PRBD202104058
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 7/13/2021 (12:30 - 2:30) | 7/13/2021 (PM) | 07/13/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/13/2021
Site visit, footings are not ready for inspection, rebar to be placed prior to inspection.
|
||||
Miscellaneous/Other
Comment Only
07/13/2021
Site visit, footings are not ready for inspection, rebar to be placed prior to inspection.
|
||||
Footing Inspection | Partial Pass | 7/14/2021 (10:00 - 12:00) | 7/14/2021 (AM) | 07/14/2021 |
Corrections:
Miscellaneous/Other
Comment Only
07/14/2021
Footings and rebar, grid G, lines 5 to 16… approved for concrete placement.
|
||||
Footing Inspection | Partial Pass | 08/17/2021 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/17/2021
3 piers on line 12, grids F.7,E, and E.4
Last small section of wall at dock area.
|
||||
Footing Inspection | Partial Pass | 8/19/2021 (7:00 - 8:00) | 8/19/2021 (AM) | 08/19/2021 |
Corrections:
Miscellaneous/Other
Comment Only
08/19/2021
Pad footing on line 7.1, grid F
Retaining wall footings off grid”A”, lines 2.7,3, and 6.3
Approved for concrete placement
|
||||
Progress Inspection | Partial Pass | 11/23/2021 (2:30 - 3:30) | 11/23/2021 (PM) | 11/23/2021 |
Vapor Barrier Inspection | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/23/2021
Under slab poly at remainder of mezzanine area… approved
|
||||
Progress Inspection | Partial Pass | 12/15/2021 (2:30 - 3:30) | 12/15/2021 (PM) | 12/15/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/15/2021
Under slab poly at south end of building complete to the west end of building… approved
|
||||
Framing Inspection | Partial Pass | 12/20/2021 (12:30 - 2:30) | 12/20/2021 (PM) | 12/20/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2021
Mezzanine level framing of walls. … Approved
South entry’s framing…approved
Under slab Poly at north east section of building… approved
|
||||
Progress Inspection | Partial Pass | 12/27/2021 (10:00 - 12:00) | 12/27/2021 (AM) | 12/27/2021 |
Corrections:
Miscellaneous/Other
Comment Only
12/27/2021
This section of under slab poly approved… ok to place concrete.
|
||||
Framing Inspection | Partial Pass | 1/3/2022 (10:00 - 12:00) | 1/3/2022 (AM) | 01/03/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/03/2022
Hard lid / soffit framing on mezzanine level… approved
|
||||
Framing Inspection | Partial Pass | 1/11/2022 (12:30 - 2:30) | 1/11/2022 (PM) | 01/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/11/2022
1st floor framing at mezzanine… approved
|
||||
Framing Inspection | Partial Pass | 1/31/2022 (8:00 - 10:00) | 1/31/2022 (AM) | 01/31/2022 |
Corrections:
Miscellaneous/Other
Comment Only
01/31/2022
Framing of rooms in area E…. Approved
|
||||
Framing Inspection | Partial Pass | 2/11/2022 (8:00 - 10:00) | 2/11/2022 (AM) | 02/11/2022 |
Corrections:
Miscellaneous/Other
Comment Only
02/11/2022
Framing at south entry and bathrooms… approved.
Trades and sprinkler inspections needed prior to covering ceiling.
|
||||
Above Ceiling Inspection | Passed | 03/02/2022 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/02/2022
Above ceiling and ceiling framing at mezzanine areas… approved.
Leave open some tiles for sprinkler inspection.
|
||||
Progress Inspection | Partial Pass | 3/11/2022 (8:00 - 10:00) | 3/11/2022 (AM) | 03/11/2022 |
Above Ceiling Inspection | ||||
Corrections:
Miscellaneous/Other
Comment Only
03/11/2022
First level above ceiling and ceiling framing… approved, pending the correction o the exposed non plenum rated insulation in the lab rooms being covered or switched out with approved plenum rated materials.
|
||||
Progress Inspection | Partial Pass | 5/16/2022 (8:00 - 10:00) | 5/16/2022 (AM) | 05/16/2022 |
Corrections:
Miscellaneous/Other
Comment Only
05/16/2022
Went through building and checked accessibility too bathrooms mothers room, and kitchens… approved
Note… cane rail to still be installed at east stair.
Exiting appears compliant.
Note… when shelving is installed, exiting to be reevaluated.
|
||||
Building Final Inspection | Partial Pass | 5/27/2022 (8:00 - 10:00) | 5/27/2022 (AM) | 05/27/2022 |
Corrections:
Miscellaneous/Other
Carried Forward
07/15/2022
Additional exiting signage to be installed for final of this permit by final inspection.
Parking lot to be completed with 2nd lift of asphalt and striping.
Landscaping to be completed for final.
|
||||
Miscellaneous/Other
Comment Only
05/27/2022
Approved for TCO (temporary occupancy). See outstanding comments for final inspection requirements.
|
||||
Fire Inspection Final | Partial Pass | 5/27/2022 (8:00 - 10:00) | 5/27/2022 (AM) | 06/02/2022 |
Lighting Inspection | Passed | 07/09/2022 | ||
SICK lighting | ||||
Building Final Inspection | Partial Pass | 7/15/2022 (8:00 - 10:00) | 7/15/2022 (AM) | 07/15/2022 |
Corrections:
Miscellaneous/Other
Comment Only
07/15/2022
Building is compliant to code and will remain on temp co. Items pending to complete final…
1) landscape inspection to be performed by city
2) electronic asbuilts to be sent to city engineering dept.
3) fire final to be completed and sprinkler heads to be installed in the sound proof stand alone cube rooms.
|
||||
Fire Inspection Final | Partial Pass | 7/15/2022 (8:00 - 10:00) | 7/15/2022 (AM) | 07/20/2022 |
Landscaping Inspection | Passed | 8/29/2022 | 08/24/2022 | |
Building Final Inspection | Issue CO | 8/25/2022 (10:00 - 12:00) | 8/25/2022 (AM) | 08/25/2022 |
Corrections:
Miscellaneous/Other
Resolved
08/25/2022
Additional exiting signage to be installed for final of this permit by final inspection.
Parking lot to be completed with 2nd lift of asphalt and striping.
Landscaping to be completed for final.
|
||||
Miscellaneous/Other
Comment Only
08/25/2022
All outstanding items are resolved.
The 3 sound proof pods have been removed and this eliminates the fire inspection requirement for sprinkler coverage to those pods.
Final for this building and permit is approved, pending fire inspection final approval.
|
||||
Fire Inspection Final | Passed | 8/25/2022 (10:00 - 12:00) | 8/25/2022 (AM) | 08/29/2022 |