Summary

PRBD202106294
Building
Finaled
GKII NORTHLAND CENTER LLC
Alteration/Repair/Replace
Not Required
Tenant improvement project of existing office space.
05/25/2021
06/14/2021
07/24/2022
01/25/2022

Locations

Permits

Permit Number: PRBD202106294

Building
Finaled
06/14/2021
07/24/2022

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Rated Assemblies Inspection Passed 08/13/2021
Fire caulk penetrations. A. 1 inch hole in 2 hr rated floor. B. Above ceiling - fire caulk penetrations at elevator /elevator lobby.
Framing Inspection Passed 8/13/2021 (12:30 - 2:30) 8/13/2021 (PM) 08/13/2021
Building Final Inspection Passed w/ Conditions 11/15/2021 (8:00 - 10:00) 11/15/2021 (AM) 11/15/2021
See corrections.
Corrections:


Miscellaneous/Other
Outstanding
11/15/2021
A. Need fire marshal final. B. North west suite area, the very north exit sign does not illuminate properly. Older red exit sign. C. All other OK.

Fire Inspection Final Partial Pass 11/15/2021 (8:00 - 10:00) 11/15/2021 (AM) 11/15/2021
Fire Inspection Final Passed 01/25/2022