PRBD202106359
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 7/26/2021 (12:30 - 2:30) | 7/26/2021 (PM) | 07/26/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/26/2021
Wall framing approved pending corrections of adding supports at the over- notched studs and unfastens top plates from ducting.
|
||||
| Framing Inspection | Passed w/ Conditions | 8/2/2021 (12:30 - 2:30) | 8/2/2021 (PM) | 08/02/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/02/2021
Bathroom and kitchen walls framing approved, pending picture of fire stop at kitchen wall for plumbing piping.
|
||||
| Progress Inspection | Passed | 9/15/2021 (10:00 - 12:00) | 9/15/2021 (AM) | 09/15/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/15/2021
2nd floor above ceiling and suspended ceiling installation… approved.
Verbal to contractor to cover exposed insulation.
|
||||
| Building Final Inspection | Passed | 10/20/2021 (12:30 - 2:30) | 10/20/2021 (PM) | 10/20/2021 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/20/2021
Accessibility, EM lighting, and exiting checked and compliant. Final for this permit approved, pending fire marshal final.
|
||||
| Fire Inspection Final | Passed | 10/20/2021 (12:30 - 2:30) | 10/20/2021 (PM) | 10/20/2021 |