PRBD202013783
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 12/11/2020 (8:00 - 10:00) | 12/11/2020 (AM) | 12/11/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/11/2020
This was a consultation visit to go over requirements with this buildout. Plans show Storefront with wood attached to framing...Storefront wall has to be built of steel stud framing and encapsulated on both sides with gypsum before any wood can be attached to the wall.
Went over firestops and rated assembly’s that also need to be patched in. Call for inspection when ready and trades have had their inspections.
|
||||
Framing Inspection | Partial Pass | 12/23/2020 (10:00 - 12:00) | 12/23/2020 (AM) | 12/23/2020 |
Corrections:
Miscellaneous/Other
Comment Only
12/23/2020
This inspection was to go over the store front detail as per the plan submitted. A chance had to be made due to the requirements of the mall. The plywood is now located outside the wall with gypsum behind it. This was approved by the design team so they could proceed with the framing and move forward with new finish dimensions for the exterior covering.
|
||||
Framing Inspection | Partial Pass | 1/11/2021 (8:00 - 10:00) | 1/11/2021 (AM) | 01/11/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/11/2021
Walls and ceilings, framing. Approved pending adding a stiff back and kicker to brace wall at hallway where studs are over notched.
This inspection does not include the storefront and the small section of ceiling that ties into front.
|
||||
Framing Inspection | Partial Pass | 1/22/2021 (8:00 - 10:00) | 1/22/2021 (AM) | 01/22/2021 |
Corrections:
Miscellaneous/Other
Comment Only
01/22/2021
Storefront wall and ceiling framing , not including the roll up door opening ... approved , ok to cover.
|
||||
Framing Inspection | Partial Pass | 01/29/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
01/29/2021
Platform framing and gypsum encasement at storefront of display area... approved.
|
||||
Framing Inspection | Passed | 3/1/2021 (8:00 - 10:00) | 3/1/2021 (AM) | 03/01/2021 |
Corrections:
Miscellaneous/Other
Comment Only
03/01/2021
Front rating at coiling door and the catwalk for the motor servicing approved.
|
||||
Fire Inspection Final | Passed | 3/4/2021 (10:00 - 12:00) | 3/4/2021 (AM) | 03/04/2021 |
Building Final Inspection | Partial Pass | 3/4/2021 (10:00 - 12:00) | 3/4/2021 (AM) | 03/04/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
03/04/2021
Complete the firestops at through penetrations at the inside portion of rated wall in storeroom. Call in for inspection of this for the full final.
|
||||
Miscellaneous/Other
Comment Only
03/04/2021
Approved for a temp final, with approval to stock and setup space. Accessibility is compliant within this space.
See outstanding comments for corrections and reinspection.
|
||||
Building Final Inspection | Passed | 3/5/2021 (12:30 - 2:30) | 3/5/2021 (PM) | 03/05/2021 |
Corrections:
Miscellaneous/Other
Resolved
03/05/2021
Complete the firestops at through penetrations at the inside portion of rated wall in storeroom. Call in for inspection of this for the full final.
|
||||
Miscellaneous/Other
Comment Only
03/05/2021
Final approved for this Building permit, corrections completed.
|