PRBD202105271
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 6/29/2021 (12:30 - 2:30) | 6/29/2021 (PM) | 06/29/2021 |
Building Final Inspection | Issue TCO | 8/6/2021 (10:00 - 12:00) | 8/6/2021 (AM) | 08/10/2021 |
Corrections:
Miscellaneous/Other
Carried Forward
08/10/2021
Need final electrical approval. 30 day temporary C.O. approved.
|
||||
Fire Inspection Final | Passed | 8/6/2021 (10:00 - 12:00) | 8/6/2021 (AM) | 08/16/2021 |
Building Final Inspection | Passed | 9/24/2021 (10:00 - 12:00) | 9/24/2021 (AM) | 09/24/2021 |
Corrections:
Miscellaneous/Other
Resolved
09/24/2021
Need final electrical approval. 30 day temporary C.O. approved.
|
||||
Miscellaneous/Other
Comment Only
09/24/2021
Note…. To be compliant with accessibility, the microwave needs to be installed at counter height. The upper microwave in wall mount upper cabinets is ok to keep in location it’s in. Relocate or install microwave if need arises to be compliant to Mn. Accessibility code.
Final for this permit approved.
|