PRBD202013425
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 2/10/2021 (10:00 - 12:00) | 2/10/2021 (AM) | 02/10/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
4C units and common areas checked for the future final... approved
|
||||
Progress Inspection | Passed | 3/25/2021 (12:30 - 2:30) | 02/10/2021 | |
Corrections:
Miscellaneous/Other
Comment Only
02/10/2021
Viewed fireproofing to structural steel located in loading dock where additional reinforcement was added for the space above....approved
|
||||
Framing Inspection | Partial Pass | 2/24/2021 (12:30 - 2:30) | 2/24/2021 (PM) | 02/24/2021 |
Corrections:
Miscellaneous/Other
Comment Only
02/24/2021
Back of house framing and firestops in wall., and fireproofing of posts... approved pending firestop of gray PVC pipe in corner,( provide photo to inspector).
|
||||
Progress Inspection | Partial Pass | 5/5/2021 (8:00 - 10:00) | 03/29/2021 | |
Corrections:
Miscellaneous/Other
Comment Only
03/29/2021
Fire proofing patching completed with Cafco hand patch to match existing coverage... Approved
|
||||
Framing Inspection | Partial Pass | 5/3/2021 (8:00 - 10:00) | 5/3/2021 (AM) | 05/03/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/03/2021
Progress framing of boxed in soffit areas approved. Call for trades inspections and complete all framing prior to next inspection.
|
||||
Progress Inspection | Partial Pass | 5/5/2021 (8:00 - 10:00) | 5/5/2021 (AM) | 05/05/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/05/2021
Ceilings in storefront approved to cover, except north and south soffits.
|
||||
Framing Inspection | Passed w/ Conditions | 6/7/2021 (8:00 - 10:00) | 6/7/2021 (AM) | 06/07/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/07/2021
Framing of storefront, knee walls, and firestops at plumbing... approved
Contractor to send pictures of firestops at elevator penetrations to inspector.
|
||||
Building Final Inspection | Failed | 7/22/2021 | 7/22/2021 (AM) | 07/22/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
07/22/2021
Complete finishes and installations, clean space and removal of equipment with construction use … all is required with a final occupancy.
Inspections with all trades to be completed as well.
The branding group is allowed to come in and set up space as work progresses, this is part of finishing the space.
Final not approved
|
||||
Fire Inspection Final | Failed | 7/22/2021 (8:00 - 10:00) | 7/22/2021 (AM) | 07/23/2021 |
Building Final Inspection | Partial Pass | 7/26/2021 (8:00 - 10:00) | 7/26/2021 (AM) | 07/26/2021 |
Corrections:
Miscellaneous/Other
Resolved
07/26/2021
Complete finishes and installations, clean space and removal of equipment with construction use … all is required with a final occupancy.
Inspections with all trades to be completed as well.
The branding group is allowed to come in and set up space as work progresses, this is part of finishing the space.
Final not approved
|
||||
Miscellaneous/Other
Comment Only
07/26/2021
Approval to stock, setup, and decorate space.
No opening to public yet, complete work and all trades inspections, environmental health requirements as well for final inspection.
|
||||
EH Progress Inspection | Passed w/ Conditions | 5/13/2021 (Morning) | 08/11/2021 | |
Building Final Inspection | Passed | 12/13/2022 |