PRBD202011079
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Passed | 9/23/2020 (8:00 - 10:00) | 9/23/2020 (AM) | 09/23/2020 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/23/2020
Installation approved for this draintile system. Electrical permit, installation and inspection to be done by other contractor.
|
||||