Permit Application Status

PRBD202106128


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202106128
Building
Finaled
BCS3 HOUSING LLC
Alteration/Repair/Replace
Not Required
Tenant Improvement Project within existing shell retail space. Construction of coffee shop/restaurant within the shell retail space at BCS3/The Fenley Apartment Building. Construction includes: plumbing, electrical, HVAC, Kitchen Equipment, Framing/Drywall & Paint and other flooring and wall finished in the approx 2,300 sf retail space.
05/21/2021
06/29/2021
05/28/2022
11/29/2021

Locations

Permits

Permit Number: PRBD202106128

Building
Finaled
06/29/2021
05/28/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 7/20/2021 (10:00 - 12:00) 7/20/2021 (AM) 07/20/2021
Corrections:


Miscellaneous/Other
Comment Only
07/20/2021
Framing of walls, and entry ceiling… approved

Fire Inspection Final Not Ready 9/28/2021 (10:00 - 12:00) 9/28/2021 (AM) 09/28/2021
Building Final Inspection Not Ready 9/28/2021 (10:00 - 12:00) 9/28/2021 (AM) 09/28/2021
Corrections:


Miscellaneous/Other
Comment Only
09/28/2021
Mechanical and fire finals to be approved, along with environmental health approval. Not ready for final at this time.

Fire Inspection Final Passed 9/29/2021 (AM) 09/29/2021
Building Final Inspection Not Ready 10/5/2021 (8:00 - 10:00) 10/5/2021 (AM) 10/05/2021
Corrections:


Miscellaneous/Other
Comment Only
10/05/2021
Unable to approve a final yet, trades finals needed and Environmental Health to follow up with their requirements. Occupancy signage has been installed. Please call in for finals of all permits.

Temporary Certificate of Occupancy Inspection Passed 10/05/2021
Corrections:


Miscellaneous/Other
Comment Only
10/05/2021
Approval has been given by trades inspectors for their scope of work with the open permits, environmental health also has given approval for temp CO. Temp CO is approved at this time to stock, train, bring in food, and for soft opening. Final inspections to follow once all equipment has arrived and is installed and trades inspections and permits have been final.

Building Final Inspection Issue CO 11/29/2021
Corrections:


Miscellaneous/Other
Comment Only
11/29/2021
Approved for building final and full C.O. This permit and scope of work approved for final.