Summary

PRBD202008942
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
A retail tenant improvement within the Mall of America Includes demolition and new construction with MEP engineering.
08/13/2020
10/08/2020
06/20/2021
12/22/2020

Locations

Permits

Permit Number: PRBD202008942

Building
Finaled
10/08/2020
06/20/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 10/21/2020 (8:00 - 10:00) 10/21/2020 (AM) 10/21/2020
Corrections:


Miscellaneous/Other
Comment Only
10/21/2020
Framing of soffits and perimeter column wraps, and built up floor platform... approved

Framing Inspection Passed w/ Conditions 10/28/2020 (12:30 - 2:30) 10/28/2020 (PM) 10/28/2020
Corrections:


Miscellaneous/Other
Comment Only
10/28/2020
Fireproofing patching, approved Back room framing and firestops... approved

Miscellaneous/Other
Outstanding
10/28/2020
Need to verify 3 fire collars at underside of piping at back room plumbing. Plumbing Contractor to provide pictures where inaccessible to view.

Progress Inspection Passed 11/13/2020 (8:00 - 10:00) 11/13/2020 (AM) 11/13/2020
Corrections:


Miscellaneous/Other
Comment Only
11/13/2020
Above ceiling in back room .... approved to close up

Fire Inspection Final Partial Pass 11/25/2020 (10:00 - 12:00) 11/25/2020 (AM) 11/25/2020
Corrections:


Miscellaneous/Other
Comment Only
11/25/2020
Partial final approved for temp c/o of store. Store front decorations/display has yet to be approved and installed and needs final inspections.

Building Final Inspection Partial Pass 11/25/2020 (10:00 - 12:00) 11/25/2020 (AM) 11/25/2020
Corrections:


Miscellaneous/Other
Comment Only
11/25/2020
Exit door corrected. Still need to inspect storefront when it get completed. Approved for a temp C.O. And for opening on Black Friday. Final to follow web all work is completed.

Building Final Inspection Passed 12/22/2020 (12:30 - 2:30) 12/22/2020 (PM) 12/22/2020
Corrections:


Miscellaneous/Other
Comment Only
12/22/2020
Exterior is completed, final for this permit approved

Fire Inspection Final Passed 12/22/2020 (12:30 - 2:30) 12/22/2020 (PM) 12/22/2020