PRBD202007299
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Above Ceiling Inspection | Pending | |||
Insulation Inspection | Pending | |||
Lath Inspection | Pending | |||
Gypsum Board/Sheet Rock Inspection | Pending | |||
Footing Inspection | Pending | |||
Footing Inspection | Partial Pass | 8/19/2020 (10:00 - 12:00) | 8/19/2020 (AM) | 08/19/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2020
Line 1.A and 1.B the whole 80 ft. run of footing and rebar. Wall rebar and pier bar, tied as well, and as per shop drawings. Approved for concrete placement.
|
||||
Footing Inspection | Passed | 8/26/2020 (10:00 - 12:00) | 8/26/2020 (AM) | 08/26/2020 |
Corrections:
Miscellaneous/Other
Comment Only
08/26/2020
Footings on south end of the 1.B and 1.A approved as per rebar shops. Wall rebar on both sets of footings also installed per the rebar shops. Approved for concrete placement.
|
||||
Framing Inspection | Passed | 12/15/2021 (Afternoon) | 12/15/2021 (PM) | 12/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/15/2021
Structures are built as per design and approved plans.
|
||||
Building Final Inspection | Passed | 12/15/2021 (Afternoon) | 12/15/2021 (PM) | 12/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/15/2021
Completed as per the approved plans and design. Final for this permit approved.
|