PRBD202015820
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Passed | 04/12/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/12/2021
4 thickened pads with #4 rebar 3 each way for steel supports at storefronts... viewed by photos, contractor didn’t call for city inspection, 3rd party inspection may have viewed these.
|
||||
Framing Inspection | Partial Pass | 4/12/2021 (10:00 - 12:00) | 4/12/2021 (AM) | 04/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/12/2021
Wall framing... approved
|
||||
Above Ceiling Inspection | Passed | 5/12/2021 (8:00 - 10:00) | 5/12/2021 (AM) | 05/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/12/2021
Ceiling framing, and platforms for damper service in ceilings, and above ceiling... approved and ok to cover.
|
||||
Building Final Inspection | Failed | 6/25/2021 (8:00 - 10:00) | 6/25/2021 (AM) | 06/25/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/25/2021
Not ready for final at this time, complete workin this space, and have all trades inspections completed prior to building final inspection.
|
||||
Fire Inspection Final | Not Ready | 6/25/2021 (8:00 - 10:00) | 6/25/2021 (AM) | 06/25/2021 |
Fire Inspection Final | Passed | 6/29/2021 (12:30 - 2:30) | 6/29/2021 (PM) | 06/29/2021 |
Building Final Inspection | Passed | 6/29/2021 (12:30 - 2:30) | 6/29/2021 (PM) | 06/29/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/29/2021
Final approved, ok to set up all wares and open for use.
|