Permit Application Status

PRBD202006031


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202006031
Building
Issued
BLOOMINGTON H R A
Alteration/Repair/Replace
Not Required
Roadway modifications & construction to accommodate new transit bus stations and handicap accessible sidewalks/ramps. Work includes utilities, electrical, and signage as well. A mechanical restroom building renovation will also be part of the construction.
06/12/2020
08/07/2020
06/15/2022

Locations

Permits

Permit Number: PRBD202006031

Building
Expired

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Gypsum Board/Sheet Rock Inspection Pending
Lath Inspection Pending
Insulation Inspection Pending
Above Ceiling Inspection Pending
Footing Inspection Partial Pass 9/21/2020 (10:00 - 12:00) 9/21/2020 (AM) 09/21/2020
Miscellaneous/Other
Comment Only
09/21/2020
120’ of footing and rebar with all wall rebar in place as per plan design. Located on north corner of amercan boulevard. Approved for concrete placement.

Footing Inspection Partial Pass 12/28/2020 (8:00 - 10:00) 12/28/2020 (AM) 12/28/2020
Footing Inspection Passed 1/6/2021 (8:00 - 10:00) 1/6/2021 (AM) 01/06/2021
Framing Inspection Passed 12/15/2021 (Afternoon) 12/15/2021 (PM) 12/15/2021
Miscellaneous/Other
Comment Only
12/15/2021
Assembly of this structure is per design and complies with the approved plans.

Building Final Inspection Passed 12/15/2021 (Afternoon) 12/15/2021 (PM) 12/15/2021
Miscellaneous/Other
Comment Only
12/15/2021
Final for this scope of work is per the approved plans. Final for this permit approved.

Fire Inspection Final Passed 12/15/2021 (Afternoon) 12/15/2021 (PM) 12/17/2021