Permit Application Status

PRBD202005318


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202005318
Building
Expired
AEON VP BLOOMINGTON LLC
New
Not Required
172 unit apartment building with sub-grade enclosed parking and surface parking. (Northern Building = Building B)
05/29/2020
07/30/2020
05/28/2022

Locations

Permits

Permit Number: PRBD202005318

Building
Expired
07/30/2020
05/28/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 11/2/2020 (10:00 - 12:00) 11/2/2020 (AM) 11/02/2020
Corrections:


Miscellaneous/Other
Comment Only
11/02/2020
Center stair, elevator and adjacent shaft, first layer of gypsum at first level... approved

Footing Inspection Partial Pass 11/3/2020 (10:00 - 12:00) 11/3/2020 (AM) 11/03/2020
Corrections:


Miscellaneous/Other
Comment Only
11/03/2020
Perimeter footings of building B, halfway between lines 14b and 15b to line 18b. Grid Fb to grid Cb. Line 15.8b to line 18b. Approved for concrete placement.

Footing Inspection Partial Pass 11/4/2020 (10:00 - 12:00) 11/4/2020 (AM) 11/04/2020
Corrections:


Miscellaneous/Other
Comment Only
11/04/2020
Perimeter footings at grid Cb, lines 3b.75 to 5b.5 Grid Cb, lines 14b.5 to 9b. Approved for concrete placement

Footing Inspection Partial Pass 11/5/2020 (10:00 - 12:00) 11/5/2020 (AM) 11/05/2020
Corrections:


Miscellaneous/Other
Comment Only
11/05/2020
Strip footings at : Line 4B and small section of Ab. Grid Fb from 14b.5 to 10b.5. 3 pads at grid Eb, lines 17b, 16b, and 15b. Approved for concrete placement

Footing Inspection Partial Pass 11/6/2020 (10:00 - 12:00) 11/6/2020 (AM) 11/06/2020
Corrections:


Miscellaneous/Other
Comment Only
11/06/2020
4 pads on grid Eb ,lines 11b,12b, 13b and 14b Grid Fb from line10b.5 to line 2b.5 Approved for concrete placement

Footing Inspection Not Ready 11/16/2020 (10:00 - 12:00) 11/16/2020 (AM) 11/16/2020
Corrections:


Miscellaneous/Other
Comment Only
11/16/2020
Not ready for inspection at this time.

Footing Inspection Partial Pass 11/17/2020 (10:00 - 12:00) 11/17/2020 (AM) 11/17/2020
Corrections:


Miscellaneous/Other
Comment Only
11/17/2020
5 pad footings on grid Db, lines 11.b, 12.b, 13.b,14.b, and 16.8b... approved for concrete placement

Footing Inspection Partial Pass 11/18/2020 (10:00 - 12:00) 11/18/2020 (AM) 11/18/2020
Corrections:


Miscellaneous/Other
Comment Only
11/18/2020
Grid Db, between lines 15b and 15.8b ... pads and stair. Pad at Grid Db, line 9b Elevator at line7b.6, between grids Db and Cb. Approved for concrete placement

Footing Inspection Partial Pass 11/19/2020 (10:00 - 12:00) 11/19/2020 (AM) 11/19/2020
Corrections:


Miscellaneous/Other
Comment Only
11/19/2020
Foundation walls at elevator... approved

Footing Inspection Partial Pass 11/20/2020 (10:00 - 12:00) 11/20/2020 (AM) 11/20/2020
Corrections:


Miscellaneous/Other
Comment Only
11/20/2020
Pads on grid Db, lines 2b, 4.1b, 5b, and 6b.remaining footings between grade steps on grid Ab. Approved for concrete placement Waterproofing at elevator pit and walls... approved

Footing Inspection Not Ready 11/30/2020 (10:00 - 12:00) 11/30/2020 (AM) 11/30/2020
Corrections:


Miscellaneous/Other
Comment Only
11/30/2020
Not ready for inspection

Footing Inspection Partial Pass 12/1/2020 (10:00 - 12:00) 12/1/2020 (PM) 12/01/2020
Corrections:


Miscellaneous/Other
Comment Only
12/01/2020
Strip footings remainder of line 1b to Fb, and Remainder of grid Fb to 3b.5 Pads on grid Eb , lines 2b, 3b, and 4.1b. Approved for concrete placement. Other remains footings and pads not inspected by city were inspected by special inspector, see special inspection reports .

Progress Inspection Partial Pass 12/2/2020 (10:00 - 12:00) 12/2/2020 (AM) 12/02/2020
Corrections:


Miscellaneous/Other
Comment Only
12/02/2020
Foundation waterproofing at 4’ height for 1st lift on north and east foundation of building and draintile... approved.

Progress Inspection Partial Pass 02/05/2021
Corrections:


Miscellaneous/Other
Comment Only
02/05/2021
West shaft on installation level, first outer layer of gypsum... approved

Framing Inspection Partial Pass 02/22/2021
Corrections:


Miscellaneous/Other
Comment Only
02/22/2021
First layers of gypsum at outer layer of shaft walls on west side of building (from entry to west end). Approved

Progress Inspection Partial Pass 02/25/2021
Corrections:


Miscellaneous/Other
Comment Only
02/25/2021
First gypsum outer layer of shaft walls on level to of western portion of building... approved

Progress Inspection Not Ready 3/4/2021 (12:30 - 2:30) 3/4/2021 (PM) 03/04/2021
Corrections:


Miscellaneous/Other
Comment Only
03/04/2021
Not ready for inspection

Progress Inspection Partial Pass 03/05/2021
Corrections:


Miscellaneous/Other
Comment Only
03/05/2021
2nd level west end shafts, outer 1st layer of gypsum approved

Progress Inspection Partial Pass 03/12/2021
Corrections:


Miscellaneous/Other
Comment Only
03/12/2021
1st outer layer gypsum at west stair and mechanical shaft of 3rd floor building B... approved

Progress Inspection Partial Pass 03/19/2021
Corrections:


Miscellaneous/Other
Comment Only
03/19/2021
3rd floor west end shaft walls, outer first layer of gypsum... approved

Progress Inspection Partial Pass 03/26/2021
Corrections:


Miscellaneous/Other
Comment Only
03/26/2021
4th level west end stair and shaft, outer 1st layer of gypsum... approved

Progress Inspection Failed 4/5/2021 (10:00 - 12:00) 4/5/2021 (AM) 04/05/2021
Corrections:


Miscellaneous/Other
Comment Only
04/05/2021
Footings for trash enclosure on NW site end. High voltage power is uncovered and the design of footings for enclosure would encapsulate the high voltage and fiber optic lines. Verbal Stop work with remaining footings to the company, until Excel comes out to access the situation.

Progress Inspection Partial Pass 4/6/2021 (8:00 - 10:00) 4/6/2021 (AM) 04/06/2021
Corrections:


Miscellaneous/Other
Comment Only
04/06/2021
NW trash enclosure for 1910 Bldg... footings approved. Issue with Excel power resolved.

Footing Inspection Partial Pass 04/13/2021
Corrections:


Miscellaneous/Other
Comment Only
04/13/2021
Footing for trash enclosure at 1920 building .... approved

Framing Inspection Partial Pass 04/19/2021
Corrections:


Miscellaneous/Other
Comment Only
04/19/2021
Roof washer anchors for west end of building installed as per design...approved. Testing of the anchors to be done by contractor, approved to start roofing.

Progress Inspection Partial Pass 04/27/2021
Corrections:


Miscellaneous/Other
Comment Only
04/27/2021
Stairwell on 1st floor east end, outer 1st layer of gypsum... approved

Progress Inspection Partial Pass 05/05/2021
Corrections:


Miscellaneous/Other
Comment Only
05/05/2021
Exterior first layer of gypsum at east stair shaft of 2nd floor... approved

Framing Inspection Partial Pass 5/17/2021 (8:00 - 10:00) 5/17/2021 (AM) 05/17/2021
Corrections:


Miscellaneous/Other
Comment Only
05/17/2021
Zone 1 magic pac closet framing on floors 1-4... approved and ok to insulate.

Progress Inspection Partial Pass 05/19/2021
Corrections:


Miscellaneous/Other
Comment Only
05/19/2021
Stair shaft of zone 2, 3rd floor outer gypsum first layer... approved

Housewrap Inspection Partial Pass 05/19/2021
Corrections:


Miscellaneous/Other
Comment Only
05/19/2021
Housewrap of building to zone 1.... approved

Framing Inspection Partial Pass 5/20/2021 (8:00 - 10:00) 5/20/2021 (AM) 05/20/2021
Corrections:


Miscellaneous/Other
Comment Only
05/20/2021
Magic pac insulation/poly zone 1,4th floor... approved Framing and firestops of units, misc rooms, and hallways of 4th floor zone 1...approved

Insulation Inspection Partial Pass 5/26/2021 (12:30 - 2:30) 5/26/2021 (PM) 05/26/2021
Corrections:


Miscellaneous/Other
Comment Only
05/26/2021
Poly/ insulation in zone 1 units 419-425... approved

Progress Inspection Partial Pass 5/27/2021 (12:30 - 2:30) 5/27/2021 (PM) 05/27/2021
Corrections:


Miscellaneous/Other
Comment Only
05/27/2021
Remaining insulation/poly at units on 4th floor zone 1... approved. First layer of gypsum on ceiling of the 2 end units of zone 1, 4th floor... approved.

Progress Inspection Partial Pass 5/28/2021 (12:30 - 2:30) 5/28/2021 (PM) 05/28/2021
Corrections:


Miscellaneous/Other
Comment Only
05/28/2021
3rd floor zone 1 framing and firestops. Hallway and units starting at west end to about halfway of this floor. 4th floor firestops layer of gypsum at ceiling, units done are approximately 7. Approved

Progress Inspection Partial Pass 6/1/2021 (12:30 - 2:30) 6/1/2021 (PM) 06/01/2021
Corrections:


Miscellaneous/Other
Comment Only
06/01/2021
Units and hallways of zone 1, 3rd floor, framing and firestops... approved . 4 units of 1st layer gypsum at rated ceiling of 4th floor. Mechanical shaft of 1st floor, 1st and 2nd layer gypsum. East Stair and shaft at 4th floor , outer first gypsum layer. Approved.

Progress Inspection Partial Pass 6/2/2021 (12:30 - 2:30) 6/2/2021 (PM) 06/02/2021
Corrections:


Miscellaneous/Other
Comment Only
06/02/2021
Zone 1. First layer of gypsum at ceiling of hallway and 3 more units 4th floor. Poly/ insulation at elevator 4th floor. Framing and firestops at laundry room and elevator lobby 3rd floor. Approved

Progress Inspection Partial Pass 6/3/2021 (12:30 - 2:30) 6/3/2021 (PM) 06/03/2021
Corrections:


Miscellaneous/Other
Comment Only
06/03/2021
Center elevator at 4th floor, 1st layer of gypsum.... approved. First layer of gypsum at ceiling of the last 2 units in zone 1, 4th floor...approved.

Progress Inspection Partial Pass 6/4/2021 (12:30 - 2:30) 6/4/2021 (PM) 06/04/2021
Corrections:


Miscellaneous/Other
Comment Only
06/04/2021
Zone 1, 4th floor ceilings first layer gypsum at elevator lobby, hallway and laundry room..approved

Insulation Inspection Partial Pass 06/08/2021
Corrections:


Miscellaneous/Other
Comment Only
06/08/2021
Insulation/poly at zone 1, 3rd floor units... approved.

Progress Inspection Partial Pass 6/8/2021 (12:30 - 2:30) 06/08/2021
Corrections:


Miscellaneous/Other
Comment Only
06/08/2021
Zone 1, 4th floor shear walls in 5 units... approved First layer gypsum in mechanical shaft and trash shaft at 3rd floor...approved

Progress Inspection Partial Pass 6/9/2021 (12:30 - 2:30) 6/9/2021 (PM) 06/09/2021
Corrections:


Miscellaneous/Other
Comment Only
06/09/2021
4 more units of shear was f 4th floor zone 1…approved

Progress Inspection Partial Pass 6/10/2021 (12:30 - 2:30) 6/10/2021 (PM) 06/10/2021
Corrections:


Miscellaneous/Other
Comment Only
06/10/2021
2nd floor zone 1… framing and firestops to a areas except electrical rooms and stairways. Approved with corrections marked at units of nail plates needed.

Progress Inspection Partial Pass 06/11/2021
Corrections:


Miscellaneous/Other
Comment Only
06/11/2021
West and center stair of 3rd and 4th floor framing firestops…approved

Progress Inspection Partial Pass 6/14/2021 (10:00 - 12:00) 6/14/2021 (AM) 06/14/2021
Corrections:


Miscellaneous/Other
Comment Only
06/14/2021
Reminder of units in zone 1, 4th floor shear walls…approved. First layer of gypsum at 3rd floor elevator… approved Insulation/ poly of west and center stairs floors 3&4…approved

Housewrap Inspection Passed 06/15/2021
Corrections:


Miscellaneous/Other
Comment Only
06/15/2021
Housewrap at zone 2 / remainder of building… approved

Progress Inspection Partial Pass 06/15/2021
Corrections:


Miscellaneous/Other
Comment Only
06/15/2021
First layer of gypsum at center stair of floors 3&4… approved . Remainder roof washer anchors to zone two, installation as per design and tested to hold implied load.. approved

Progress Inspection Not Ready 6/16/2021 (8:00 - 10:00) 6/16/2021 (AM) 06/16/2021
Corrections:


Miscellaneous/Other
Comment Only
06/16/2021
Not ready for inspection

Progress Inspection Partial Pass 6/21/2021 (10:00 - 12:00) 6/21/2021 (AM) 06/21/2021
Corrections:


Miscellaneous/Other
Comment Only
06/21/2021
Zone 1, floor 2… insulation/ poly in units, and first layer gypsum at elevator…approved. Geo grid at retaining wall at garage entry… approved.

Progress Inspection Partial Pass 6/22/2021 (8:00 - 10:00) 6/22/2021 (AM) 06/22/2021
Corrections:


Miscellaneous/Other
Comment Only
06/22/2021
Framing and fire stops for zone 1, units, corridor and misc utility rooms up to elevator lobby. 6 units of shear walls in zone 1, 3rd floor. Approved

Progress Inspection Partial Pass 06/23/2021
Corrections:


Miscellaneous/Other
Comment Only
06/23/2021
1st floor elevator… first layer gypsum approved. 2nd floor trash and mechanical shafts…approved. 3rd floor , 2 more units with shear walls… approved. Fire stops at rain leaders of 4th floor at rated walls… approved

Progress Inspection Partial Pass 6/28/2021 (10:00 - 12:00) 6/28/2021 (AM) 06/28/2021
Corrections:


Miscellaneous/Other
Comment Only
06/28/2021
3 more units of shear walls on 3rd floor zone 1. Magic pacs approved to insulate for all floors zone 2. Stairs A& B framing and fire stops from basement to top floor. Approved First floor entry and rooms, 160- A,B,C, 161,162, 150, and restroom. Approved with framing and fire stops.

Progress Inspection Partial Pass 06/30/2021
Corrections:


Miscellaneous/Other
Comment Only
06/30/2021
Last 2 units of shear walls on 3rd floor zone 1. Tip in wall to mechanical shaft on 3rd floor. Approved

Progress Inspection Partial Pass 7/2/2021 (12:30 - 2:30) 7/2/2021 (PM) 07/02/2021
Corrections:


Miscellaneous/Other
Comment Only
07/02/2021
Shear walls in units 219,222,223,224, & 225… approved

Progress Inspection Partial Pass 7/7/2021 (10:00 - 12:00) 7/7/2021 (AM) 07/07/2021
Corrections:


Miscellaneous/Other
Comment Only
07/07/2021
Trash shaft, and mechanical shaft first layer gypsum at first floor… approved Shear wall in units 217,218,220 & 221… approved

Framing Inspection Partial Pass 7/9/2021 (8:00 - 10:00) 7/9/2021 (AM) 07/09/2021
Corrections:


Miscellaneous/Other
Comment Only
07/09/2021
Remaining units of shear walls on second floor zone one. Insulation/poly in zone 1 units and east side common areas. Zone 2 fourth floor units and hallway framing and fire stops. Approved

Progress Inspection Partial Pass 7/13/2021 (8:00 - 10:00) 7/13/2021 (AM) 07/13/2021
Corrections:


Miscellaneous/Other
Comment Only
07/13/2021
Zone 1, second floor … remaining unit shear walls approved.

Progress Inspection Partial Pass 7/16/2021 (8:00 - 10:00) 7/16/2021 (AM) 07/16/2021
Corrections:


Miscellaneous/Other
Comment Only
07/16/2021
Zone 2, third floor units and hallway… framing and fire stops. Approved

Progress Inspection Passed 7/21/2021 (8:00 - 10:00) 7/21/2021 (AM) 07/21/2021
Corrections:


Miscellaneous/Other
Comment Only
07/21/2021
Zone 1 first floor unit shear walls. Units approved are marked at the inspection slip on entry door frame. 4th floor unit and stair insulation/poly. Approved.

Progress Inspection Partial Pass 7/23/2021 (8:00 - 10:00) 7/23/2021 (AM) 07/23/2021
Corrections:


Miscellaneous/Other
Comment Only
07/23/2021
Zone 2, 2nd floor framing and fire stops… approved Zone 1 unit shear walls all completed and approved Tip in panels to mechanical shafts in zone 1 floors 1&2… approved. Insulation in units of 3rd floor zone 2… approved

Progress Inspection Partial Pass 7/26/2021 (12:30 - 2:30) 7/26/2021 (PM) 07/26/2021
Corrections:


Miscellaneous/Other
Comment Only
07/26/2021
Zone 2, 4th floor first layer of gypsum at units ceilings… approved for units marked on door inspection card.

Progress Inspection Partial Pass 7/27/2021 (8:00 - 10:00) 7/27/2021 (AM) 07/27/2021
Corrections:


Miscellaneous/Other
Comment Only
07/27/2021
Zone 2, 4th floor … first layer of gypsum at ceiling in units inspected and marked at inspection slip at entry door…. Approved note… 2 units and hallway are left for inspection.

Progress Inspection Partial Pass 7/28/2021 (8:00 - 10:00) 7/28/2021 (AM) 07/28/2021
Corrections:


Miscellaneous/Other
Comment Only
07/28/2021
First floor common areas fire stops… approved Zone 2, 4th floor first layer of gypsum at ceilings of all units completed and approved.

Progress Inspection Partial Pass 7/30/2021 (8:00 - 10:00) 7/30/2021 (AM) 07/30/2021
Corrections:


Miscellaneous/Other
Comment Only
07/30/2021
Zone 2… 2nd floor units and stair insulation/poly. First floor framing and fire stops in hallway and units… Approved pending corrections given to contractor with anchor bolts.

Progress Inspection Partial Pass 08/03/2021
Corrections:


Miscellaneous/Other
Comment Only
08/03/2021
Zone 2, 4th floor hallway ceiling first layer gypsum…approved 3 units of shear walls marked approved at unit entry inspection sheet.

Progress Inspection Partial Pass 8/6/2021 (8:00 - 10:00) 8/6/2021 (AM) 08/06/2021
Corrections:


Miscellaneous/Other
Comment Only
08/06/2021
1st floor zone 2 units insulation/poly… approved 4th floor shear walls for all units except 2 that need to be hung… approved

Progress Inspection Partial Pass 8/10/2021 (8:00 - 10:00) 8/10/2021 (AM) 08/10/2021
Corrections:


Miscellaneous/Other
Comment Only
08/10/2021
Zone 2 , 4th floor … last 2 units of shear and hallway fire stops.. approved

Progress Inspection Partial Pass 8/18/2021 (8:00 - 10:00) 8/18/2021 (AM) 08/18/2021
Corrections:


Miscellaneous/Other
Comment Only
08/18/2021
Zone 2, 3rd floor units shear walls… approved

Framing Inspection Passed 08/20/2021
Corrections:


Miscellaneous/Other
Comment Only
08/20/2021
Remaining shear walls on the last 2 units of 3rd floor approved. First layer of gypsum at inside of elevator front wall… approved. Mechanical shaft inside layer gypsum of 2nd floor …. Approved

Progress Inspection Partial Pass 8/25/2021 (8:00 - 10:00) 8/25/2021 (AM) 08/25/2021
Corrections:


Miscellaneous/Other
Comment Only
08/25/2021
Tip in panels to mechanical shaft on floors 2-4… approved Trash chute inner gypsum of wall.. approved, pending fire caulking at chute penetration. Elevator shaft fire stops inside shaft… approved 2nd floor shear walls… approved

Progress Inspection Partial Pass 8/27/2021 (8:00 - 10:00) 8/27/2021 (AM) 08/27/2021
Corrections:


Miscellaneous/Other
Comment Only
08/27/2021
Zone 2, 2nd floor units shear walls. Fire stop at trash chutes on floors 1,3, & 4 approved. See outstanding comments for correction.

Miscellaneous/Other
Outstanding
08/27/2021
Fire stop trash chutes on 2nd floor. Reinspection needed to verify.

Progress Inspection Partial Pass 8/31/2021 (10:00 - 12:00) 8/31/2021 (AM) 08/31/2021
Corrections:


Miscellaneous/Other
Comment Only
08/31/2021
Inner first layer of gypsum at 1st floor mechanical shaft zone 2…approved First layer gypsum at east stair… approved, pending the corrections marked on sheets. Shear walls in 2 units of fist floor.. approved

Progress Inspection Partial Pass 11/2/2021 (8:00 - 10:00) 11/2/2021 (AM) 11/02/2021
Corrections:


Miscellaneous/Other
Comment Only
11/02/2021
Zone 1, 4th floor units checked for final… approved

Progress Inspection Partial Pass 11/04/2021
Corrections:


Miscellaneous/Other
Comment Only
11/04/2021
Zone 1 floors 2 & 3, units checked for future final… approved

Progress Inspection Partial Pass 11/5/2021 (8:00 - 10:00) 11/5/2021 (AM) 11/05/2021
Corrections:


Miscellaneous/Other
Comment Only
11/05/2021
Zone 1, first floor units checked for final… approved Garage has been checked for fire stops at penetrations.

Lighting Inspection Passed 11/05/2021
Underneath parking garage passed inspection - completed on 11/05/2021. NMJ
Progress Inspection Partial Pass 11/8/2021 (8:00 - 10:00) 11/8/2021 (AM) 11/08/2021
Corrections:


Miscellaneous/Other
Comment Only
11/08/2021
Zone 2, floors 3&4 checked for final.

Progress Inspection Partial Pass 11/9/2021 (8:00 - 10:00) 11/9/2021 (AM) 11/09/2021
Corrections:


Miscellaneous/Other
Comment Only
11/09/2021
Zone 2, units on first and second floor approved for future final, pending …. See outstanding comments for inspection and correction.

Miscellaneous/Other
Outstanding
11/09/2021
1) electrical and data rooms to be viewed again for fire stops as needed and seen at inspection. 2) units on first floor need CO2 detectors installed in magic pac closets.

Progress Inspection Passed 11/18/2021 (10:00 - 12:00) 11/18/2021 (AM) 11/18/2021
Corrections:


Miscellaneous/Other
Comment Only
11/18/2021
Viewed the deckers and installation at main level… approved CO2 detectors installed in magic pac closets…. Approved

Building Final Inspection Passed 11/29/2021 (8:00 - 10:00) 11/29/2021 (AM) 11/29/2021
Corrections:


Miscellaneous/Other
Comment Only
11/29/2021
Accessibility signage in garage is approved for the height placed at due to the bike rack installation and arrangement of parking stalls. Building final approved for this permit and building, pending fire final for signs depicting “ no parking in fire lane” .

Fire Inspection Final Passed w/ Conditions 11/29/2021