PRBD202101233
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
12/27/2021
Final building inspection, phase 2. A. Open permits - 1. PRUT202106331 for visual storm sewer visual inspection. 2. PREL202105956 FOR 40 AMP PANEL, 15KVA, NEW LIGHTING AND OUTLETS.
|
||||
Building Final Inspection | Issue TCO | 11/2/2021 (12:30 - 2:30) | 11/2/2021 (PM) | 11/02/2021 |
Pending fire final, and electrical final, and add accessible emergency exit ramp off curb, north east exit. | ||||
Fire Inspection Final | Passed | 11/2/2021 (12:30 - 2:30) | 11/2/2021 (PM) | 12/08/2021 |
Footing Inspection | Passed | 01/14/2022 | ||
Footings completed. | ||||
Lath Inspection | Passed | 01/14/2022 | ||
Progress Inspection | Passed | 01/14/2022 | ||
Fire Inspection Final | Passed | 01/14/2022 | ||
Framing Inspection | Passed | 01/14/2022 | ||
Framing completed. | ||||
Footing Inspection | Passed | 5/20/2021 (12:30 - 2:30) | 5/20/2021 (PM) | 01/14/2022 |
Phase 3 storage building - A. Reinforced frost footings per plan. B. Braun on site for special inspections. Passed. Ongoing work. | ||||
Insulation Inspection | Passed | 01/14/2022 | ||
Progress Inspection | Passed | 8/23/2021 (2:30 - 3:30) | 8/23/2021 (PM) | 01/14/2022 |
Progress. Need special inspections for welding, bolting, of steel columns. | ||||
Progress Inspection | Passed | 7/12/2021 (8:00 - 10:00) | 7/12/2021 (AM) | 01/14/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/12/2021
core filling of block, this inspection is performed by special inspection. Records to be sent to city inspection for record retention.
|
||||
Progress Inspection | Passed | 6/21/2021 (12:30 - 2:30) | 6/21/2021 (PM) | 01/14/2022 |
Slab on grade concrete foundation with reinforcement rebars, on top of 2 inch rigid polystyrene. Location - south end. Passed. Ongoing work. | ||||
Progress Inspection | Passed | 6/16/2021 (2:30 - 3:30) | 6/16/2021 (PM) | 01/14/2022 |
Slab on grade with poly and sand base - ";peast side | ||||
Progress Inspection | Passed | 6/15/2021 (10:00 - 12:00) | 6/15/2021 (AM) | 01/14/2022 |
Prep for slab on grade concrete floor, with poly vapor barrier on new sand cushion. Passed. Ongoing work. | ||||
Building Final Inspection | Passed | 01/14/2022 | ||
Passed. A. Need copy of all special inspection reports final approved. Please email file to Bernadette Gillespie. B Gillespie@bloomingtonmn.gov | ||||
Corrections:
Miscellaneous/Other
Comment Only
01/14/2022
Please e mail all final inspections reports to B Gillespie @bloomingtonmn.gov
Thank you and nice working with you.
|