PRBD202008326
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 10/1/2020 (12:30 - 2:30) | 10/1/2020 (PM) | 10/01/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/01/2020
Viewed draintile system in lower level, approved to dowel slab bars and place concrete
|
||||
Framing Inspection | Partial Pass | 10/8/2020 (8:00 - 10:00) | 10/8/2020 (AM) | 10/08/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/08/2020
Exterior wall furred framing on 2dnd floor approved... ok to spray foam, and cover.
|
||||
Framing Inspection | Partial Pass | 10/16/2020 (12:30 - 2:30) | 10/16/2020 (PM) | 10/16/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/16/2020
Exterior wall furred framing on 1st floor and spray foam at exterior walls on 2nd. DC315 Fire protectant was sprayed at the exposed foam in the above ceiling plenum area.... approved
|
||||
Framing Inspection | Passed | 10/21/2020 (12:30 - 2:30) | 10/21/2020 (PM) | 10/21/2020 |
Corrections:
Miscellaneous/Other
Comment Only
10/21/2020
Wall Framing west of stairway. Approved
|
||||
Framing Inspection | Partial Pass | 11/2/2020 (8:00 - 10:00) | 11/2/2020 (AM) | 11/02/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/02/2020
First floor walls approved.
Dead spaces to remain open for inspection of firestops.
|
||||
Framing Inspection | Partial Pass | 11/13/2020 (8:00 - 10:00) | 11/13/2020 (AM) | 11/13/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/13/2020
Approved to cover soffit and chase walls, firestops also approved .
|
||||
Framing Inspection | Partial Pass | 11/19/2020 (12:30 - 2:30) | 11/19/2020 (PM) | 11/19/2020 |
Corrections:
Miscellaneous/Other
Comment Only
11/19/2020
Wall Framing in basement approved
|
||||
Fire Inspection Final | Not Ready | 12/1/2020 (8:00 - 10:00) | 12/1/2020 (AM) | 12/01/2020 |
Framing Inspection | Partial Pass | 1/5/2021 (8:00 - 10:00) | 1/5/2021 (AM) | 01/05/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/05/2021
Drift house enclosure at roof... framing and fastening to roof and supporting bar joists is as per design.
|
||||
Progress Inspection | Partial Pass | 2/10/2021 (8:00 - 10:00) | 2/10/2021 (AM) | 02/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
Ceiling framing and above ceiling for basement, first and send floors... approved
|
||||
Progress Inspection | Passed w/ Conditions | 03/18/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/18/2021
Client services room being remodeled on first floor ... above ceiling and ceiling installation approved, pending corrections of the ceiling grid being supported off the ducting and its supports. Ceiling cannot be supported off the ducting or it’s supports, installer to add independent support and retire support wiring to that independent support.
|
||||
Building Final Inspection | Partial Pass | 3/26/2021 (8:00 - 10:00) | 3/26/2021 (AM) | 03/26/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
03/26/2021
1)Sac charges to be addressed.
2) install accessibility signage to bathrooms
3) sprinkler head in basement needs to be 4” from partition wall... address accordingly.
|
||||
Miscellaneous/Other
Comment Only
03/26/2021
First phase inspected and approved for temp final. See outstanding comments for corrections.
|
||||
Fire Inspection Final | Partial Pass | 3/26/2021 (8:00 - 10:00) | 3/26/2021 (AM) | 03/29/2021 |
Fire Inspection Final | Passed | 04/20/2021 | ||
Building Final Inspection | Passed | 04/20/2021 | ||
Corrections:
Miscellaneous/Other
Resolved
04/20/2021
1)Sac charges to be addressed.
2) install accessibility signage to bathrooms
3) sprinkler head in basement needs to be 4” from partition wall... address accordingly.
|
||||
Miscellaneous/Other
Comment Only
04/20/2021
Accessibility completed, and partition was moved to maintain clearance for sprinkler coverage. Dampers were checked with system and with mechanical final, see associated mechanical permit for this project. Final approved for this permit and scope of work.
|
||||
Miscellaneous/Other
Comment Only
04/20/2021
Accessibility completed, and partition was moved to maintain clearance for sprinkler coverage. Dampers were checked with system and with mechanical final, see associated mechanical permit for this project. Final approved for this permit and scope of work.
|
||||
Miscellaneous/Other
Comment Only
04/20/2021
Accessibility completed, and partition was moved to maintain clearance for sprinkler coverage. Dampers were checked with system and with mechanical final, see associated mechanical permit for this project. Final approved for this permit and scope of work.
|