PRBD202005494
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 8/25/2020 (10:00 - 12:00) | 8/25/2020 (AM) | 08/25/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/25/2020
Strip footings at lines 10A to15A On grid Da
Strip footings at grid Aa , lines 10a to 15a.
Hook bars hare approved to wet stick per design professional
Approved for concrete placement
|
||||
Footing Inspection | Partial Pass | 8/26/2020 (12:30 - 2:30) | 8/26/2020 (PM) | 08/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/26/2020
Line 15A from grids Aa to Da. Two CF7-0 pads included in this strip footing run. Approved for concrete placement.
|
||||
Footing Inspection | Not Ready | 8/27/2020 (12:30 - 2:30) | 8/27/2020 (PM) | 08/27/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/27/2020
Inspection canceled due to rebar not yet onsite.
|
||||
Footing Inspection | Partial Pass | 8/28/2020 (12:30 - 2:30) | 8/28/2020 (PM) | 08/28/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/28/2020
Line Da grids 2a to 10a strip footings.
Pad footings on grid Ba at lines, 11a, 12a, 14a footings and pads inclusive to grid 13a.
Approved for concrete placement.
|
||||
Footing Inspection | Not Ready | 8/31/2020 (12:30 - 2:30) | 8/31/2020 (PM) | 08/31/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/31/2020
Inspection canceled
|
||||
Footing Inspection | Partial Pass | 9/1/2020 (12:30 - 2:30) | 9/1/2020 (PM) | 09/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/01/2020
Elevator pit just off grid Aa at line 7a.5 . Bentonite, and rebar , and drain pipe... approved.
Trash enclosure footings at S.E. Location... approved
|
||||
Footing Inspection | Not Ready | 9/2/2020 (12:30 - 2:30) | 9/2/2020 (PM) | 09/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/02/2020
Footings not ready for inspection, inspection canceled.
|
||||
Footing Inspection | Not Ready | 9/3/2020 (12:30 - 2:30) | 9/3/2020 (PM) | 09/03/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/03/2020
Footing inspection again canceled, no footings ready for inspection
|
||||
Footing Inspection | Not Ready | 9/4/2020 (12:30 - 2:30) | 9/4/2020 (PM) | 09/04/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/04/2020
Site visit, only block walls being placed. No footing crew onsite for any footings to be placed.
|
||||
Footing Inspection | Partial Pass | 9/8/2020 (12:30 - 2:30) | 9/8/2020 (PM) | 09/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/08/2020
Poured walls at elevator on line 7a.5, grid Aa.5.
Section of strip footing off grid Da, line 2a.
Approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 9/9/2020 (12:30 - 2:30) | 9/9/2020 (PM) | 09/09/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/09/2020
Strip footings and 2 pads on one 1a, grids Da to Aa.
Remaining strip footing on grid Da from 1a to 2a.
Approved for concrete placement
|
||||
Footing Inspection | Not Ready | 9/10/2020 (12:30 - 2:30) | 9/10/2020 (PM) | 09/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/10/2020
Inspection canceled, not ready with any new footings.
|
||||
Footing Inspection | Passed | 9/11/2020 (12:30 - 2:30) | 9/11/2020 (PM) | 09/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/11/2020
7 pad footings inspected and marked on plans for today’s inspection... approved for concrete placement
|
||||
Footing Inspection | Partial Pass | 9/15/2020 (12:30 - 2:30) | 9/15/2020 (PM) | 09/15/2020 |
Corrections:
Miscellaneous/Other
Outstanding
09/15/2020
Strip footings at grid Aa lines 1a to 10a. Approved
|
||||
Footing Inspection | Partial Pass | 9/16/2020 (12:30 - 2:30) | 9/16/2020 (PM) | 09/16/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/16/2020
4 pads and strip footings from lines 6a.8 to 10a , grids Aa to Ba.
Approved for concrete placement
|
||||
Footing Inspection | Partial Pass | 9/17/2020 (12:30 - 2:30) | 9/17/2020 (PM) | 09/17/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/17/2020
Remaining strip footings off line 3a to 4a and pad footings on grid Ba from lines 2a to 6a. Approved for concrete placement
|
||||
Footing Inspection | Partial Pass | 9/18/2020 (12:30 - 2:30) | 9/18/2020 (PM) | 09/18/2020 |
Corrections:
Miscellaneous/Other
Comment Only
09/18/2020
3 pads on grid Ca, lines 6a,7a, and 8a... approved for concrete placement
|
||||
Progress Inspection | Partial Pass | 10/08/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/08/2020
Foundation waterproofing and R/10 insulation , and draintile at remainder of East and west wall for the first 4ft high lift .... approved
|
||||
Progress Inspection | Partial Pass | 10/15/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/15/2020
Perimeter strip footings west of grid “A” between grids 7a to just past 9 A. Approved for concrete placement
|
||||
Progress Inspection | Partial Pass | 10/26/2020 (7:00 - 8:00) | 10/26/2020 (AM) | 10/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/26/2020
First floor SW stair shaft at building A ... first outer layer of gypsum covering approved
|
||||
Progress Inspection | Partial Pass | 10/27/2020 (7:00 - 8:00) | 10/27/2020 (AM) | 10/27/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/27/2020
2nd layer of gypsum at SW 1st level stair shaft exterior... approved
|
||||
Progress Inspection | Partial Pass | 11/06/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/06/2020
2nd floor south stair shaft, 1st outer layer of gypsum...approved
|
||||
Progress Inspection | Partial Pass | 11/18/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/18/2020
Center stair and trash chute at floor 2 , first layer outer gypsum... approved
|
||||
Progress Inspection | Partial Pass | 12/02/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
12/02/2020
Slab on grade poly at stairwell ... approved
Elevator shaft outer gypsum 1st. layer and adjacent shaft at 3rd floor... approved.
|
||||
Progress Inspection | Partial Pass | 12/10/2020 (12:30 - 2:30) | 12/10/2020 (PM) | 12/10/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/10/2020
4th floor south and center stairs outer 1st layer gypsum... approved
|
||||
Progress Inspection | Not Ready | 12/15/2020 (12:30 - 2:30) | 12/15/2020 (PM) | 12/15/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/15/2020
Not ready for inspection
|
||||
Framing Inspection | Partial Pass | 12/31/2020 (12:30 - 2:30) | 12/31/2020 (PM) | 12/31/2020 |
Corrections:
Miscellaneous/Other
Carried Forward
01/20/2021
Went over individual encasement of structural steel . This structural steel has to be individually encased before and finishes are installed. Some framing will need to be moved to do so.
|
||||
Miscellaneous/Other
Comment Only
12/31/2020
Viewed Roof dabbit framing , as per design. Approved
|
||||
Framing Inspection | Partial Pass | 1/20/2021 (12:30 - 2:30) | 1/20/2021 (PM) | 01/20/2021 |
Corrections:
Miscellaneous/Other
Outstanding
12/31/2020
Went over individual encasement of structural steel . This structural steel has to be individually encased before and finishes are installed. Some framing will need to be moved to do so.
|
||||
Miscellaneous/Other
Comment Only
01/20/2021
Building “A” zone 1 floors 1-4 elevator shaft, mechanical and trash shafts... framing and firestops approved.
|
||||
Insulation Inspection | Partial Pass | 1/22/2021 (12:30 - 2:30) | 1/22/2021 (PM) | 01/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/22/2021
Insulation and Poly at fourth floor, zone one magic packs approved.
|
||||
Framing Inspection | Partial Pass | 1/28/2021 (8:00 - 10:00) | 1/28/2021 (AM) | 01/28/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
01/28/2021
Went over individual encasement of structural steel . This structural steel has to be individually encased before and finishes are installed. Some framing will need to be moved to do so.
|
||||
Miscellaneous/Other
Comment Only
01/28/2021
Building “A” zone 14th floor... units, hallway, and common areas. Framing and firestops... approved
|
||||
Insulation Inspection | Partial Pass | 2/2/2021 (2:30 - 3:30) | 2/2/2021 (PM) | 02/02/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/02/2021
Building “A” zone 1 , fourth floor insulation/poly at exterior walls, and stair “C” framing and firestops, floors 3&4... approved
|
||||
Progress Inspection | Partial Pass | 2/3/2021 (12:30 - 2:30) | 2/3/2021 (PM) | 02/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/03/2021
Building “A” zone one floor 3, 6 units marked for framing and firestops approved pending correction of gusset plates for two floor trusses and correct bearing at triple microlam. Will reinspect these two units at next inspection. 1st layer of gypsum at 4th floor ceilings of 5 units approved for the 1hour assembly.
|
||||
Progress Inspection | Partial Pass | 2/4/2021 (10:00 - 12:00) | 2/4/2021 (AM) | 02/04/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/04/2021
Building “A” zone 1, 3rd floor. Remaining units and hallway including up to elevator , framing and firestops... approved.
Note... electrical room was not inspected, this is to be looked over when room is completed.
|
||||
Progress Inspection | Partial Pass | 2/5/2021 (Morning) | 2/5/2021 (AM) | 02/05/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/05/2021
Progress... steel columns on first level are being wrapped with gypsum as per the UL assembly provided. Will recheck when they are done.
Zone one forth floor rated ceilings... patching where gypsum was broken out is done, ok to second layer the units looked at.
|
||||
Insulation Inspection | Passed | 2/10/2021 (8:00 - 10:00) | 2/10/2021 (AM) | 02/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
Insulation approved.
|
||||
Insulation Inspection | Partial Pass | 02/10/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
Insulation and poly at units 301-306... approved.
Shear walls at units 401,02,& 04 checked. Went over shear walls with contractor, screws set between sheets at middle of seam and broken out edges don’t count in shear. Correct fastening and make sure screws are not set to deep.
Shear walls to be rechecked at next inspection.
|
||||
Framing Inspection | Partial Pass | 2/12/2021 (8:00 - 10:00) | 2/12/2021 (AM) | 02/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/12/2021
Framing and firestops on 2nd floor zone1.. approved pending marked corrections at units, see card at entry.
4th floor shear walls... approved
|
||||
Framing Inspection | Partial Pass | 2/22/2021 (8:00 - 10:00) | 2/22/2021 (AM) | 02/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/22/2021
Building “A” first floor units and hallway and upper portion of common area of entry. Framing and firestops... approved pending som minor framing corrections given to contractor.
|
||||
Insulation Inspection | Partial Pass | 2/23/2021 (8:00 - 10:00) | 2/23/2021 (AM) | 02/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/23/2021
Insulation on floor 2 units 200 - 205
Shear walls on 3rd floor, units 300-308
Framing and firestops at entry of zone 1.
Approved
|
||||
Insulation Inspection | Partial Pass | 3/8/2021 (8:00 - 10:00) | 3/8/2021 (AM) | 03/08/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/08/2021
Shear walls at 2nd floor zone 1.
Insulation/ poly partial approved on 1st floor zone 1.
Fire caulking at plumbing membrane penetrations of units floors1-4 zone 1.
Approved.
|
||||
Housewrap Inspection | Passed | 03/09/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/09/2021
This building is fully Housewrapped and sealed.
|
||||
Insulation Inspection | Partial Pass | 03/09/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/09/2021
1st floor zone 1 exterior wall insulation/poly... approved
|
||||
Framing Inspection | Partial Pass | 3/12/2021 (8:00 - 10:00) | 3/12/2021 (AM) | 03/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2021
Membrane firestops of the missed locations on 3rd and 4th floor of zone1 ... approved.
Framing and firestops of zone 2, 4th floor.
Stairwell with shaft at hallway from 1st to 4th... approved
|
||||
Progress Inspection | Partial Pass | 3/18/2021 (12:30 - 2:30) | 3/18/2021 (PM) | 03/18/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/18/2021
Insulation/poly4th floor zone 1.
1st floor zone 1 shear walls and fire stops at common area of entry, rooms and cooridor.
Approved
|
||||
Framing Inspection | Partial Pass | 3/19/2021 (8:00 - 10:00) | 3/19/2021 (AM) | 03/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/19/2021
Zone 2, 3rd floor framing and firestops... approved pending corrections given to contractor.
|
||||
Framing Inspection | Partial Pass | 3/22/2021 (8:00 - 10:00) | 3/22/2021 (AM) | 03/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/22/2021
4th floor zone 2, first layer of gypsum at rated ceiling approved in units.
|
||||
Progress Inspection | Partial Pass | 3/23/2021 (12:30 - 2:30) | 3/23/2021 (PM) | 03/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/23/2021
1st layer of gypsum board at ceilings of remaking units of 4th floor zone2.... approved
|
||||
Progress Inspection | Partial Pass | 03/25/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/25/2021
Zone 2 , floors 1&2 framing and firestops in hallways and units ... approved pending some framing corrections marked at units.reinspection of corrections to follow prior to insulation.
|
||||
Insulation Inspection | Partial Pass | 3/26/2021 (10:00 - 12:00) | 3/26/2021 (AM) | 03/26/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/26/2021
Zone 2 third floor insulation and poly.
Viewed 3 units of shear walls on zone 2 forth floor.
Corrections to framing and plumbing firestops at zone 2 first and second floors.
Approved.
|
||||
Progress Inspection | Partial Pass | 3/31/2021 (8:00 - 10:00) | 3/31/2021 (AM) | 03/31/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/31/2021
Shear wall of Remaining units on 4th floor zone 2 ... approved
|
||||
Insulation Inspection | Partial Pass | 4/2/2021 (10:00 - 12:00) | 4/2/2021 (AM) | 04/02/2021 |
changed time per Jon, thx. 3/31/21 | ||||
Corrections:
Miscellaneous/Other
Comment Only
04/02/2021
Insulation/poly to units on 2nd floor zone 2....approved
|
||||
Framing Inspection | Partial Pass | 04/06/2021 | ||
Corrections:
Miscellaneous/Other
Resolved
04/06/2021
Went over individual encasement of structural steel . This structural steel has to be individually encased before and finishes are installed. Some framing will need to be moved to do so.
|
||||
Miscellaneous/Other
Comment Only
04/06/2021
4th floor center stair and shafts. Outer 1st layer of gypsum... approved.
|
||||
Progress Inspection | Partial Pass | 4/9/2021 (8:00 - 10:00) | 4/9/2021 (AM) | 04/09/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/09/2021
Zone 2 ,3rd floor shear walls... approved
|
||||
Insulation Inspection | Partial Pass | 4/14/2021 (8:00 - 10:00) | 4/14/2021 (AM) | 04/14/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/14/2021
Insulation/ poly at units on first floor zone 2... approved
|
||||
Progress Inspection | Partial Pass | 04/16/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/16/2021
Zone 2, second floor units. Shear walls approved
|
||||
Structural Inspection | Not Ready | 4/19/2021 (8:00 - 10:00) | 4/19/2021 (AM) | 04/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2021
Not ready for inspection in building ”A”.
|
||||
Structural Inspection | Partial Pass | 4/26/2021 (8:00 - 10:00) | 4/26/2021 (AM) | 04/26/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/26/2021
1) Viewed 3 units with sheer walls in zone 1 of 1st floor.
2) Saw firestops in basement of through penetrations, review of the firestops needed and reinspection of them.
3) went over tip in walls, need to see these installed at next inspection.
|
||||
Progress Inspection | Partial Pass | 4/27/2021 (8:00 - 10:00) | 4/27/2021 (AM) | 04/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2021
Shear walls in units of zone 2 level 1. All units viewed approved, except for the incomplete units 15,17,&18. These units to be checked at next inspection.
|
||||
Structural Inspection | Partial Pass | 4/28/2021 (10:00 - 12:00) | 4/28/2021 (AM) | 04/28/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/28/2021
Remaining shear walls on installation floor zone 2 units... approved
Tip in wall at 3rd floor mechanical shaft ... approved
|
||||
Progress Inspection | Partial Pass | 05/04/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/04/2021
Floors 1&2 north end mechanical shaft tip in walls... approved
|
||||
Progress Inspection | Partial Pass | 06/02/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/02/2021
Viewed elevator front wall first layer of gypsum inside the shaft of 2nd floor...approved
|
||||
Footing Inspection | Passed | 06/04/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/04/2021
16 pier footings with rebar cage... approved
|
||||
Progress Inspection | Partial Pass | 06/04/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/04/2021
First layer gypsum of front infill wall at inside of shaft. All floors... approved
|
||||
Progress Inspection | Partial Pass | 06/09/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
06/09/2021
Elevator shaft front wall inside of shaft gypsum and firestops from floors 2-4… approved
|
||||
Building Final Inspection | Partial Pass | 7/15/2021 (10:00 - 12:00) | 7/15/2021 (AM) | 07/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/15/2021
Went through zone 1 units floors 1-4. All accessibility, exiting and life safety, approved.
Trades inspections of zone one to also be completed.
|
||||
Progress Inspection | Passed w/ Conditions | 7/23/2021 (8:00 - 10:00) | 7/23/2021 (AM) | 07/23/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/23/2021
E.M. Lighting tested and approved, pending the addition of lighting in each stairway at the first level entry point towards the underground parking.
|
||||
Progress Inspection | Partial Pass | 8/5/2021 (8:00 - 10:00) | 8/5/2021 (AM) | 08/05/2021 |
Corrections:
Miscellaneous/Other
Comment Only
08/05/2021
Zone 2 common areas and units approved for inal pending small list of corrections given to contractor to complete in a couple units and electrical rooms.
|
||||
Building Final Inspection | Passed | 8/20/2021 (10:00 - 12:00) | 8/20/2021 (AM) | 08/20/2021 |
Corrections:
Miscellaneous/Other
Comment Only
08/20/2021
All trades finals given and approved. Elevator final given by the state. Building final for this 1926 addressed building… approved.
|
||||
Fire Inspection Final | Passed | 08/20/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/20/2021
Exiting and extinguishers, fire sprinklers , alarms, and all testing, routes and Knox box… verified. Final approved as per directive from Kris K. Fire inspector.
|
||||
Lighting Inspection | Passed | 08/20/2021 | ||
Landscaping Inspection | Passed | 08/20/2021 |