Permit Application Status

PRBD202103967


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202103967
Building
Finaled
FINANCING PARTNERSHIP LP
Alteration/Repair/Replace
Not Required
The project is a renovation to an existing commercial distribution center for Best Buy - one story, 39,400 sq ft. The scope of work includes upgrade to the existing sprinkler system (ESFR sprinkler heads) and upgrade to new LED interior lighting. Architectural - upgrade existing toilets to ADA, finishes and plumbing fixtures. In addition, new offices and breakroom.
04/09/2021
07/02/2021
10/18/2022
04/21/2022

Locations

Permits

Permit Number: PRBD202103967

Building
Finaled
07/02/2021
10/18/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Issue TCO 10/15/2021 (8:00 - 10:00) 09/07/2021
Corrections:


Miscellaneous/Other
Carried Forward
09/07/2021
Missing sleeve protection for plumbing under sink counter for wheelchair protection. Missing vertical grab bars in ambulatory stall in women’s and missing vertical and horizontal grab bar in men’s ambulatory store. Missing rear grab bar in men’s handicap stall. Missing ADA signage outside of toilet rooms. 15 day temporary occupancy approved four security desk check in area. Obtain finals from electrical, plumbing and fire prior to calling for building final.

Building Final Inspection Passed 10/15/2021 (8:00 - 10:00) 10/15/2021 (AM) 10/15/2021
Corrections:


Miscellaneous/Other
Resolved
10/15/2021
Missing sleeve protection for plumbing under sink counter for wheelchair protection. Missing vertical grab bars in ambulatory stall in women’s and missing vertical and horizontal grab bar in men’s ambulatory store. Missing rear grab bar in men’s handicap stall. Missing ADA signage outside of toilet rooms. 15 day temporary occupancy approved four security desk check in area. Obtain finals from electrical, plumbing and fire prior to calling for building final.

Fire Inspection Final Passed 04/21/2022