Permit Application Status

PRBD202009438


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202009438
Building
Expired
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
INTERIOR TENANT BUILD OUT OF A RETAIL SPACE WITHIN EXISTING MALL (Phase 2)
08/24/2020
10/27/2020
10/13/2021

Locations

Permits

Permit Number: PRBD202009438

Building
Expired
10/27/2020
10/13/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Inspection Final Pending
Framing Inspection Partial Pass 11/2/2020 (8:00 - 10:00) 11/2/2020 (AM) 11/02/2020
Corrections:


Miscellaneous/Other
Comment Only
11/02/2020
Soffit faces and one side walls approved to cover.

Framing Inspection Partial Pass 11/17/2020 (8:00 - 10:00) 11/17/2020 (AM) 11/17/2020
Corrections:


Miscellaneous/Other
Comment Only
11/17/2020
All wall framing except where not completed at storefronts... approved. Ceiling framing , fireproofing, firestops, and building above ceiling, for hard lids has been inspected and where access panels are needed, diffusers will be located in place of panels to allow for electrical and HVAC maintenance. Ceilings are not to be covered until electrical, HVAC, and sprinkler has done their inspections and given approval.

Framing Inspection Partial Pass 12/22/2020 (8:00 - 10:00) 12/22/2020 (AM) 12/22/2020
Corrections:


Miscellaneous/Other
Comment Only
12/22/2020
Firesafeing at 2nd floor, at exterior wall along Nickelodeon... approved

Framing Inspection Partial Pass 1/14/2021 (10:00 - 12:00) 1/14/2021 (AM) 01/14/2021
Corrections:


Miscellaneous/Other
Comment Only
01/14/2021
Framing in office area of first level... approved Provide access panel in ceiling for boxes and equipment above.

Above Ceiling Inspection Partial Pass 1/25/2021 (8:00 - 10:00) 1/25/2021 (AM) 01/25/2021
Corrections:


Miscellaneous/Other
Comment Only
01/25/2021
2nd level above ceiling approved, pending the outstanding comments listed for completion and corrections.

Miscellaneous/Other
Carried Forward
01/25/2021
1) complete sprinkler coverage at back of house, and at entry from back of house,(2nd floor). 2) card reader electrical box at back entry 2nd level corridor to be rated or protected to match wall rating.

Progress Inspection Failed 4/7/2021 (7:00 - 8:00) 4/7/2021 (AM) 04/07/2021
Meeting with Kris for a smoke test?
Corrections:


Miscellaneous/Other
Comment Only
04/07/2021
Smoke test performed. Evacuation of smoke crossed into and through another zone and into the mall common area. System is an existing system and needs to be fine tuned to contain smoke from migrating over. System design to be addressed by a design professional and programmed to function correctly. Retest of system needed with city to verify functionality.

Building Final Inspection Partial Pass 4/8/2021 (2:30 - 3:30) 4/8/2021 (PM) 04/08/2021
Corrections:


Miscellaneous/Other
Carried Forward
04/08/2021
1) mirror heights in 2nd floor bathrooms to be 40” max to reflective edge from finished floor. 2) protect column in elevator room. 3) 1st level exit to Nicolodeon.... correct stair height at first step and raise handrail to 34-38”. 4) complete roof ramp and railing from exit at roof. 5) elevator finals needed, send to city for record retention. 6) smoke test to performed when all systems have been adjusted and pre tested. 7) all trades permits to be closed out for final.

Miscellaneous/Other
Comment Only
04/08/2021
See outstanding comments for corrections and for final. Approved for stock and training.

Building Final Inspection Partial Pass 4/14/2021 (12:30 - 2:30) 4/14/2021 (PM) 04/14/2021
Corrections:


Miscellaneous/Other
Carried Forward
04/14/2021
1) mirror heights in 2nd floor bathrooms to be 40” max to reflective edge from finished floor. 2) protect column in elevator room. 3) 1st level exit to Nicolodeon.... correct stair height at first step and raise handrail to 34-38”. 4) complete roof ramp and railing from exit at roof. 5) elevator finals needed, send to city for record retention. 6) smoke test to performed when all systems have been adjusted and pre tested. 7) all trades permits to be closed out for final.

Miscellaneous/Other
Comment Only
04/14/2021
Smoke test performed as per the designed system... Approved See outstanding comments with inspection of items at next inspection.

Building Final Inspection Passed w/ Conditions 04/16/2021
Corrections:


Miscellaneous/Other
Resolved
04/16/2021
1) mirror heights in 2nd floor bathrooms to be 40” max to reflective edge from finished floor. 2) protect column in elevator room. 3) 1st level exit to Nicolodeon.... correct stair height at first step and raise handrail to 34-38”. 4) complete roof ramp and railing from exit at roof. 5) elevator finals needed, send to city for record retention. 6) smoke test to performed when all systems have been adjusted and pre tested. 7) all trades permits to be closed out for final.

Miscellaneous/Other
Comment Only
04/16/2021
All corrections completed. Open permits to be followed up with the appropriate inspector and division. Final was approved and ok to occupy by fire inspector and EH inspector. Building final approved and ok to occupancy. Temp occupancy load signage is in place, change to permanent signage when those signs come in.