PRBD202015649
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 3/18/2021 (10:00 - 12:00) | 3/18/2021 (AM) | 03/18/2021 |
Progress Inspection | Passed | 4/1/2021 (12:30 - 2:30) | 4/1/2021 (PM) | 04/01/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/01/2021
Remaining framing approved.
|
||||
Progress Inspection | Passed | 4/29/2021 (8:00 - 10:00) | 4/29/2021 (AM) | 04/29/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/29/2021
Above ceiling inspection approved.
|
||||
Building Final Inspection | Issue TCO | 6/25/2021 (10:00 - 12:00) | 6/25/2021 (AM) | 06/25/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
06/25/2021
Need final fire, electrical, mechanical and health approvals. 30 day temporary CO approved.
|
||||
Fire Inspection Final | Passed | 7/22/2021 (10:00 - 12:00) | 7/22/2021 (AM) | 07/22/2021 |
Building Final Inspection | Passed | 7/22/2021 (10:00 - 12:00) | 7/22/2021 (AM) | 07/22/2021 |
Corrections:
Miscellaneous/Other
Resolved
07/22/2021
Need final fire, electrical, mechanical and health approvals. 30 day temporary CO approved.
|
||||
Lighting Inspection | Failed | 09/07/2021 | ||
Lighting Inspection | Passed | 12/22/2021 | 12/23/2021 | |