| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 7/13/2020 (10:00 - 12:00) | 7/13/2020 (AM) | 07/13/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/13/2020
Call for above ceiling fire proofing inspection.
|
||||
| Progress Inspection | Passed | 9/1/2020 (8:00 - 10:00) | 9/1/2020 (AM) | 09/01/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/01/2020
Above ceiling approved.
|
||||
| Fire Inspection Final | Passed | 9/24/2020 (8:00 - 10:00) | 9/24/2020 (AM) | 09/24/2020 |
| Building Final Inspection | Passed | 9/25/2020 (10:00 - 12:00) | 9/25/2020 (AM) | 09/25/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/25/2020
Final approved , approved for occupancy.
|
||||
|
Miscellaneous/Other
Comment Only
09/25/2020
Final approved , approved for occupancy.
|
||||