PRBD202012644
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 11/13/2020 | ||
Corrections:
Miscellaneous/Other
Comment Only
11/13/2020
Footing slab epoxy coated rebar installation as per design... approved for concrete placement.
|
||||
Fire Inspection Final | Passed | 02/17/2023 | ||
Building Final Inspection | Passed | 02/17/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/17/2023
All inspections completed, final approved
|