PRBD202100633
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 04/26/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/26/2021
Wall framing for exam room, office, etc. behind sales area ... approved to cover. Furred walls at demising walls ok to cover.
|
||||
Framing Inspection | Partial Pass | 4/27/2021 (8:00 - 10:00) | 4/27/2021 (AM) | 04/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/27/2021
Progress/information inspection...
Electrical boxes installed at the back of house rated cooridor wall to have putty packs installed to them and to be verified at inspection.
Electrical that is terminated in portion wall of adjoining space to be removed. Also to be verified at inspection... Told electrical contractor as well.
|
||||
Framing Inspection | Partial Pass | 4/28/2021 (12:30 - 2:30) | 4/28/2021 (PM) | 04/28/2021 |
Corrections:
Miscellaneous/Other
Comment Only
04/28/2021
Ceiling framing and above ceiling in back of sales area ( bathroom, breath room, exam, and office)... approved.... Pending trades inspections prior to covering.
|
||||
Framing Inspection | Passed | 5/6/2021 (12:30 - 2:30) | 5/6/2021 (PM) | 05/06/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/06/2021
Sales floor ceiling and above ceiling, and storefront framing... approved
|
||||
Progress Inspection | Passed w/ Conditions | 5/19/2021 (12:30 - 2:30) | 5/19/2021 (PM) | 05/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
05/19/2021
Ceiling framing and above ceiling in managers ffice and break room approved.
Note... empty electrical box in above ceiling over the back of house door to be covered with gypsum to maintain wall rating.
|
||||
Fire Inspection Final | Passed | 06/11/2021 | ||
Building Final Inspection | Partial Pass | 6/14/2021 (12:30 - 2:30) | 6/14/2021 (PM) | 06/14/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/14/2021
Approved for setup, stock and training. Clean space for final.
|
||||
Building Final Inspection | Passed | 6/16/2021 (10:00 - 12:00) | 6/16/2021 (AM) | 06/16/2021 |
Corrections:
Miscellaneous/Other
Comment Only
06/16/2021
Final for this permit approved approved.
|