restrooms to see if compliance with ADA clearances is OK. Currently investigating.

Progress Inspection Passed 4/19/2022 (2:30 - 3:30) 4/19/2022 (PM) 04/19/2022
Corrections:


Miscellaneous/Other
Comment Only
04/19/2022
Reviewed scheduling needs for month of May.

Progress Inspection Partial Pass 4/26/2022 (2:30 - 3:30) 4/26/2022 (PM) 04/26/2022
Corrections:


Miscellaneous/Other
Comment Only
04/26/2022
Preliminary final walk-through to inspect items like exiting, exit signage, fire and smoke ratings of doors and miscellaneous. No outstanding issues.

Progress Inspection Partial Pass 5/5/2022 (2:30 - 3:30) 5/5/2022 (PM) 05/05/2022
Corrections:


Miscellaneous/Other
Comment Only
05/05/2022
Partial preliminary final inspection on first floor only. Discussed missing fire extinguisher on site. Will discuss exit sign locations after all three floors have been reviewed.

Progress Inspection Partial Pass 5/11/2022 (12:30 - 2:30) 5/11/2022 (PM) 05/11/2022
Corrections:


Miscellaneous/Other
Comment Only
05/11/2022
Preliminary final walk-through of third and second floors show no items of concern.

Lighting Inspection Passed 05/12/2022
Progress Inspection Partial Pass 5/12/2022 (2:30 - 3:30) 5/12/2022 (PM) 05/12/2022
Corrections:


Miscellaneous/Other
Comment Only
05/12/2022
Preliminary walk-through of garage level shows no major concerns. Suggest review of fire caulked penetrations in concrete deck above. Discuss with building inspector.

Progress Inspection Partial Pass 5/13/2022 (2:30 - 3:30) 5/13/2022 (PM) 05/13/2022
Corrections:


Miscellaneous/Other
Comment Only
05/13/2022
Preliminary final walk-through on first floor reveals no concerns.

Progress Inspection Passed 5/17/2022 (2:30 - 3:30) 5/17/2022 (PM) 05/17/2022
Corrections:


Miscellaneous/Other
Comment Only
05/17/2022
Phase 2 skilled nursing building, final approved.

Building Final Inspection Passed 05/17/2022
Corrections:


Miscellaneous/Other
Comment Only
05/17/2022
Phase two skilled nursing building final approved.

Fire Inspection Final Passed 6/28/2022 (10:00 - 12:00) 6/28/2022 (AM) 07/22/2022