PRBD202104233
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Pending | |||
Above Ceiling Inspection | Pending | |||
Insulation Inspection | Pending | |||
Lath Inspection | Pending | |||
Gypsum Board/Sheet Rock Inspection | Pending | |||
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Footing Inspection | Pending | |||
Footing Inspection | Pending | 10/28/2021 (10:00 - 12:00) | ||
Chuck from concrete company canceled inspection for 10/28. KB | ||||
Progress Inspection | Partial Pass | 9/24/2021 (10:00 - 12:00) | 9/24/2021 (AM) | 09/24/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/24/2021
1st lift of waterproofing around the poured walls… approved
|
||||
Footing Inspection | Partial Pass | 9/29/2021 (8:00 - 10:00) | 9/29/2021 (AM) | 09/29/2021 |
Passed, ongoing work. Braun is special inspector. | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/29/2021
Footing - reinforced concrete floor pour, with all wall steel incorporated in the floor pour. Braun is special inspector.
|
||||
Progress Inspection | Partial Pass | 9/30/2021 (10:00 - 12:00) | 9/30/2021 (AM) | 09/30/2021 |
Corrections:
Miscellaneous/Other
Comment Only
09/30/2021
Pit slab waterproofing… approved
|
||||
Footing Inspection | Passed | 10/12/2021 (12:30 - 2:30) | 10/12/2021 (PM) | 10/12/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/12/2021
Remaining strip footing with rebar along south wall approved. Waterproofing on interior poured wall approved.
|
||||
Progress Inspection | Not Ready | 10/15/2021 (8:00 - 10:00) | 10/15/2021 (AM) | 10/15/2021 |
Footing Inspection | Passed | 10/26/2021 (10:00 - 12:00) | 10/26/2021 (AM) | 10/26/2021 |
Corrections:
Miscellaneous/Other
Comment Only
10/26/2021
To stoop footings with rebar on south side approved.
|
||||
Landscaping Inspection | VOID | 9/29/2023 | 09/20/2023 |