Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Framing Inspection | Partial Pass | 6/14/2021 (8:00 - 10:00) | 6/14/2021 (AM) | 06/14/2021 |
Framing - passed. A. Need above ceiling corrections. 1.North tenant separation wall requires gypsum patching holes, fire caulk penetrations around pipes, etc. B. Stuff roof deck flutes with mineral wool insulation. | ||||
Corrections:
Miscellaneous/Other
Outstanding
06/14/2021
Framing - passed. A. Patch all gypsum holes at north tenant one Hr rated gypsum separation to other tenants. B. Stuff open roof deck flutes using mineral wool, not fiberglass insulation, and call for re inspection before installing ceiling tiles.
C. Call for fire marshal rough in for sprinkler coverage rough in. Your fire marshal is Kris Kaiser.
|
||||
Progress Inspection | Passed w/ Conditions | 6/25/2021 (2:30 - 3:30) | 6/25/2021 (PM) | 06/25/2021 |
Above ceiling - penetrations in neighboring tenant walls - passed. Note - call for above ceiling inspections for fire sprinkler. Note - call for required plumbing rough in’s and environmental health inspections. Note - existing HVAC SYSTEM. A. NEW LOCATIONS FOR DIFFUSERS, with NEW INSULATED FLEX DUCT - PASSED. | ||||
Corrections:
Miscellaneous/Other
Outstanding
06/25/2021
Call for above ceiling trade inspections for fire sprinkler, AND electrical.
Above ceiling for HVAC DIFFUSERS - PASSED PER B.POST.
|
||||
Fire Inspection Final | Failed | 7/13/2021 (8:00 - 10:00) | 7/13/2021 (AM) | 07/13/2021 |
Corrections:
Miscellaneous/Other
Outstanding
07/13/2021
Remove plastic plant/foliage covering wall in the seating area or provide the information on the products flame spread and smoke index rating for further review.
|
||||
Building Final Inspection | Not Ready | 7/13/2021 (8:00 - 10:00) | 7/13/2021 (AM) | 07/13/2021 |
Need environmental health final, need fire marshal final to remove artificial grass due to flame spread rating. | ||||
Fire Inspection Final | Passed | 7/15/2021 (2:30 - 3:30) | 7/15/2021 (PM) | 07/15/2021 |
Corrections:
Miscellaneous/Other
Resolved
07/15/2021
Remove plastic plant/foliage covering wall in the seating area or provide the information on the products flame spread and smoke index rating for further review.
|
||||
Building Final Inspection | Issue TCO | 7/15/2021 (2:30 - 3:30) | 7/15/2021 (PM) | 07/15/2021 |
Existing restroom. A. New mirror installed. Bottom edge of mirror must be 40 inches off the finished floor. B. Move new paper towel dispenser installed to other side of wall and a max height above floor to bottom of dispenser to be 40 inches. C.TEMP OCCUPANCY PER ENVIRONMENTAL HEALTH FOR CORRECTIONS PER JESSICA JUTZ, JULY 22, 2021. | ||||
Framing Inspection | Passed | 07/27/2021 | ||
Corrections:
Miscellaneous/Other
Outstanding
06/14/2021
Framing - passed. A. Patch all gypsum holes at north tenant one Hr rated gypsum separation to other tenants. B. Stuff open roof deck flutes using mineral wool, not fiberglass insulation, and call for re inspection before installing ceiling tiles.
C. Call for fire marshal rough in for sprinkler coverage rough in. Your fire marshal is Kris Kaiser.
|
||||
Insulation Inspection | Passed | 07/27/2021 | ||
Not required. | ||||
Building Final Inspection | Passed w/ Conditions | 7/27/2021 (12:30 - 2:30) | 7/27/2021 (PM) | 07/27/2021 |
See corrections for environmental health. Building final inspection passed. | ||||
Corrections:
Miscellaneous/Other
Outstanding
07/27/2021
Complete environmental health final punch list.
Final Building inspection - passed.
|