PRBD202013191
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Pending | |||
Canceled 3/15 inspection - set to rain. Keeping 3.16 inspection | ||||
Above Ceiling Inspection | Pending | |||
Insulation Inspection | Pending | |||
Lath Inspection | Pending | |||
Gypsum Board/Sheet Rock Inspection | Pending | |||
Footing Inspection | Partial Pass | 3/17/2021 (10:00 - 12:00) | 3/17/2021 (AM) | 03/17/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/17/2021
Rebar for wall and piers tied into the rebar for footings. All bar is approved. Concrete is being pumped and will displace any water that is in footings at this time. Frost blankets are not needed since temperatures outside will not be a factor in concrete freezing.
Approved for concrete placement.
Call in for foundation inspection when ready.
|
||||
Framing Inspection | Passed | 7/21/2021 (8:00 - 10:00) | 7/21/2021 (AM) | 07/21/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/21/2021
All framing approved
|
||||
Progress Inspection | Passed | 10/6/2021 (8:00 - 10:00) | 10/6/2021 (AM) | 10/06/2021 |
Progress Inspection as per contractor. [Navarro\, Derly 2021-10-05T08:35:16-05:00] | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/06/2021
Progress inspection…
Viewed roof, metal edge covering to be completed.
Interior is at the finishes stage, need to have above ceiling/ framing inspection .
Complete building and call in inspections as needed.
|
||||
Lighting Inspection | Failed | 11/1/2021 | 11/1/2021 | 10/26/2021 |
BOA Parking lot and Security lighting | ||||
Fire Inspection Final | Passed w/ Conditions | 11/1/2021 (12:30 - 2:30) | 11/1/2021 (PM) | 11/01/2021 |
pass with the understanding owner will install address numbers and the contractor is working on installing the knox box | ||||
Building Final Inspection | Partial Pass | 11/1/2021 (12:30 - 2:30) | 11/1/2021 (PM) | 11/01/2021 |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2021
Temp CO approved.
See outstanding comments for final inspection
|
||||
Miscellaneous/Other
Carried Forward
11/01/2021
1) open trades permits to be final, ( will check with individual inspectors to verify)
2) install accessibility signage at both bathrooms and at parking stalls.
|
||||
Lighting Inspection | Passed | 11/2/2021 | 11/02/2021 | |
Building Final Inspection | Issue CO | 11/17/2021 (8:00 - 10:00) | 11/17/2021 (AM) | 11/17/2021 |
Corrections:
Miscellaneous/Other
Resolved
11/17/2021
1) open trades permits to be final, ( will check with individual inspectors to verify)
2) install accessibility signage at both bathrooms and at parking stalls.
|
||||
Miscellaneous/Other
Comment Only
11/17/2021
All work and corrections completed. Final for this permit and full C.O. approved .
|