Summary

PRBD202015820
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
THE SCOPE OF NEW WORK INCLUDES NEW MILLWORK & FINISHES. TRADES INCLUDE MECHANICAL & ELECTRICAL. NEW INTERIOR PARTITIONS.NEW SPRINKLER HEAD LOCATIONS. MINOR HVAC WORK INCLUDING NEW SUPPLY AND RETURN LOCATIONS, AND NEW DUCT BRANCHES. NEW INTERIOR STOREFRONT STONE PANEL SYSTEM
12/31/2020
03/31/2021
12/26/2021
06/29/2021

Locations

Permits

Permit Number: PRBD202015820

Building
Finaled
03/31/2021
12/26/2021

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Passed 04/12/2021
Corrections:


Miscellaneous/Other
Comment Only
04/12/2021
4 thickened pads with #4 rebar 3 each way for steel supports at storefronts... viewed by photos, contractor didn’t call for city inspection, 3rd party inspection may have viewed these.

Framing Inspection Partial Pass 4/12/2021 (10:00 - 12:00) 4/12/2021 (AM) 04/12/2021
Corrections:


Miscellaneous/Other
Comment Only
04/12/2021
Wall framing... approved

Above Ceiling Inspection Passed 5/12/2021 (8:00 - 10:00) 5/12/2021 (AM) 05/12/2021
Corrections:


Miscellaneous/Other
Comment Only
05/12/2021
Ceiling framing, and platforms for damper service in ceilings, and above ceiling... approved and ok to cover.

Building Final Inspection Failed 6/25/2021 (8:00 - 10:00) 6/25/2021 (AM) 06/25/2021
Corrections:


Miscellaneous/Other
Comment Only
06/25/2021
Not ready for final at this time, complete workin this space, and have all trades inspections completed prior to building final inspection.

Fire Inspection Final Not Ready 6/25/2021 (8:00 - 10:00) 6/25/2021 (AM) 06/25/2021
Fire Inspection Final Passed 6/29/2021 (12:30 - 2:30) 6/29/2021 (PM) 06/29/2021
Building Final Inspection Passed 6/29/2021 (12:30 - 2:30) 6/29/2021 (PM) 06/29/2021
Corrections:


Miscellaneous/Other
Comment Only
06/29/2021
Final approved, ok to set up all wares and open for use.